Envtl Board v. Allen Rd. Land Co. & Larkin

CourtVermont Superior Court
DecidedMarch 7, 2003
Docket96-5-02 Vtec
StatusPublished

This text of Envtl Board v. Allen Rd. Land Co. & Larkin (Envtl Board v. Allen Rd. Land Co. & Larkin) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Envtl Board v. Allen Rd. Land Co. & Larkin, (Vt. Ct. App. 2003).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

Vermont Environmental Board, Plaintiff, } } v } Docket No. 96-5-02 Vtec } Allen Road Land Co., Inc and } John Larkin, Respondents

Decision and Order

On April 23, 2002, the Chair of the Vermont Environmental Board (the Board) issued an administrative order pursuant to 10 V.S.A. ' 8008 regarding Respondents, who timely requested a hearing in Environmental Court. The Environmental Board is represented by Thomas G. Walsh, Esq.; Respondent Allen Road Land Co., Inc., and its president Respondent John Larkin, are represented by Carl H. Lisman, Esq. As necessary to distinguish between the Respondents, we will refer to them in this decision as Respondent Company and Respondent Larkin.

The Court extended the time for the hearing for good cause at the request of and by agreement of the parties to allow motions to be decided in advance of trial. The parties also agreed to bifurcate the hearing, so that all that is before the Court at the present time is the question of whether any violations occurred, and whether any remedial order is necessary regarding the permitted hours of operation. The parties agreed that a hearing on whether any penalty is warranted should be postponed until after the question of violation is resolved.

The statutes, rules and permits applicable to this matter are 4 V.S.A. Chapter 27; 10 V.S.A. Chapter 151 (Act 250); 10 V.S.A. Chapter 201; and Land Use Permit (Act 250 Permit) No. 4C1060-EB and 4C1060. 10 V.S.A. ' 8012(c)(2).

Findings

Respondent Larkin signed the Act 250 permit application for the Irish Farm Development at issue in this case, signing both as Applicant and as Landowner. Deborah Sherman is the Project 1 Manager for the Irish Farm Development. She is employed by Respondent Company and reports directly to Respondent Larkin. She visited the Irish Farm Development on an approximately daily basis from the time that site work began there in the spring of 1991 at least to the time of trial.

The Act 250 Permit issued by the Board defines the project as the subdivision of a 28.21 acre parcel (known as Parcel C) on Allen Road in South Burlington to create 32 single-family residential lots and one lot (Lot 36) with six residential duplex structures (also described as 12 multi-family units), to be served with municipal water and sewage facilities, plus three additional lots: Lot 35 to be retained by Respondent Company, Lot 33 proposed as open space, and Lot 34 to be dedicated as a city park. The project includes new roadways to be dedicated to the City and a stormwater system including three detention basins to be maintained by the homeowners= association.

The permittee is required by the Board= s decision to A complete, operate and maintain@ the project in accordance with the terms and conditions of both the Act 250 Permit as issued by the District Commission and the Act 250 Permit as issued by the Board, with the plans and exhibits on file with the Board and with the conditions of the Board= s permit. In turn, the District Commission= s permit requires that the project be A completed, operated and maintained@ in accordance with the Commission= s Findings of Fact and Conclusions of Law, with the plans and exhibits on file with the Commission, and with the conditions of the Commission= s permit. The permittee of the District Commission= s permit is shown on its cover page as the Respondent Company, by its president Respondent Larkin. The permittee of the Environmental Board= s permit is shown on its cover page as Respondent Company, by its attorney Carl H. Lisman, Esq.

Respondents proposed in the application that Respondent Company would construct the multi-family structures but that the undeveloped subdivided lots would be sold to individual homeowners to construct single-family homes of their own design, limited by the permit application and approval as to specific building envelopes and water demand and sewage flow (as limited by number of bedrooms allowed). Other than those limitations, the design and construction specifications of the single-family houses were not submitted for approval as part of the project application, as contrasted with those for the multi-family buildings.

Construction on the Irish Farm Development began in mid-March of 2001. From time to time in April and May 2001 at lease two residents of the neighboring Harbor Heights and Bay View Drive areas observed that work on the roads and infrastructure occurred on weekdays after 5:00 p.m. until as late as 6:00 or 7:00 p.m., and on some weekends, but neither kept a log recording the specific dates or times of these observations during those months. The Administrative Order at issue in this case alleges a violation involving work outside the standard hours of operation on March 28, 2001, but no evidence was presented or findings requested specific to that date.

S.D. Ireland Brothers Corporation (S.D. Ireland Brothers) and S.D. Ireland Concrete Construction Corporation (S.D. Ireland Concrete) are related corporations. S.D. Ireland Brothers Corporation is the excavation and earthmoving company with which Respondent Company contracted for the site work, road construction, and to install the utility infrastructure at the Irish Farm Development, including to dig the foundation holes for the duplex buildings. S.D. Ireland Concrete Construction Corporation is the concrete construction company with which Respondent Company contracted to install the concrete curbs along the roadways and to install the concrete foundations, basement floors and curbs needed for the duplex buildings. Observers unfamiliar with the corporate structure will not necessarily differentiate between them and may perceive and refer to both as A S.D. Ireland.@

Mr. Tim Cole is a vice-president and was the project manager for S.D. Ireland Brothers for the work performed at the Irish Farm Development from the spring of 2001 to the time of trial. From the time S.D. Ireland Brothers began work in March 2001 until Mr. Cole received an email regarding the limited hours of operation from a neighbor on May 11, 2001 (regarding her observations of work beyond those hours on May 10, 2001 and before), the workers and equipment would show up at the job site between about 6:30 a.m. and 7:00 a.m. to be ready to start work at 7:00 a.m., and would routinely work until 7:00 or 8:00 p.m. Prior to May 11, 2001, Mr. Cole may have received a copy of the Irish Farm Development= s Act 250 Permit but Respondents had not specifically informed him of the time limitations on the activities of S.D. Ireland Brothers and had not made those time limitations an element of any contract involving S.D. Ireland Brothers.

As of May 11, 2001, Mr. Cole and hence S.D. Ireland Brothers Corp. was aware of the limited hours of operation imposed by the Act 250 Permit for the project. Shortly after that date, Mr. Cole discussed the hours of operation with Ms. Sherman, Project Manager for Respondent Company, who told him that it was acceptable under Respondent Company= s understanding of the permit limitations for S.D. Ireland Brothers to continue for an undefined > short time= after 5:00 p.m. > if necessary= to > button up= the site at the end of a work day. Mr. Scott Ireland is the president of S.D. Ireland Concrete Construction Corporation. Respondents had not specifically informed him of the time limitations on S.D. Ireland Concrete= s activities at the Irish Farm Development and had not made those time limitations an element of any contract involving S.D. Ireland Concrete. At some time after June 12, 2001 and before July 28, 2001, Mr. Cole made Mr. Ireland, and hence S.D. Ireland Concrete, aware of the Monday through Friday, 7:00 a.m. to 5:00 p.m. time limitations in the Act 250 Permit. Mr. Scott Ireland testified that S.D. Ireland= s workers >

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
Envtl Board v. Allen Rd. Land Co. & Larkin, Counsel Stack Legal Research, https://law.counselstack.com/opinion/envtl-board-v-allen-rd-land-co-larkin-vtsuperct-2003.