ER Group, LLC. v. Great American Insurance Agency, Inc.

District Court, N.D. Indiana·Decided September 9, 2024·No. 2:20-cv-00426·Unknown

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF INDIANA HAMMOND DIVISION ER GROUP, LLC d/b/a ENGINEERED ) RIGGING, ) ) Plaintiff, ) ) v. ) Cause No. 2:20-CV-426-PPS ) FIGG BRIDGE BUILDERS, LLC and ) GREAT AMERICAN INSURANCE ) COMPANY, ) ) Defendants. ) OPINION AND ORDER This is a contract dispute arising from the construction of a bridge over the Indiana Harbor and Ship Canal in East Chicago. Plaintiff ER Group, a subcontractor, sued Figg Bridge Builders, the general contractor for the construction of the bridge, for unpaid invoices. ER Group also sought to collect from Figg’s surety, Great American Insurance Company.1 On March 27, 2024, I granted in part ER Group’s motion for summary judgment. In sum, I found that ER Group demonstrated the absence of a triable issue as to Figg’s liability under the terms of the parties’ equipment rental agreement, but that genuine fact disputes regarding the amount of damages precluded judgment on the claim. [DE 153.] I further concluded that Great American was entitled to judgment on the payment bond claim, and so I dismissed Great American from the case. Id. 1Subject matter jurisdiction in this case is based on diversity of citizenship. [DE 1.] A bench trial followed on July 23, 2024 limited to the issue of what damages were owed to ER Group from Figg and whether ER Group acted reasonably in attempting to mitigate its damages. [DE 182; DE 183; DE 184.] ER Group and Figg have submitted

proposed findings of fact and conclusions of law. [DE 171; DE 172.] Having considered the parties’ arguments and the evidence submitted, I now make the following findings of fact and conclusions of law pursuant to Rule 52(a) of the Federal Rules of Civil Procedure. To the extent that any finding of fact is deemed to be a conclusion of law, it is incorporated as such, and vice versa.

Findings of Fact On June 8, 2017, Figg, as general contractor, entered into a contract for the design and construction of a bridge over the Indiana Harbor and Ship Canal in East Chicago, Indiana for the owner, Cline Avenue Bridge, LLC which I’ll refer to as “CAB”. [DE 164 at 5–6.] On March 4, 2020, ER Group and Figg entered into a separate agreement for ER

Group to provide professional engineering services to design a Cantilever Segment Bridge Lift for the project and field technical assistance to supervise the assembly of the bridge lift according to the design plans, as well as to monitor safe use of all related equipment used with lifting bridge segments into their permanent location. [Pltf. Exh. 1.]2 The same day, ER Group and Figg entered a purchase agreement, under which

Figg agreed to purchase custom fabricated parts for the bridge lift. [Pltf. Exh. 2.] 2In referencing exhibits tendered by the parties, I will uniformly cite to Plaintiff’s admitted exhibits as “Pltf. Exh. #,” and Defendant’s admitted exhibits as “Def. Exh. #,” as these documents have not been electronically filed on the docket. 2 Most importantly, at least for present purposes, the pair on March 4, 2020 also entered a rental agreement, pursuant to which Figg leased equipment it needed to operate the bridge lift. [DE 14-2.]3 The rental agreement sets forth monthly, weekly, and

daily rental rates on the various pieces of equipment. Under the lease, Figg agreed to lease the listed equipment for a minimum of one month commencing March 30, 2020, with “minimum rent . . . paid on demand.” Any future payments would come “due thirty (30) days following the determination of the amount due,” and Figg’s initial payment was due “prior to release of equipment for shipment to [Figg]’s facility.” With

respect to the daily, weekly, and monthly rates, the lease provides that “[r]ental rates are based upon monthly use not to exceed 160 hours per month,” and use “beyond 160 hours shall be prorated hourly and added to the base rental rate.” Id. at 3. The agreement incorporates a set of additional terms and conditions. [DE 14-2.] For example, the lease agreement was portal to portal. In other words, it began “on the

date the first piece of Equipment is shipped to [Figg], and ends on the date that the last piece of Equipment is returned to [ER Group].” Following delivery to Figg, if the equipment “proves unfit for use because of accident or otherwise, [Figg]’s sole remedy is to return the equipment and terminate this lease. [Figg] shall pay all rental and other amounts due prior to termination, which shall never be less than rent due for the

minimum rental period, transportation charges and costs of any repairs.” Id. at 4. The 3DE 14-2 is the same as Pltf. Exh. 3. Because this particular exhibit does not have page numbers, with this exhibit, I will cite to the docket entry which has stamped page numbers so as to enable pinpoint cites. 3 terms further state that the equipment would be loaded at ER Group’s expense “F.O.B. [ER Group’s] yard or other point designated by [ER Group],” and Figg would, “at its own expense, . . . do all other loading, unloading, installation, dismantling and

transportation of the equipment and shall pay all other freight . . . or other transportation charges . . . from the time of loading by [ER Group] to and including the time of the equipment’s return to [ER Group].” Id. at 5. Finally, per § 15 of the terms and conditions, ER Group may “declare this Lease is in default if” Figg fails to make any payment under the lease. Id. at 6. The rental agreement includes agreed-upon rental rates for the equipment and

accessories leased. Id. at 2. The first six line items amount to $29,250.00 per month; the following five line items amount to $38,700.00 per month; and the final line item is for a $5,500.00 lump sum. Id. The rental agreement further provides for interest at the rate of 1 Month Libor (London Inter-Bank Offered Rate) + 3.25% and a 5% late fee for payments that are not received within 30 days. Id. at 3.

On March 31, 2020, the unassembled equipment (which would later be assembled into the bridge lift) was delivered to the project site. [Pltf. Exh. 4.] On April 14, 2020, ER Group issued an invoice to Figg (Invoice No. 1291) for rental fees covering the period April 28, 2020 to May 25, 2020, in the principal sum of $67,950.00. [Pltf. Exh. 5.] The invoice reiterates that the “Rental is Portal to Portal,” meaning, as suggested

above, that it could only be ended by returning the equipment to ER Group at its listed facility. Id. On April 24, 2020, ER Group issued another invoice (Invoice No. 1293) for 4 engineering services in the amount of $39,725.00. [Pltf. Exh. 6.] On April 24, 2020, ER Group also sent Figg an invoice (Invoice No. 1294) for equipment sales (material for fabrication purposes) in the amount of $14,856.54 [Pltf. Exh. 7.] The same day, ER Group

sent another invoice (Invoice No. 1295) for equipment sales (material and labor for fabrication purposes) in the sum of $75,431.60. [Pltf. Exh. 8.] On May 5, 2020, ER Group issued a final invoice (Invoice No. 1298) for rental equipment for the period May 26, 2020 to June 22, 2020, in the principal amount of $67,950. [Pltf Exh. 9.] On April 7, 2020, CAB terminated Figg as general contractor on the bridge project. But for reasons that are unclear, for many weeks, Figg did not formally notify

ER Group about its termination from the job. Christopher Cox, ER Group’s President, testified credibly that there was consistent communication between ER Group and Figg during this time period, but Figg continued to indicate that it was moving forward as general contractor on the project. For example, on April 13, Figg’s Senior VP and Project Manager William (Jay) Rohleder, Jr., emailed Robert Schlyer of ER Group, in response

Free access — add to your briefcase to read the full text and ask questions with AI

ER Group, LLC. v. Great American Insurance Agency, Inc., (N.D. Ind. 2024).

ER Group, LLC. v. Great American Insurance Agency, Inc. (ER Group, LLC. v. Great American Insurance Agency, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Thomas K. Allen, Jr. v. Cedar Real Estate Group, LLP
236 F.3d 374 (Seventh Circuit, 2001)
Willis v. Westerfield
839 N.E.2d 1179 (Indiana Supreme Court, 2006)
Troutwine Estates Development Co. v. ComSub Design & Engineering, Inc.
854 N.E.2d 890 (Indiana Court of Appeals, 2006)
Oxford Financial Group, Ltd. v. Evans
795 N.E.2d 1135 (Indiana Court of Appeals, 2003)
McCalment v. Eli Lilly & Co.
860 N.E.2d 884 (Indiana Court of Appeals, 2007)
Abbey Villas Development Corp. v. Site Contractors, Inc.
716 N.E.2d 91 (Indiana Court of Appeals, 1999)
Fetz v. Phillips
591 N.E.2d 644 (Indiana Court of Appeals, 1992)
Roy A. Miller & Sons, Inc. v. Industrial Hardwoods Corp.
775 N.E.2d 1168 (Indiana Court of Appeals, 2002)
Indiana Bureau of Motor Vehicles v. Ash, Inc.
895 N.E.2d 359 (Indiana Court of Appeals, 2008)
USA Life One Insurance v. Nuckolls
682 N.E.2d 534 (Indiana Supreme Court, 1997)
Art Country Squire, L.L.C. v. Inland Mortgage Corp.
745 N.E.2d 885 (Indiana Court of Appeals, 2001)
Four Seasons Manufacturing, Inc. v. 1001 Coliseum, LLC
870 N.E.2d 494 (Indiana Court of Appeals, 2007)
BANK ONE, NAT. ASS'N v. Surber
899 N.E.2d 693 (Indiana Court of Appeals, 2009)
Leaf Funding, Inc. v. Brogan Pharmaceuticals, Inc.
642 F. Supp. 2d 844 (N.D. Indiana, 2009)
McVay v. Store House Co.
289 F. Supp. 3d 892 (S.D. Indiana, 2017)