Erb Lumber Co. v. Gregory Industries, Ltd.

769 F. Supp. 221, 37 Cont. Cas. Fed. 76,206, 1991 U.S. Dist. LEXIS 10984, 1991 WL 152609
CourtDistrict Court, E.D. Michigan
DecidedJuly 16, 1991
Docket89-71022
StatusPublished

This text of 769 F. Supp. 221 (Erb Lumber Co. v. Gregory Industries, Ltd.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Erb Lumber Co. v. Gregory Industries, Ltd., 769 F. Supp. 221, 37 Cont. Cas. Fed. 76,206, 1991 U.S. Dist. LEXIS 10984, 1991 WL 152609 (E.D. Mich. 1991).

Opinion

MEMORANDUM AND ORDER

COHN, District Judge.

I.

This action is brought under the Cape-hart Act, 42 U.S.C. § 1594, and the Miller Act, 40 U.S.C. 270a et seq. 1 Plaintiff Erb Lumber Company (Erb) seeks to recover payment for materials provided for use on a project at the Selfridge Air National Guard base. In Count I, Erb seeks recovery pursuant to the Capehart Act, on a labor and material payment bond from defendant Gregory Industries, Ltd. (Gregory), the principal, and defendant International Fidelity Insurance Company (International), the surety. Count II is an action against Gregory and International under the Miller Act for payment on a Miller Act bond. Count III is an action against Gregory and defendant Randolph Jordan, the guarantor of Gregory’s account, for payment for materials supplied by Erb.

International now moves for summary judgment, arguing that: 1) Count I is barred by the statute of limitations and 2) the materials at issue in Count II were not covered by the Miller Act bond. Erb has responded, arguing: 1) the Miller Act statute of limitations is not incorporated into a Capehart Act bond, and 2) that the Miller Act covers the materials at issue in Count II. Because the Court finds that Count I is time-barred and that Count II is not covered by the Miller Act, International’s motion is GRANTED.

II.

The following facts are undisputed. This action arises out of two construction projects at the Selfridge Air National Guard Base (Selfridge) in Mt. Clemens, Michigan. Gregory was the prime contractor on both projects and, as part of its contractual obligations with respect to each, exe *223 rated two separate payment bonds in which International is named as surety.

Erb provided materials to Gregory under contracts DAA-EO7-86-C-Q078 (the Cape-hart contract) and DAH-A20-86-C-6058 (the Miller contract), between Gregory and the United States. The Capehart contract required that Gregory replace certain roofs at the Capehart housing facility at Selfridge. The contract was for an amount greater than $25,000. On September 30, 1986, a payment bond was executed by Gregory and International with respect to the Capehart contract. The United States is the sole obligee.

The government then issued a notice to proceed on the Capehart contract, received by Gregory on June 8, 1987. The contract provided that the work was to be completed within 240 calendar days of the date of receipt of the notice to proceed. The Cape-hart contract closed in October 1988. Erb provided its last shipment of materials under the contract on January 12, 1988.

The Miller contract was for the repair of roofs on various buildings located at Selfridge. On April 30, 1986, a payment bond was executed by Gregory and International with respect to the Miller contract. The government’s notice to proceed with work was received on June 3, 1986. Pursuant to the contract, work was to be completed within 140 calendar days of receipt of the notice to proceed. On December 2, 1986, Gregory notified the government that all work was complete. In a progress report dated December 1, 1986, the government found the contract work to be 99.20 percent complete. All work specified in the Miller contract was certified as complete in a final inspection report dated September 17,1987. Because of a dispute between the government and Gregory that was not settled until January 11, 1990, the contract was closed out on April 2, 1990.

According to Erb’s delivery receipts, the first delivery of material, allegedly made under the Miller contract, took place on December 3, 1987. Erb made its last such delivery on September 26, 1988. Gregory had two separately numbered accounts with Erb. One was known as “Capehart Housing,” and the other was known as “Selfridge Air National Guard.” The account billed depended on the location where the materials were delivered. Gregory opened its accounts with Erb in August 1987. During the relevant time period, Gregory also served as the contractor on two other projects at Selfridge.

III.

A.

International first argues that Count I of Erb’s complaint, which was filed on April 3, 1989, is barred by the statute of limitations. The Capehart Act contains no statute of limitations, but courts have held that the statute of limitations contained in the Miller Act also governs actions brought under the Capehart Act. See, e.g., Missouri-Illinois Tractor & Equipment Co. v. D & L Constr. Co., 337 F.2d 507, 508 (8th Cir.1964) (Blackmun, J.). The relevant provision of the Miller Act states that “no ... suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied.” 40 U.S.C. § 270b(b). Because it is undisputed that Erb’s last delivery under the Capehart contract took place on January 12, 1988, application of the Miller Act limitations period would necessitate the dismissal of Count I.

In opposition to International’s motion, Erb relies heavily on Miles Lumber Co. v. Harrison & Grimshaw Constr. Co., 305 F.2d 363, 369 (10th Cir.1962), which contains the statement: “We are concerned [in the case before us] with a Capehart Act project bond, and we are convinced that the Miller Act has no application to such a bond.” Based on Miles, Erb argues that there is a split of authority among courts of appeals as to whether the statute of limitations in the Miller Act applies to actions under the Capehart Act. This is not entirely true. The split of authority concerns the extent to which the Miller Act’s notice provisions, 40 U.S.C. § 270b(a), which establish the procedure to be followed before commencing suit, apply to Capehart Act bonds.

*224 All of the cases cited by Erb as support for its position involve a choice between differing notice provisions. That is, they involve a determination as to whether the notice provisions explicitly stated in a Cape-hart Act bond or the notice provisions set forth at 40 U.S.C. § 270b(a) control. Even the case applying Michigan law cited by Erb as an indication of how the Court of Appeals for the Sixth Circuit might rule on the question presented in this case, Hub Elec. Co. v. Gust Constr. Co., 585 F.2d 183 (6th Cir.1978), involves a conflict between statutory notice provisions and the notice provisions contained in a bond.

As to the limitations provision of the Miller Act, contained in 40 U.S.C. § 270b(b), there is no conflict. The statute of limitations in the Miller Act applies to Capehart Act bonds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
769 F. Supp. 221, 37 Cont. Cas. Fed. 76,206, 1991 U.S. Dist. LEXIS 10984, 1991 WL 152609, Counsel Stack Legal Research, https://law.counselstack.com/opinion/erb-lumber-co-v-gregory-industries-ltd-mied-1991.