ERECTION & WELDING CONTRACTORS v. ARCO CONSTRUCTION GROUP (L-2829-21, MIDDLESEX COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided February 15, 2022·No. A-3348-20·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-3348-20

ERECTION & WELDING CONTRACTORS,

Plaintiff-Respondent,

v.

ARCO CONSTRUCTION GROUP and ANGEL CABRERA,

Defendants-Appellants,

and MONROE TOWNSHIP,

Defendant.

Submitted December 14, 2021 – Decided February 15, 2022 Before Judges Rothstadt, Mayer, and Natali.

On appeal from the Superior Court of New Jersey, Law Division, Middlesex County, Docket No. L-2829-21.

Joseph J. Hocking, attorney for appellants.

Frederick A. Jacob, attorney for respondent.

PER CURIAM Defendants ARCO Construction Group, Inc. (ARCO) and its principal, Angel Cabrera, appeal from a June 11, 2021 order compelling arbitration of their dispute with plaintiff, Erection and Welding Contractors, LLC, and requiring ARCO to file a demand for arbitration with the American Arbitration Association (AAA) and pay the filing fee. 1 The motion judge entered the order after finding it was undisputed that, under the parties' agreement, ARCO had the exclusive option to litigate or arbitrate disputes and that it exercised its option, which obligated ARCO to file for arbitration and pay the required fee, subject to adjustment by the arbitrator, if warranted.

On appeal, defendants do not challenge the order compelling arbitration, but argue there was no legal basis for the judge to order that ARCO file for arbitration and pay the required fee. They also contend, for the first time on appeal, that two arbitration clauses in the parties' contract were in conflict and should have been interpreted to mean that either party had a right to compel

1 The same order dismissed with prejudice plaintiff's claims against defendant Monroe Township. Neither party appeals from that provision and the Township did not participate in this appeal, although ARCO's amended notice of appeal named the Township as an appellant.

A-3348-20

arbitration, and, therefore, because plaintiff filed this action, it should have been compelled to file the arbitration and pay the required fee.

We conclude, under the facts of this case, ARCO's argument is without any merit. We affirm as there was no dispute ARCO had the exclusive right to compel arbitration and originally asserted its right to arbitrate the parties' dispute, which resulted in the dismissal of a complaint plaintiff filed years earlier seeking the same relief as in this action.

The facts taken from the motion record are summarized as follows. On July 30, 2010, ARCO, as the general contractor on a project for Monroe Township, entered into a contract with plaintiff to perform services as a subcontractor on the project. The contract contained two provisions relating to the arbitration of disputes arising from the parties' agreement. 2

2 Section AF of the parties' agreement was captioned "Dispute Resolution." Section AF(1) stated as follows: "At the sole and exclusive option of [ARCO], any and all disputes arising from or related to the [s]ubcontract or the breach thereof shall be decided by binding arbitration in accordance with the [c]onstruction [i]ndustry [a]rbitration [r]ules of the American Arbitration Association then applicable." (Emphasis added). It also stated in Section AF(2) that "The [s]ubcontractor expressly agrees to arbitrate all disputes and this obligation as provided in the [s]ubcontract shall be specifically enforceable under applicable law." Section AG, entitled "Actions and Proceedings and Applicable Law," stated in pertinent part that "Any and all disputes arising from or relating to the [s]ubcontract or the breach thereof shall be decided by binding

A-3348-20

In 2012, ARCO began making untimely payments to plaintiff and other subcontractors. In March 2012, plaintiff requested full payment from ARCO and that if payment was not made, plaintiff would "commenc[e] an arbitration" as "[a]rbitration [was] required under section AF of the contract between the parties."

In June 2012, Monroe Township began making only partial payments to ARCO due to the disputes between ARCO and its subcontractors, which caused ARCO to file a demand for arbitration against the Township. Plaintiff did not participate in that arbitration. 3 The arbitration terminated when ARCO and Monroe Township resolved their dispute through mediation in 2014.

On November 30, 2015, plaintiff filed a complaint asserting claims against ARCO involving the Monroe project. 4 ARCO responded on January 22, 2016,

arbitration in accordance with the [c]onstruction [i]ndustry [a]rbitration [r]ules of the American Arbitration Association then applicable." 3 In February 2014, ARCO successfully petitioned a specially appointed arbitrator to join subcontractors to the arbitration, including plaintiff. Although the arbitrator's joinder award stated "ARCO ha[d] elected to arbitrate its disputes with its subcontractors" and "[t]herefore, all said contractors [were] free to bring whatever claims they may have [had] against ARCO," plaintiff did not bring any claims against ARCO or otherwise participate in that arbitration. 4 In its complaint, plaintiff asserted causes of action for breach of contract, Cabrera's personal liability, misrepresentation, breach of fiduciary duty,

A-3348-20

with a letter to plaintiff demanding arbitration of the claims plaintiff raised in its complaint. Also, on July 22, 2016, defendant filed an answer, which asserted the court lacked jurisdiction because ARCO invoked its right to arbitrate and pleaded arbitral jurisdiction as an affirmative defense.

On April 10, 2017, plaintiff acceded to ARCO's arbitration demand. On that date, the parties filed a stipulation of dismissal which stated: "[ARCO] having elected to arbitrate this matter in accordance with the Arbitration Clause of the applicable contract; it is hereby stipulated that this matter is dismissed, with prejudice, to allow the parties to proceed to arbitration." (Emphasis added). However, neither party filed for arbitration. Instead, the parties unsuccessfully engaged in settlement discussions over the course of the ensuing three years.

On June 29, 2018, plaintiff's counsel wrote to ARCO's attorney stating if payment of the money allegedly owed to his client was not paid by July 6, 2018, "we will move to arbitration." Unable to reach a resolution, on October 6, 2020, plaintiff requested ARCO set dates for arbitration. ARCO refused, asserting it believed that plaintiff had the right to file for arbitration at any time since "ARCO invoked the arbitration clause" in 2016 and that plaintiff's claims were

consumer fraud, and unjust enrichment. Plaintiff also asserted claims involving another project, however those claims were resolved separately.

A-3348-20

time-barred because plaintiff could have filed for arbitration, but it did not without any agreement to toll the statute of limitations on those claims.

On January 12, 2021, plaintiff filed the complaint in this action,5 and it applied for the entry of an order to show cause, seeking, among other relief, an order compelling ARCO to file for arbitration. On April 14, 2021, 6 a Law Division judge entered an order to show cause requiring ARCO to appear and be heard on why judgment should not be entered against it, including an order to "compel arbitration" or grant "such other relief as the court deem[ed] equitable and just." ARCO responded by filing a motion to dismiss plaintiff's complaint with prejudice and to compel plaintiff to "pursue its claims against ARCO in an arbitration that plaintiff initiates with the [AAA]."

Free access — add to your briefcase to read the full text and ask questions with AI

ERECTION & WELDING CONTRACTORS v. ARCO CONSTRUCTION GROUP (L-2829-21, MIDDLESEX COUNTY AND STATEWIDE), (N.J. Ct. App. 2022).

ERECTION & WELDING CONTRACTORS v. ARCO CONSTRUCTION GROUP (L-2829-21, MIDDLESEX COUNTY AND STATEWIDE) (ERECTION & WELDING CONTRACTORS v. ARCO CONSTRUCTION GROUP (L-2829-21, MIDDLESEX COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related