Eric Hovde v. ISLA Development LLC

51 F.4th 771
CourtCourt of Appeals for the Seventh Circuit
DecidedOctober 24, 2022
Docket21-2894
StatusPublished
Cited by3 cases

This text of 51 F.4th 771 (Eric Hovde v. ISLA Development LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eric Hovde v. ISLA Development LLC, 51 F.4th 771 (7th Cir. 2022).

Opinion

In the

United States Court of Appeals For the Seventh Circuit ____________________ No. 21-2894 ERIC D. HOVDE and STEVEN D. HOVDE, Plaintiffs-Appellants, v.

ISLA DEVELOPMENT LLC and JEFFREY T. RIEGEL, Defendants-Appellees. ____________________

Appeal from the United States District Court for the Northern District of Illinois, Eastern Division. No. 1:18-cv-07323 — Franklin U. Valderrama, Judge. ____________________

ARGUED APRIL 13, 2022 — DECIDED OCTOBER 24, 2022 ____________________

Before ROVNER, WOOD, and ST. EVE, Circuit Judges. ROVNER, Circuit Judge. Jeffrey Riegel sought to build a con- dominium development in Isla Mujeres, and toward that end he formed ISLA Development LLC (“ISLA”) and secured a loan of millions of dollars from Steve and Eric Hovde. That project, however, ultimately failed, and more than ten years later, the Hovdes filed suit seeking to recover their funds from ISLA and Riegel. 2 No. 21-2894

Riegel formed ISLA in 2004 and acted as its manager and sole member. In exchange for the loan from the Hovdes, ISLA promised to pay the Hovdes a 25% interest rate, and Riegel agreed to act as a guarantor. Financial problems eventually shut down the project and the Hovdes sued ISLA and Riegel. The district court granted summary judgment to the defend- ants as to the claim based on the Mortgage Note (“Note”), holding that the claim was brought beyond the expiration of the ten-year statute of limitations period. That left the claim against Riegel based on his status as a guarantor. The district court initially held that the case could proceed as to Riegel, but a different district court judge who subsequently took over the case determined that the statute of limitations could be asserted in the action against the guarantor as well, hold- ing that a waiver did not operate to block that defense and the claim against Riegel was therefore untimely. The Hovdes now appeal those grants of summary judgment. We turn first to the claim based on the obligations under the Note. By its terms, the Note provided that the principal and interest on the loans would be due in June 2007, but the Note’s event-of-default acceleration clause provided that if an Event of Default occurred, “the outstanding unpaid principal balance of the Note, the accrued interest thereon and all other obligations of the Borrower to the Bank under the Loan Doc- uments shall automatically become immediately due and payable,” thus triggering the ten-year statute of limitations. One such “Event of Default” specified in the contract was if an “Act of Bankruptcy shall occur,” and “Act of Bank- ruptcy” is defined in the contract to include if ISLA or Riegel “admit in writing its inability to pay its debts as they mature.” The district court properly held that two emails sent by Riegel No. 21-2894 3

to the Hovdes constituted an admission in writing of an ina- bility to pay the debts and therefore an event of default. In an email on August 7, 2008, to Steven Hovde, Riegel revealed that a tax bill of $137,000 had to be paid by August 18, that he had been buying time with the tax officials most of the spring and summer but that it was now absolute and non-negotiable, and that he needed an advance of $250,000 just to make it until an anticipated closing in mid-September. Steven Hovde re- sponded on August 11 that he had no more money to give and that the last time he lent money he had told Riegel to shut the project down and that they would not lend any additional amounts. On September 2, Riegel sent another email, stating that he had pursued financing options but that “[a]t this point in time, my resources are exhausted.” In that email he detailed the financial challenges, including stating that as of two weeks prior all construction workers were suspended and that the management team was kept on but was not paid that past Friday, and that if all construction workers and manage- ment staff were terminated that day then outstanding sever- ance and federal taxes would total another $200–250,000. He further stated that funds of $75,000 were needed by Wednes- day morning “to avoid having Social Security persons in Mex- ico shut down the entire operation immediately.” He contin- ued that he was told that trucks would be coming to confis- cate all computer equipment from the offices and other assets and materials at the construction site to pay the social security bill owed, and that “[s]uch an action would be the instant death of the project.” He concluded by stating that he was “a very ‘stand up’ guy but at this point, with no resources of my own, I would not be able to attempt re-assembling a team on the ground.” 4 No. 21-2894

The district court did not err in holding that the language of the emails met the contract language of an admission in writing of an inability to pay his debts as they mature. Alt- hough the Hovdes argue that Riegel was continuing to seek alternative funding sources, and that the property itself and other assets still had some value, that does not alter the con- clusion that the emails constituted an admission of an inabil- ity to pay the debts. The language does not require actual in- solvency; it merely requires an admission of an inability to pay the debts as they mature—whether or not true—and the court properly held that the language in the emails consti- tuted that admission. Accordingly, the statute of limitations began to run as of September 2, 2008. The Hovdes next argue that a Forbearance Agreement of November 5, 2008, constituted a “new promise to pay” that restarted the ten-year limitations period, thus making the No- vember 2, 2018, lawsuit timely. Riegel argues that this claim was never presented to the district court and therefore is waived. In response to that contention, the Hovdes did not identify any part of the record raising the legal theory that the Forbearance Agreement constituted a new promise to pay. In- stead, they argued that the court was presented with the rele- vant facts, including the existence of the Forbearance Agree- ment, and that the applicable statute was before the court as well, “even if the precise ‘new promise to pay’ phrase was not used by the parties.” Appellant’s Reply Brief at 1. But those facts were raised only with respect to a distinctly different ar- gument, which was that the Forbearance Agreement tempo- rarily tolled the running of the statute of limitations thus ex- tending the ten-year limit. The district court rejected that ar- gument because even if the period was tolled during the forty-two days that the Forbearance Agreement was in effect, No. 21-2894 5

the Hovdes would have had to bring the claim by October 18, 2018, and the claim filed on November 2, 2018, therefore was still untimely. The argument that the Hovdes assert here, that the Forbearance Agreement was a new promise to pay that triggered a new 10-year limitations period, was never as- serted below, and is inconsistent with the argument actually made below. To the extent that the Hovdes are arguing that the court could have put together the Forbearance Agreement and the limitations period and fashioned such an argument, that is not the court’s role. The argument that the Forbearance Agreement constituted a new promise to pay was never ar- gued to the district court at all and therefore is not properly raised on appeal. Compare Rozumalski v. W.F. Baird & Assocs., Ltd., 937 F.3d 919, 925–26 (7th Cir. 2019) (holding that an issue cannot be raised on appeal if the party failed to make the spe- cific argument below even if the issue may have been before the district court in more general terms), and Domka v. Portage Cty., Wis., 523 F.3d 776, 783 (7th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hovde v. Freud
N.D. Illinois, 2024
WEC 98C-3 LLC v. SFA Holdings Inc.
99 F.4th 961 (Seventh Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
51 F.4th 771, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eric-hovde-v-isla-development-llc-ca7-2022.