Equitable Asphalt Mtnc. Co. v. Parker-Washington Co.

211 F. 1019, 127 C.C.A. 663, 1913 U.S. App. LEXIS 1397
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 2, 1913
DocketNo. 3887
StatusPublished

This text of 211 F. 1019 (Equitable Asphalt Mtnc. Co. v. Parker-Washington Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Equitable Asphalt Mtnc. Co. v. Parker-Washington Co., 211 F. 1019, 127 C.C.A. 663, 1913 U.S. App. LEXIS 1397 (8th Cir. 1913).

Opinion

PER CURIAM.

Reversed and remanded, with directions to enter decree sustaining validity of patent, per stipulation, each party to pay its own costs. Costs incurred after entry of decree to be divided equally between parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
211 F. 1019, 127 C.C.A. 663, 1913 U.S. App. LEXIS 1397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/equitable-asphalt-mtnc-co-v-parker-washington-co-ca8-1913.