Environmental Protection Information Center v. Carlson

CourtDistrict Court, N.D. California
DecidedDecember 4, 2019
Docket3:19-cv-06643
StatusUnknown

This text of Environmental Protection Information Center v. Carlson (Environmental Protection Information Center v. Carlson) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Protection Information Center v. Carlson, (N.D. Cal. 2019).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 NORTHERN DISTRICT OF CALIFORNIA 6 7 ENVIRONMENTAL PROTECTION Case No. 19-cv-06643-EMC INFORMATION CENTER, 8 Plaintiff, ORDER DENYING PLAINTIFF’S 9 MOTION FOR PRELIMINARY v. INJUNCTION 10 ANN CARLSON, et al., Docket No. 11 11 Defendants. 12 13 14 I. INTRODUCTION 15 The United States Forest Service approved six logging projects to mitigate the safety 16 hazards affecting the roads in Mendocino National Forest. These projects will allow commercial 17 logging of nearly 7,000 acres of trees that are dead, dying, and/or live trees that are rapidly 18 deteriorating such that they pose a risk of falling onto the public roadway. The operations of two 19 projects have already begun. 20 Plaintiff Environmental Protection Information Center (“EPIC”) moves the Court for a 21 preliminary injunction “to preserve the status quo pending resolution of the case, allow[] only the 22 felling of hazard trees which are imminently likely to fall into a roadway [or] other developed 23 area, prohibit tree felling along Level 1 roads and OHV trails, and prohibit the sale and removal of 24 any felled trees in order to avoid irreparable harm to Plaintiff.” Docket No. 11 (“Mot.”) at 1. 25 In an earlier ruling, this Court partially granted EPIC’s motion for a temporary restraining 26 order:

27 The Government may not authorize any operations as to the M10 represented the project has not yet begun, and would not begin until, 1 as government counsel estimated, a week after a contractor wins the bid. However, the Government may continue to advertise and/or 2 sell the M10 West project (e.g., continue the bidding process, finalize the contract award, etc.), so long as it informs bidders that 3 any awarded contract is subject to an injunction. Plaintiff’s remaining relief for a TRO is DENIED. The Bartlett and M5 4 Pacific projects may continue. 5 Docket No. 42. Based on a review of the administrative record, the briefs filed herein pertaining 6 to the instant motion as well as the motion for a temporary restraining order (including the 7 amicus), and oral argument of the parties, the preliminary injunction motion is DENIED. 8 II. BACKGROUND 9 A. Factual Background 10 In July 2018, the Ranch Fire burned nearly 300,000 acres in Mendocino county. Docket 11 No. 1 (“Compl.”) ¶ 16. In response, the Forest Service announced six projects to “remove 12 ‘merchantable’ trees within 200 feet on both sides of selected roads and within 100 feet of the 13 roads that run adjacent to the Snow Mountain Wilderness.” Id. ¶ 19. The projects are titled as the 14 M1, M3, M5, M10, Bartlett, and Felkner Projects (collectively, the “Projects”). Id. ¶ 22. 15 The complaint alleges the location of these Projects “are draped by mixed conifer forest, 16 oak woodlands, and are interspersed by recovering burned, logged, and un-forested areas, 17 including chaparral. The conifer forests and oak woodlands, where logging is proposed, provide 18 essential wildlife habitat, hiding cover, and core habitat for old forest-dependent wildlife, 19 including the threatened Northern spotted owl.” Id. ¶ 17. According to Plaintiff, the Ranch Fire 20 “created new forest habitat types, including complex early seral forest habitat, also known as ‘snag 21 forest’ habitat, which, if left unlogged, serves as important habitat for small mammals and birds. 22 Predators, including Northern spotted owls, seek out these burned areas due to their abundance of 23 small mammal prey species.” Id. ¶ 18. 24 In June 2019, the Forest Service began accepting bids for the Bartlett Project, which 25 pertained to the sale of 1.7 million board feet of timber. Id. ¶ 28. Bidding ended the following 26 month. Id. The Forest Service awarded the Bartlett Project in August 2019. In August 2019, the 27 Forest Service began accepting bids for the M5 Pacific Ridge Project, which involved 6.5 million 1 Project. Id. ¶ 34. 2 The Forest Service did not conduct an environmental review under the National 3 Environmental Quality Act (“NEPA”) for any of the Projects. Instead, it relied on the categorical 4 exclusion under 36 C.F.R. § 220.6(d)(4), which applies to “[r]epair and maintenance of roads, 5 trails, and landline boundaries.” 6 As of November 21, 2019, operations for the Bartlett and M5 Pacific Ridge Projects were 7 underway with five and seven weeks of operations remaining until completion, respectively. The 8 Forest Service finalized bidding for the M10 West Project. The Court extended its TRO of the 9 M10 West Project’s operations to December 2, 2019. The Court determined that the TRO would 10 have little to no prejudice to the Forest Service because finalization of the M10 West contract will 11 take at least one or two weeks before operations can begin. The remaining projects have not 12 entered their bidding phases. 13 In its motion for a preliminary injunction, EPIC does not argue for a blanket ban on 14 logging. Instead, it takes the position that the Forest Service must comply with NEPA by 15 conducting an environmental review before approving and permitting the Projects to go forward. 16 Nor does EPIC object to the felling of trees at risk of falling. It argues only truly at-risk trees 17 should be felled, and that once felled they should remain on the forest ground in their natural 18 habitat and not removed by loggers for harvesting. 19 B. Procedural Background 20 EPIC filed its lawsuit on October 16, 2019. See Compl. The complaint alleges one claim 21 for relief: NEPA violation. Id. ¶ 63–67. EPIC concurrently filed this motion, noticed for 22 November 14, 2019, but not in compliance with this Court’s 35-day rule for noticing motions. 23 The Court reset the hearing to December 19, 2019. Thereafter, EPIC moved for a temporary 24 restraining order to enjoin all logging pending the resolution of the preliminary injunction motion. 25 Docket No. 18. The Court then advanced the TRO hearing to November 21, 2019. Docket No. 26 42. Sierra Pacific Industries (“SPI”), the contractor of the M5 Pacific Project, filed a motion to 27 intervene as of right under FRCP 24(a) or, in the alternative, permissive intervention pursuant to 1 Id. 2 As noted above, on November 5, 2019, the Court issued a TRO and set the hearing on the 3 preliminary injunction for November 21, 2019. 4 III. LEGAL STANDARD 5 A party seeking a preliminary injunction must meet one of two variants of the same 6 standard. Under the original Winter standard, a party must show “that he is likely to succeed on 7 the merits, that he is likely to suffer irreparable harm in the absence of preliminary relief, that the 8 balance of equities tips in his favor, and that an injunction is in the public interest.” Winter v. 9 NRDC, Inc., 555 U.S. 7, 20 (2008). Under the “sliding scale” variant of the Winter standard, “if a 10 plaintiff can only show that there are ‘serious questions going to the merits’—a lesser showing 11 than likelihood of success on the merits—then a preliminary injunction may still issue if the 12 ‘balance of hardships tips sharply in the plaintiff’s favor,’ and the other two Winter factors are 13 satisfied.” All. for the Wild Rockies v. Pena, 865 F.3d 1211, 1217 (9th Cir. 2017) (quoting Shell 14 Offshore, Inc. v. Greenpeace, Inc.,709 F.3d 1281,1291 (9th Cir. 2013)). 15 IV. DISCUSSION 16 A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robertson v. Methow Valley Citizens Council
490 U.S. 332 (Supreme Court, 1989)
United States v. Anthony W. Dawson
1 F.3d 457 (Seventh Circuit, 1993)
United States v. Iupeli Migi
329 F.3d 1085 (Ninth Circuit, 2003)
Native Ecosystems Council v. Leslie Weldon
697 F.3d 1043 (Ninth Circuit, 2012)
Shell Offshore, Inc. v. Greenpeace, Inc.
709 F.3d 1281 (Ninth Circuit, 2013)
The Lands Council v. McNair
537 F.3d 981 (Ninth Circuit, 2008)
Alliance for the Wild Rockies v. Jim Pena
865 F.3d 1211 (Ninth Circuit, 2017)
Earth Island Inst. v. Elliott
290 F. Supp. 3d 1102 (E.D. California, 2017)
Earth Island Inst. v. Elliott
318 F. Supp. 3d 1155 (E.D. California, 2018)
Luterman v. Levin
318 F. Supp. 11 (D. Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
Environmental Protection Information Center v. Carlson, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-protection-information-center-v-carlson-cand-2019.