Eric Kafton and Amanda Kafton v. Robert Merchant Jr., D/B/A R.A.M. Construction

Court of Appeals of Iowa·Decided March 26, 2014·No. 3-1182 / 13-1000·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 3-1182 / 13-1000

Filed March 26, 2014

ERIC KAFTON and AMANDA KAFTON, Plaintiffs-Appellants, vs.

ROBERT MERCHANT JR., d/b/a R.A.M. CONSTRUCTION, Defendant-Appellee.

Appeal from the Iowa District Court for Monona County, John D.

Ackerman, Judge.

Homeowners appeal the district court’s ruling on cross motions for summary judgment. AFFIRMED IN PART, REVERSED IN PART, AND REMANDED FOR DISMISSAL.

Michael P. Jacobs of Rawlings, Ellwanger, Jacobs, Mohrhauser & Nelson, L.L.P., Sioux City, for appellants.

Thomas J. Culhane of Erickson & Sederstrom, P.C., Omaha, Nebraska, for appellee.

Heard by Vogel, P.J., and Tabor and McDonald, JJ.

TABOR, J.

We are asked to decide if homeowners Eric and Amanda Kafton may bring a negligence suit against the contractor they hired to dig their basement after they paid him “settlement funds” to lift a mechanic’s lien against their property. After receiving a letter from the Kaftons listing complaints about his work on their home, Robert Merchant (doing business as R.A.M. Construction) filed a mechanic’s lien of $25,933 on their property for the remaining amount due under the contract. After back-and-forth negotiations, Merchant released the lien as the Kaftons delivered him a check for $20,000.

Eight months later, the Kaftons sued Merchant, alleging he negligently damaged their property during the construction. Merchant answered and filed a counterclaim, alleging the Kaftons breached the contract and still owed him $4,029.95. Both parties filed motions for summary judgment. The district court granted Merchant’s motion for summary judgment, holding “as a matter of law the Kaftons’ intent was to enter a global settlement” of all claims arising from the excavation work. The district court overruled the Kaftons’ motion for summary judgment on Merchant’s counterclaim. On appeal, the Kaftons ask for their negligence claims to be reinstated and for Merchant’s counterclaim to be dismissed.

Like the district court, we find ourselves bound by the reasoning in Mensing v. Sturgeon, 97 N.W.2d 145, 151 (1959), where the court held a settlement without any express reservation of rights by the settlor constitutes a complete accord and satisfaction of all claims arising from the same set of facts. Accordingly, we affirm the grant of Merchant’s motion for summary judgment on

the Kaftons’ negligence claims, reverse the denial of the Kaftons’ motion for summary judgment on Merchant’s breach-of-contract counterclaim, and remand for dismissal of the counterclaim. I. Background Facts and Proceedings In July 2011, the Kaftons entered a contract with Merchant to dig out the basement beneath their home, which was originally built in 1884. The process included jacking up the house, excavating the earth below, pouring new concrete footings, and building new basement walls. Merchant completed the project in October 2011, and submitted a final invoice dated November 2, 2011, for $27,088.

On November 22, 2011, the Kaftons sent an email to Merchant communicating their displeasure with the work done and disputing the amounts owed on the invoice. Their complaints included a longer-than projected completion time, daily mess and safety issues, backfill of only three-quarters of the house, uneven wall and floor heights, and damage to an industrial fan lent to Merchant, furnace wire, and their septic system.

On December 2, 2011, Merchant filed a mechanic’s lien in the amount of $25,933, which he alleged represented the amount remaining unpaid on the Kaftons’ account.

Through counsel, the Kraftons responded in a letter dated December 19, 2011, stating:

I represent Eric and Amanda Kafton. I have reviewed the Mechanic’s Lien and your letter of December 12, 2011. I have also reviewed the Kaftons’ line item by line item dispute regarding the invoice plus their itemization of issues and damages and expenses they suffered as a result of the work of RAM Construction. Clearly,

some or all of these issues will result in an offset of the amount [you claim] in favor of the Kaftons. In the interest of compromise and settlement, they are willing to pay $17,873.10 in exchange for a full and final release, including, obviously, a release of the Mechanic’s Lien.

In a January 4, 2012 letter, Merchant’s attorney countered:

Be advised, that my client continues to deny a majority of the issues, damages and expenses claimed by your clients. It is evident to my client that the Kaftons used his original bid to obtain a bank loan to pay for the construction cost. During the construction the Kaftons experienced problems with their septic system, due to no fault of my client, and required funds to address the septic issue.

Now the Kaftons are attempting to create issues and blame my client for the septic problem to reduce his bill and pay for the outstanding construction costs and septic expenses out of the total amount of loan funds.

Merchant’s attorney continued:

My client is unable and unwilling to accept the settlement amount stated in your letter as this would require him to take a loss on the project. However, in the interest of resolving this matter, my client will split the difference and accept payment in the amount of $21,903.05 for full satisfaction on account and release the mechanic’s lien.

On January 6, 2012, Merchant’s attorney sent an email to the Kaftons’

attorney proposing to release the mechanic’s lien upon receipt of $20,000 in “settlement funds.” In a reply email, the Kaftons’ attorney wrote: “The release is acceptable.” That email also noted the time the client would drop off the certified check for $20,000. The mechanic’s lien release stated: “The Claimant, for valuable consideration, acknowledges full and final satisfaction of the amount claimed in the Mechanic’s Lien and releases and discharges such lien against the above-referenced property.”

On September 10, 2012, the Kaftons filed a petition alleging Merchant was negligent in his work, and his negligence caused damage to their property,

including the septic tank, an industrial fan, furnace wire, and other personal property. The petition also alleged: “Defendant’s negligence resulted in a foundation that is uneven and unstable which is resulting in water intrusion and damage to the upper floors of the residence.”

On September 28, 2012, Merchant filed an answer and counterclaim. As affirmative defenses, Merchant asserted the Kaftons’ cause of action was barred due to accord and satisfaction, release, discharge, and estoppel. Merchant also filed a counterclaim, alleging the Kaftons failed to pay the amount agreed to in the contract and owed him a balance of $4,029.95.

Both parties filed motions for summary judgment. In support of his motion, Merchant presented an affidavit swearing he authorized release of the mechanic’s lien because “he was under the impression that all present and future disputes between the parties relating to [his] work on Plaintiffs’ home were forever compromised and settled.” In resistance to Merchant’s motion for summary judgment, Amy Kafton presented an affidavit avowing she and her husband found the January 6, 2012, release of the mechanics lien “to be acceptable in part, because it did not require us to release or waive any of our claims for past or future damages. . . . Defendant never asked for nor did we ever sign anything releasing any of our claims against Defendant.”

On May 24, 2013, the district court granted Merchant’s motion for summary judgment on the Kaftons’ negligence claims, and overruled the Kaftons’ summary judgment motion on Merchant’s counterclaim. The Kaftons now appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Eric Kafton and Amanda Kafton v. Robert Merchant Jr., D/B/A R.A.M. Construction, (iowactapp 2014).

Eric Kafton and Amanda Kafton v. Robert Merchant Jr., D/B/A R.A.M. Construction (Eric Kafton and Amanda Kafton v. Robert Merchant Jr., D/B/A R.A.M. Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Hastings
466 N.W.2d 697 (Court of Appeals of Iowa, 1990)
Verne R. Houghton Insurance Agency, Inc. v. Orr Drywall Co.
470 N.W.2d 39 (Supreme Court of Iowa, 1991)
Butler v. Hoover Nature Trail, Inc.
530 N.W.2d 85 (Court of Appeals of Iowa, 1994)
Robinson v. Norwest Bank, Cedar Falls, N.A.
434 N.W.2d 128 (Court of Appeals of Iowa, 1988)
Cyr v. Cyr
560 A.2d 1083 (Supreme Judicial Court of Maine, 1989)
Brown v. Hughes
99 N.W.2d 305 (Supreme Court of Iowa, 1959)
Waechter v. Aluminum Co. of America
454 N.W.2d 565 (Supreme Court of Iowa, 1990)
Determan v. Johnson
613 N.W.2d 259 (Supreme Court of Iowa, 2000)
Mensing v. Sturgeon
97 N.W.2d 145 (Supreme Court of Iowa, 1959)
State of Iowa v. Corey Douglas Driscoll
839 N.W.2d 188 (Supreme Court of Iowa, 2013)
Mark Peak v. Ellis Adams and Rachel Adams
799 N.W.2d 535 (Supreme Court of Iowa, 2011)
Holm v. Hansen
248 N.W.2d 503 (Supreme Court of Iowa, 1976)