E.Spire Communications, Inc. v. Morris Plumbing & Electric Co. (In Re E.Spire Communications, Inc.)

293 B.R. 639, 2003 Bankr. LEXIS 743, 2003 WL 21101406
CourtUnited States Bankruptcy Court, D. Delaware
DecidedMay 9, 2003
Docket09-11045
StatusPublished
Cited by3 cases

This text of 293 B.R. 639 (E.Spire Communications, Inc. v. Morris Plumbing & Electric Co. (In Re E.Spire Communications, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.Spire Communications, Inc. v. Morris Plumbing & Electric Co. (In Re E.Spire Communications, Inc.), 293 B.R. 639, 2003 Bankr. LEXIS 743, 2003 WL 21101406 (Del. 2003).

Opinion

MEMORANDUM OPINION 1

JERRY W. VENTERS, Bankruptcy Judge.

Before the Court is the Complaint of e.Spire Communications, Inc., et al. (“Debtors”) against Morris Plumbing & Electric Co., Inc. (“Morris”). The matter was set for trial and heard by the Court on Tuesday March 4, 2003. 2

I. BACKGROUND

A. Procedural History

The Debtors have undertaken extensive litigation in order to sort out purported mechanic’s liens asserted against the proceeds from the sale of the Debtors’ assets. There were two separate actions that involved the Defendant Morris.

Action 1 was filed by Debtors on January 14, 2002. In that action, the Debtors are seeking (a) a declaratory judgment to determine the extent, validity and priority of Morris’ claims against the Debtors, including but not limited to, a judgment against Morris that it does not have a valid perfected security interest in any assets of the Debtors; (b) payment of amounts due to the Debtors by Morris; (c) damages based on alleged fraud by Morris; (d) disallowance of proofs of claim filed by the defendant; and (e) damages for breach of contract [Doc. No. 1 (02-1418) ].

Action 2 was filed on July 10, 2002, against some 50 defendants who hold purported mechanics’ lien claims against various properties of the Debtors. The Debtors subsequently filed an amended complaint against all defendants. The Debtors are seeking essentially the same relief as in Action 1, excluding a claim for fraud, against multiple defendants, including Morris [Doc. No. 5 (02-4692) ].

Morris filed answers and counterclaims in both actions alleging (a) breach of contract; (b) fraud; (c) quantum meruit; (d) unjust enrichment; and (e) attorney’s fees. The Debtors subsequently moved to dis *642 miss the Morris counterclaims. By Memorandum Order [Doc. No. 18] dated November 14, 2002, the Court consolidated all issues in Action 2 [02-4692] pertaining to Morris into the present proceeding, Action 1 [02-1418]. On November 20, 2002, the Court issued a Memorandum Order denying the Debtors’ motion to dismiss the counterclaims [Doc. No. 23]. The Court entered a Scheduling Order on December 23, 2002 [Doc. No. 29], whereby a trial was set for March 4, 2003.

Throughout the course of the litigation the parties have had numerous problems regarding discovery and discovery related issues. In fact, on the eve of trial it was brought to the Court’s attention that a possible key witness, Roger Tate (a former employee of the Debtors), was unavailable because he had disappeared. For this reason, the Court Ordered that all other evidence would be heard on the trial date and Morris would be allowed until March 20 to locate Tate and depose him. Roger Tate was not found and deposed, therefore the evidence submitted at trial was the complete record. The parties submitted post-trial briefs in support of various legal contentions on which the parties relied, in particular those relating to the validity of the Morris lien.

Due to the procedural history of this action, the Court has before it an amalgam of pleadings as follows: (1) Complaint in Action 1; (2) Answer in Action 1; (3) Complaint in Action 2; and, (4) Answer and Counterclaim in Action 2. Since this is confusing at best, the Court has decided it will adjudicate the issues raised at trial for which evidence was submitted without binding itself to the structure of the pleadings. These issues are as follows: (1) the settlement reached between the parties; (2) restoration and warranty costs the Debtors allege they are owed from Morris; (3) the validity and extent of Morris’ purported mechanic’s lien; (4) the fraud claim asserted by the Debtors; and (5) the allowance or disallowance of Morris’ Proofs of Claim.

B. Facts

Morris was a general contractor that entered into a Master Work Agreement with the Debtors to build the infrastructure for a fiber optic network around Atlanta, Georgia. Morris was responsible for directional boring, or digging trenches for the network to be placed underground. The Debtors eventually fell behind in payments and ultimately had many outstanding purchase orders unpaid. There has been a dispute over whether the parties entered into a settlement on November 27, 2001, whereby the Debtors agreed to pay $2,167,366.05 to Morris as a “true-up” of all then-outstanding purchase orders. The settlement was allegedly evidenced by an e-mail from Mike Miller of the Debtors to D.L. Morris, Jr. (“Buddy Morris”) of Morris Plumbing. In return, Morris agreed that it would continue to work on the network. However, the Debtors did not make the settlement payments as quickly as Buddy Morris wanted and on December 11, 2001, Morris filed a mechanic’s lien in the amount of $3.4 million in Fulton County, Georgia [Debtors Ex. 6].

II. DISCUSSION

A. Morris’ Mechanic’s Lien

The purported mechanic’s lien must be analyzed under Georgia state law since the fifing was in Fulton County, Georgia, and the work was performed in the State of Georgia. First, § 44-14-361 of the Georgia Code provides a fist of persons that “shall each have a special lien on the ... property for which they furnish labor, services, or materials .... ” Ga.Code Ann. § 44-14-361(a).

*643 Section 44-14-361.1 outlines the requirements to “make good the liens specified in paragraphs (1) through (8) of subsection (а) of Code Section 44-14-361.” Ga.Code Ann. § 44-14-361.1(a). Subsection (a) further provides:

[The liens] must be created and declared in accordance with the following provisions, and on failure of any of them the lien shall not be effective or enforceable:
(1) A substantial compliance by the party claiming the hen with his contract for building, repairing, or improving ...
(2) The filing for record of his claim of lien within three months after the completion of work ... in the office of the clerk of the superior court of the county where the property is located, which claim shall be in substance as follows:
“A.B., ... contractor ... or other person (as the case may be) claims a hen in the amount of (specify the amount claimed) on the [property] and the premises or real estate on which it is erected or built, of C.D. (describing the houses, premises, real estate, or railroad), for satisfaction of a claim which became due on (specify the date the claim was due) for building, repairing, improving, or furnishing material (or whatever the claim may be).”
At the time of filing for record of his claim of hen, the hen claimant shah send a copy of the claim of hen by registered or certified mail or statutory overnight delivery to the owner of the property or the contractor, as the agent of the owner....

Ga.Code Ann § 44-14-361.1(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Richard Miller V.
Sixth Circuit, 2011
State Bank v. Miller (In Re Miller)
459 B.R. 657 (Sixth Circuit, 2011)
Chen v. Mayflower Transit, Inc.
315 F. Supp. 2d 886 (N.D. Illinois, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
293 B.R. 639, 2003 Bankr. LEXIS 743, 2003 WL 21101406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/espire-communications-inc-v-morris-plumbing-electric-co-in-re-deb-2003.