EOG Resources, Inc. v. James R. Hurt, Jr.

357 S.W.3d 144, 175 Oil & Gas Rep. 743, 2011 Tex. App. LEXIS 9914, 2011 WL 6260730
Court of Appeals of Texas·Decided December 15, 2011·No. 02-11-00093-CV·Published·Cited by 3 cases

Opinion

OPINION

BILL MEIER, Justice.

I. Introduction

Appellant and Cross-Appellee EOG Resources, Inc. appeals from an adverse judgment in favor of Appellee and Cross-Appellant James R. Hurt, Jr. Hurt appeals a postverdict ruling by the trial court. As to EOG’s appeal, we will reverse and render. As to Hurt’s appeal, we will affirm.

II. Factual and Procedural Background

EOG is an oil and gas exploration and development company. Standard Investment Company (SIC) is a Texas corporation whose owners include John E. Houston and Molly D. Houston.

In August 2004, EOG, as lessee, and SIC, as lessor, entered into an oil and gas lease agreement in which SIC granted EOG the right to “explore[ ], drill[ ], and construct] roads and structures thereon to produce, save, care for, treat and transport oil, gas and liquid hydrocarbons” from a tract of land covering over 11,000 acres in Hood and Erath Counties known as the Houston Ranch. In addition to royalties and other matters, the oil and gas lease addressed in detail “Surface Use Restrictions [and] Damages.”

Hurt was in the ranching business for thirty-five to forty years. In January 2005, he entered into an agreement with SIC to lease grassland on the Houston Ranch for purposes of grazing cattle. 1 The lease began on February 1, 2005, and expired in January 2006. This was the first time that Hurt had grazed cattle on the Houston Ranch, and he had no other leases or contracts with SIC prior to January 2005.

In July 2006, Hurt executed another agreement to lease grassland on the Houston Ranch. The lease identified the “LESSOR” as “Molly Houston (in care of Jim Howard.),” and it expired by its terms on June 31, 2007.

In early January 2008 at the Houston Ranch, Hurt received a shipment of cattle owned by John Bill Oman. 2 Hurt grazed Oman’s cattle over the next few months before moving 827 head of cattle to the Houston Ranch’s Northwest Trailer pasture on June 21, 2008. Hurt had checked the condition of the Northwest Trailer pasture’s perimeter fence about three weeks to a month before moving the cattle there, but he did not check the fence on or about June 21, 2008. On June 27, 2008, Hurt retrieved Oman’s cattle from the pasture and shipped 293 head of cattle — thirty-four less than he had transferred into the pasture on June 21, 2008. Hurt searched the pasture for the cattle but only discovered that parts of between 100 and 200 feet of a portion of the perimeter fence were damaged or down. The section of damaged fence was located approximately 250 feet *147 from the edge of the Houston Ranch Number 22-H well site. Outlaw Enterprises, a contractor hired by EOG, had performed work at the 22-H well site from June 16, 2008 to June 18, 2008.

On July 8, 2008, Hurt contacted Marco Herrera, a project coordinator for a company that performed work on the Houston Ranch, and notified him about the damaged fence at the 22-H well site. 3 Hurt and Herrera met J.D. Fish, an EOG foreman, at the well site that same day to view the fence, and EOG repaired the fence the following two days, on July 9 and 10, 2008. 4 According to Herrera and Fish, Hurt did not say anything about lost or missing cattle at the July 8, 2008 meeting. Hurt eventually recovered all but ten or eleven head of Oman’s cattle, and he demanded that EOG compensate him for ten head of cattle at a total of $7,250 because, according to Hurt, EOG was responsible for the damage to the fence near the 22-H well site. EOG never compensated Hurt for the lost cattle.

In March 2009, Hurt sued EOG for breach of the 2004 oil and gas lease agreement, alleging that he was a third-party beneficiary under the lease agreement. 5 At the jury trial, the trial court denied EOG’s motions for a directed verdict on Hurt’s breach of contract claim, and the jury awarded Hurt (1) $7,250 for damages caused by EOG’s failure to comply with the oil and gas lease agreement and (2) $25,000 in attorneys’ fees. After the jury returned its verdict, Hurt orally requested a ruling that EOG’s breach of the oil and gas lease agreement resulted in an ipso facto termination of the lease agreement, but the trial court denied the request. EOG filed a motion for new trial and a motion for judgment notwithstanding the verdict and, alternatively, a motion to modify, correct, or reform the judgment. All were denied. These appeals followed.

III. Hurt’s Breach of Contract Claim

In its first issue, EOG argues that “[t]he trial court erred in holding that Hurt is a third-party beneficiary” of the oil and gas lease agreement. EOG contested Hurt’s status as a third-party beneficiary in its motions for a directed verdict on Hurt’s breach of contract claim and in its motion for judgment notwithstanding the verdict as to the jury’s finding that EOG failed to comply with the oil and gas lease agreement. We therefore construe EOG’s argument as challenging the trial court’s rulings denying EOG’s motions contesting Hurt’s breach of contract claim on the basis of his status as a third-party beneficiary.

A directed verdict is proper when the evidence conclusively establishes the right of the movant to judgment as a matter of law. See Prudential Ins. Co. of Am. v. Fin. Review Servs., Inc., 29 S.W.3d 74, 77 (Tex.2000); Farlow v. Harris Methodist Fort Worth Hosp., 284 S.W.3d 908, 919 (Tex.App.-Fort Worth 2009, pet. denied). A trial court may disregard a jury verdict and render judgment notwithstanding the verdict if a directed verdict would have been proper. See Tex.R. Civ. P. 301; Tiller v. McLure, 121 S.W.3d 709, 713 *148 (Tex.2003); Fort Bend Cnty. Drainage Dist. v. Sbrusch, 818 S.W.2d 392, 394 (Tex.1991).

Hurt was neither a party to nor an assignee of the oil and gas lease agreement between EOG and SIC. Therefore, he could maintain an action to enforce the oil and gas lease agreement only if he was a third-party beneficiary of the lease agreement. See MCI Telecomms. Corp. v. Tex. Utils. Elec. Co., 995 S.W.2d 647, 650-51 (Tex.1999) (“We agree with MCI that TU is not a third-party beneficiary of the contract between MCI and MoPac; therefore, it cannot maintain an action to enforce the contract.”); Allan v. Nersesova, 307 S.W.3d 564, 571 (Tex.App.-Dallas 2010, no pet.).

It is well settled that third-party beneficiary claims succeed or fail according to the provisions of the contract upon which suit is brought. Union Pac. R.R. Co. v. Novus Int’l, Inc., 113 S.W.3d 418

Free access — add to your briefcase to read the full text and ask questions with AI

EOG Resources, Inc. v. James R. Hurt, Jr., 357 S.W.3d 144, 175 Oil & Gas Rep. 743, 2011 Tex. App. LEXIS 9914, 2011 WL 6260730 (Tex. Ct. App. 2011).

357 S.W.3d 144 (EOG Resources, Inc. v. James R. Hurt, Jr.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related