Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings

CourtCourt of Appeals of Iowa
DecidedAugust 5, 2020
Docket19-0508
StatusPublished

This text of Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings (Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings, (iowactapp 2020).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 19-0508 Filed August 5, 2020

ERIC ZIEL and CAROL ZIEL, Plaintiffs-Appellants,

vs.

ENGERY PANEL STRUCTURES, INC. d/b/a EPS BUILDINGS, Defendant-Appellee. ________________________________________________________________

Appeal from the Iowa District Court for Boone County, Steven J. Oeth,

Judge.

Plaintiffs appeal from the district court’s grant of summary judgment in favor

of the defendant, a manufacturer-designer of a building on their land that collapsed

during a windstorm. AFFIRMED.

Sean M. O'Brien of Bradshaw, Fowler, Proctor & Fairgrave, P.C., Des

Moines, for appellant.

Brian P. Rickert and Thomas D. Story of Brown, Winick, Graves, Gross,

Baskerville & Schoenebaum, P.L.C., Des Moines, for appellee.

Heard by Bower, C.J., and Doyle and Schumacher, JJ. Greer, J., takes no

part. 2

SCHUMACHER, Judge.

Boone County landowners, husband and wife, sought to construct a large

building for commercial and agricultural purposes. With the help of a construction

contractor, the landowners selected a “pre-engineered” building made of structural

insulated panels (SIPs). Having some building experience, the landowners

assisted in construction by grading the site and hiring third parties to complete

concrete and electrical work. As the construction contractor was nearing

completion of the structure, the landowners arranged separately with a Des Moines

company to install overhead doors, which had been excluded from the contract

with the construction contractor and for which there were no specifications in the

detailed drawings provided by the SIP manufacturer.

Approximately eleven months after completion, the largest of the building’s

overhead doors failed during a windstorm, precipitating the building’s collapse.

The wind speeds during the event measured less than the wind rating noted in the

manufacturer’s drawings but greater than the rating for the overhead door. The

landowner brought suit in contract and tort against the manufacturer, the

construction contractor, and the overhead door company. The landowners’ claims

against the manufacturer alleged that the manufacturer failed to warn of the need

for all overhead doors to be wind-rated to ninety miles per hour and that the

manufacturer was negligent in the design of the structure. This appeal arises from

the district court’s grant of summary judgment on both claims in favor of the

manufacturer, which the court based on three findings: (1) the manufacturer owed

no legal duty to the landowners, (2) the landowners’ tort claims against the

manufacturer were barred by the economic loss doctrine, and (3) a liability-limiting 3

provision in the warranty signed by the parties precluded the landowners’ tort

claims. We affirm the district court’s determination that the manufacturer owed the

plaintiffs no legal duty, and we find the economic loss doctrine applicable on these

facts. We conclude the warranty was not an affirmative defense that the

manufacturer needed to raise in the pleadings stage, and we find that the warranty

would not have failed its essential purpose. We find to be unpreserved the

landowners’ argument that the manufacturer repudiated the warranty. We further

find the warranty was not unconscionable. We affirm the district court’s grant of

summary judgment.

Background Facts and Proceedings

Eric and Carol Ziel (the Ziels) sought to erect a building on their land located

near the grounds of the Farm Progress Show in Boone, Iowa. They selected a

building sold by Energy Panel Structures, Inc. (EPS). EPS is a manufacturer of

SIPs. EPS works through a network of third-party construction contractors that

market, sell, and construct EPS buildings. EPS provides engineering expertise

and drafts plans for the pre-engineered buildings that are then used by the

contractor in the construction of the buildings.

The Ziels contracted with Lasco Construction Services, Inc. (Lasco) for the

construction of the building. Lasco is an EPS dealer and served as the

intermediary between EPS and the Ziels. The Ziels selected a building measuring

80 feet by 192 feet and provided input on where the cutouts for windows, entry

doors, and large overhead doors would be. EPS played no part in the installation

of the windows and doors. The Ziels and Lasco entered into a contract, and Lasco

submitted a simple sketch of the building for EPS to review. EPS provided a pricing 4

sheet and detailed drawings to Lasco. The drawings were drafted and reviewed

by two professional engineers at EPS.

EPS designed the building to withstand winds of up to ninety miles per hour

and noted this information on the drawings. Under the “design loads” section of

the drawings it was specified that the “wind load” was “90 mph.” The drawings

included rough openings for doors and windows in accordance with the Ziels’

desired dimensions and locations, however the drawings did not provide further

technical specifications for the doors or windows.

The drawings were completed in early June 2012. EPS forwarded the

drawings and sent a price sheet to Lasco. Lasco soon thereafter began

constructing the building, as the Ziels hoped to have the building ready for use

during the annual Farm Progress Show at the end of summer, which occurs on

neighboring land. Eric Ziel (Ziel) did grading work at the site and hired contractors

to pour the concrete slab and complete electrical work.

On July 25, 2012, the building collapsed during a wind event while it was

still under construction. The cause of this collapse was deemed to be insufficient

temporary bracing. Ziel and Lasco subsequently entered into a new contract for a

replacement building. Construction on a second building was undertaken.

Ziel contracted with Overhead Door Company of Des Moines, Inc.

(Overhead) to supply overhead doors for the project, including a large overhead

door measuring sixteen feet by twenty-eight feet that was to be placed in the center

of the building’s west face. Ziel selected the doors without input from Lasco or

EPS, and Overhead installed the doors when the building was nearing completion. 5

The large western overhead door selected by Ziel was rated for winds as high as

sixty-five miles per hour.

After Lasco completed the building, Lasco presented the Ziels with an EPS

warranty. Lasco’s president, EPS’s president, and Ziel all signed the warranty.

EPS warranted the building would be engineered “to meet the wind and snow loads

specified for the Building.” The warranty purported to limit EPS’s obligations to

repair or replacement: “EPS’s obligations with regard to a valid claim under this

warranty are limited to the repair or replacement (as determined by EPS) of the

defective part or product and shall not include any cost to remove, install, reinstall,

or ship the defective or replacement part or product.” Additionally, the document

purported to limit the Ziels’ remedies to just those enumerated, and it disclaimed

liability under a number of different theories:

4. THE WARRANTIES LISTED ABOVE THAT ARE PROVIDED DIRECTLY BY EPS CONSTITUTE THE SOLE AND EXCLUSIVE WARRANTIES FROM EPS TO OWNER AND THE REMEDIES FOR BREACH THEREOF ARE THE ONLY REMEDIES AVAILABLE UNDER SUCH WARRANTIES.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Saratoga Fishing Co. v. J. M. Martinac & Co.
520 U.S. 875 (Supreme Court, 1997)
Richards v. Midland Brick Sales Co.
551 N.W.2d 649 (Court of Appeals of Iowa, 1996)
Van Sickle Construction Co. v. Wachovia Commercial Mortgage, Inc.
783 N.W.2d 684 (Supreme Court of Iowa, 2010)
Bill Grunder's Sons Construction, Inc. v. Ganzer
686 N.W.2d 193 (Supreme Court of Iowa, 2004)
Burton v. Des Moines Metropolitan Transit Authority
530 N.W.2d 696 (Supreme Court of Iowa, 1995)
Erickson v. Wright Welding Supply, Inc.
485 N.W.2d 82 (Supreme Court of Iowa, 1992)
Sears, Roebuck and Company v. Poling
81 N.W.2d 462 (Supreme Court of Iowa, 1957)
DeVoss v. State
648 N.W.2d 56 (Supreme Court of Iowa, 2002)
Sankey v. Richenberger
456 N.W.2d 206 (Supreme Court of Iowa, 1990)
Meier v. SENECAUT III
641 N.W.2d 532 (Supreme Court of Iowa, 2002)
Olson v. Prosoco, Inc.
522 N.W.2d 284 (Supreme Court of Iowa, 1994)
Lovick v. Wil-Rich
588 N.W.2d 688 (Supreme Court of Iowa, 1999)
American Fire & Casualty Co. v. Ford Motor Co.
588 N.W.2d 437 (Supreme Court of Iowa, 1999)
Leonard v. State
491 N.W.2d 508 (Supreme Court of Iowa, 1992)
Lloyd F. Smith Co. v. Den-Tal-Ez, Inc.
491 N.W.2d 11 (Supreme Court of Minnesota, 1992)
Larsen v. United Federal Savings & Loan Ass'n of Des Moines
300 N.W.2d 281 (Supreme Court of Iowa, 1981)
Nebraska Innkeepers, Inc. v. Pittsburgh-Des Moines Corp.
345 N.W.2d 124 (Supreme Court of Iowa, 1984)
Determan v. Johnson
613 N.W.2d 259 (Supreme Court of Iowa, 2000)
Badgett Construction & Development Co. v. Kan-Build, Inc.
102 F. Supp. 2d 1098 (S.D. Iowa, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Eric Ziel and Carol Ziel v. Energy Panel Structures, Inc. d/b/a EPS Buildings, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eric-ziel-and-carol-ziel-v-energy-panel-structures-inc-dba-eps-iowactapp-2020.