Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings

Court of Appeals of Iowa·Decided August 5, 2020·No. 19-0508·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 19-0508

Filed August 5, 2020

ERIC ZIEL and CAROL ZIEL, Plaintiffs-Appellants,

vs.

ENGERY PANEL STRUCTURES, INC. d/b/a EPS BUILDINGS, Defendant-Appellee.

Appeal from the Iowa District Court for Boone County, Steven J. Oeth, Judge.

Plaintiffs appeal from the district court’s grant of summary judgment in favor of the defendant, a manufacturer-designer of a building on their land that collapsed during a windstorm. AFFIRMED.

Sean M. O'Brien of Bradshaw, Fowler, Proctor & Fairgrave, P.C., Des Moines, for appellant.

Brian P. Rickert and Thomas D. Story of Brown, Winick, Graves, Gross, Baskerville & Schoenebaum, P.L.C., Des Moines, for appellee.

Heard by Bower, C.J., and Doyle and Schumacher, JJ. Greer, J., takes no part.

SCHUMACHER, Judge.

Boone County landowners, husband and wife, sought to construct a large building for commercial and agricultural purposes. With the help of a construction contractor, the landowners selected a “pre-engineered” building made of structural insulated panels (SIPs). Having some building experience, the landowners assisted in construction by grading the site and hiring third parties to complete concrete and electrical work. As the construction contractor was nearing completion of the structure, the landowners arranged separately with a Des Moines company to install overhead doors, which had been excluded from the contract with the construction contractor and for which there were no specifications in the detailed drawings provided by the SIP manufacturer.

Approximately eleven months after completion, the largest of the building’s overhead doors failed during a windstorm, precipitating the building’s collapse. The wind speeds during the event measured less than the wind rating noted in the manufacturer’s drawings but greater than the rating for the overhead door. The landowner brought suit in contract and tort against the manufacturer, the construction contractor, and the overhead door company. The landowners’ claims against the manufacturer alleged that the manufacturer failed to warn of the need for all overhead doors to be wind-rated to ninety miles per hour and that the manufacturer was negligent in the design of the structure. This appeal arises from the district court’s grant of summary judgment on both claims in favor of the manufacturer, which the court based on three findings: (1) the manufacturer owed no legal duty to the landowners, (2) the landowners’ tort claims against the manufacturer were barred by the economic loss doctrine, and (3) a liability-limiting

provision in the warranty signed by the parties precluded the landowners’ tort claims. We affirm the district court’s determination that the manufacturer owed the plaintiffs no legal duty, and we find the economic loss doctrine applicable on these facts. We conclude the warranty was not an affirmative defense that the manufacturer needed to raise in the pleadings stage, and we find that the warranty would not have failed its essential purpose. We find to be unpreserved the landowners’ argument that the manufacturer repudiated the warranty. We further find the warranty was not unconscionable. We affirm the district court’s grant of summary judgment. Background Facts and Proceedings Eric and Carol Ziel (the Ziels) sought to erect a building on their land located near the grounds of the Farm Progress Show in Boone, Iowa. They selected a building sold by Energy Panel Structures, Inc. (EPS). EPS is a manufacturer of SIPs. EPS works through a network of third-party construction contractors that market, sell, and construct EPS buildings. EPS provides engineering expertise and drafts plans for the pre-engineered buildings that are then used by the contractor in the construction of the buildings.

The Ziels contracted with Lasco Construction Services, Inc. (Lasco) for the construction of the building. Lasco is an EPS dealer and served as the intermediary between EPS and the Ziels. The Ziels selected a building measuring 80 feet by 192 feet and provided input on where the cutouts for windows, entry doors, and large overhead doors would be. EPS played no part in the installation of the windows and doors. The Ziels and Lasco entered into a contract, and Lasco submitted a simple sketch of the building for EPS to review. EPS provided a pricing

sheet and detailed drawings to Lasco. The drawings were drafted and reviewed by two professional engineers at EPS.

EPS designed the building to withstand winds of up to ninety miles per hour and noted this information on the drawings. Under the “design loads” section of the drawings it was specified that the “wind load” was “90 mph.” The drawings included rough openings for doors and windows in accordance with the Ziels’ desired dimensions and locations, however the drawings did not provide further technical specifications for the doors or windows.

The drawings were completed in early June 2012. EPS forwarded the drawings and sent a price sheet to Lasco. Lasco soon thereafter began constructing the building, as the Ziels hoped to have the building ready for use during the annual Farm Progress Show at the end of summer, which occurs on neighboring land. Eric Ziel (Ziel) did grading work at the site and hired contractors to pour the concrete slab and complete electrical work.

On July 25, 2012, the building collapsed during a wind event while it was still under construction. The cause of this collapse was deemed to be insufficient temporary bracing. Ziel and Lasco subsequently entered into a new contract for a replacement building. Construction on a second building was undertaken.

Ziel contracted with Overhead Door Company of Des Moines, Inc.

(Overhead) to supply overhead doors for the project, including a large overhead door measuring sixteen feet by twenty-eight feet that was to be placed in the center of the building’s west face. Ziel selected the doors without input from Lasco or EPS, and Overhead installed the doors when the building was nearing completion.

The large western overhead door selected by Ziel was rated for winds as high as sixty-five miles per hour.

After Lasco completed the building, Lasco presented the Ziels with an EPS warranty. Lasco’s president, EPS’s president, and Ziel all signed the warranty. EPS warranted the building would be engineered “to meet the wind and snow loads specified for the Building.” The warranty purported to limit EPS’s obligations to repair or replacement: “EPS’s obligations with regard to a valid claim under this warranty are limited to the repair or replacement (as determined by EPS) of the defective part or product and shall not include any cost to remove, install, reinstall, or ship the defective or replacement part or product.” Additionally, the document purported to limit the Ziels’ remedies to just those enumerated, and it disclaimed liability under a number of different theories:

4. THE WARRANTIES LISTED ABOVE THAT ARE PROVIDED DIRECTLY BY EPS CONSTITUTE THE SOLE AND EXCLUSIVE WARRANTIES FROM EPS TO OWNER AND THE REMEDIES FOR BREACH THEREOF ARE THE ONLY REMEDIES AVAILABLE UNDER SUCH WARRANTIES. EPS MAKES NO OTHER EXPRESS OR IMPLIED WARRANTIES AS TO THE PACKAGE OR THE BUILDING, INCLUDING WITHOUT LIMITATION ANY WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE, AND NO PERSON, INCLUDING EMPLOYEES, REPRESENTATIVES OR AGENTS OF EPS, IS AUTHORIZED TO MAKE ANY REPRESENTATIONS OR WARRANTIES CONCERNING THE PACKAGE OR THE BUILDING ON BEHALF OF EPS. ALL OTHER WARRANTIES ARISING UNDER LAW ARE EXPRESSLY DISCLAIMED.

5. IN NO EVENT SHALL EPS BE LIABLE UNDER ANY THEORY OF RECOVERY, WHETHER BASED ON ANY THEORY OF NEGLIGENCE, STRICT LIABILITY, CONTRACT OR TORT, FOR ANY DIRECT, INDIRECT, SPECIAL, PUNITIVE, INCIDENTAL OR CONSEQUENTIAL DAMAGES OF ANY KIND OR NATURE WHICH IN ANY WAY ARISE OUT OF THE PURCHASE OF THE PACKAGE OR ANY USE OF THE BUILDING.

Free access — add to your briefcase to read the full text and ask questions with AI

Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings, (iowactapp 2020).

Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings (Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Saratoga Fishing Co. v. J. M. Martinac & Co.
520 U.S. 875 (Supreme Court, 1997)
Richards v. Midland Brick Sales Co.
551 N.W.2d 649 (Court of Appeals of Iowa, 1996)
Van Sickle Construction Co. v. Wachovia Commercial Mortgage, Inc.
783 N.W.2d 684 (Supreme Court of Iowa, 2010)
Bill Grunder's Sons Construction, Inc. v. Ganzer
686 N.W.2d 193 (Supreme Court of Iowa, 2004)
Burton v. Des Moines Metropolitan Transit Authority
530 N.W.2d 696 (Supreme Court of Iowa, 1995)
Erickson v. Wright Welding Supply, Inc.
485 N.W.2d 82 (Supreme Court of Iowa, 1992)
Sears, Roebuck and Company v. Poling
81 N.W.2d 462 (Supreme Court of Iowa, 1957)
DeVoss v. State
648 N.W.2d 56 (Supreme Court of Iowa, 2002)
Sankey v. Richenberger
456 N.W.2d 206 (Supreme Court of Iowa, 1990)
Meier v. SENECAUT III
641 N.W.2d 532 (Supreme Court of Iowa, 2002)
Olson v. Prosoco, Inc.
522 N.W.2d 284 (Supreme Court of Iowa, 1994)
Lovick v. Wil-Rich
588 N.W.2d 688 (Supreme Court of Iowa, 1999)
American Fire & Casualty Co. v. Ford Motor Co.
588 N.W.2d 437 (Supreme Court of Iowa, 1999)
Leonard v. State
491 N.W.2d 508 (Supreme Court of Iowa, 1992)
Lloyd F. Smith Co. v. Den-Tal-Ez, Inc.
491 N.W.2d 11 (Supreme Court of Minnesota, 1992)
Larsen v. United Federal Savings & Loan Ass'n of Des Moines
300 N.W.2d 281 (Supreme Court of Iowa, 1981)
Nebraska Innkeepers, Inc. v. Pittsburgh-Des Moines Corp.
345 N.W.2d 124 (Supreme Court of Iowa, 1984)
Determan v. Johnson
613 N.W.2d 259 (Supreme Court of Iowa, 2000)
Badgett Construction & Development Co. v. Kan-Build, Inc.
102 F. Supp. 2d 1098 (S.D. Iowa, 2000)