This text of 610 F. App'x 409 (Environmental Integrity Project v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Integrity Project v. United States Environmental Protection Agency, 610 F. App'x 409 (5th Cir. 2015).

Opinion

PER CURIAM: *

Under the Clean Air Act (“CAA”), 42 U.S.C. §§ 7401-7671q, each state must create and administer a State Implementation Plan (“SIP”) designed to achieve Na *410 tional Ambient Air Quality Standards. 1 The SIP must include a scheme for New Source Review (“NSR”), which governs pre-construction permits for new constructions or modifications to existing constructions. The CAA distinguishes between major and minor pollution sources based ,on a threshold amount of pollution; major sources are subject to much more stringent regulations.

In 1994, the State of Texas submitted to the Environmental Protection Agency (“EPA”) for approval a proposed SIP that provides- for flexible permits for Minor NSR. Under the plan, an entity may obtain a flexible permit for emissions up to a specified aggregate limit below the major source threshold. Thereafter, the flexible permit holder may modify its facilities without further regulatory review provided emissions remain below the aggregate permit limit. The State of Texas has always maintained that the flexible permit plan covers only Minor NSR and excludes Major NSR. Nevertheless, the EPA issued a rule disapproving the Texas SIP in 2010, 16 years after it was first submitted, based in part on its determination that the plan, as written, could allow flexible permit holders to circumvent rules for Major NSR.

The State of Texas petitioned the Fifth Circuit for review. In a 2012 opinion, we concluded that the SIP, as written, covers only Minor NSR, and that all Major NSR (both for new constructions and for modifications) remains covered by the more stringent Major NSR rules. Indeed, we concluded that the plan “affirmatively requires compliance with Major NSR” and that it therefore “does not, on its face, allow major sources to evade Major NSR.” 2 Responding to the EPA’s specific contention that the flexible permit plan might allow permit holders to evade Major NSR for major source modification, we explained, “Major sources cannot use a flexible permit to avoid Major NSR without violating the law.” 3 In short, we concluded that the flexible permit plan proposed by Texas covers only Minor NSR and categorically excludes Major NSR. Accordingly, we vacated the EPA’s final rule and remanded to the EPA for further consideration.

On remand, following a public comment period in which the parties to this proceeding participated, the EPA issued a final rule conditionally approving the SIP, 4 relying primarily on this court’s 2012 opinion. Several citizen/environmental groups have brought this petition for review, asserting that the EPA’s approval of the SIP was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law,” in violation of 5 U.S.C. § 706(2)(A). Significantly, the petitioners do not argue .that the 2012 Fifth Circuit opinion, on which the EPA relied, was incorrect or should be disregarded. We conclude that our earlier opinion controls here.

The petitioners have not materially distinguished their arguments from the EPA’s arguments in the earlier proceeding, which we already rejected. In essence, all of the petitioners’ arguments rest on the assumption that the SIP will somehow allow flexible permit holders to *411 bypass Major NSR when making major modifications to existing constructions. Our 2012 opinion forecloses that assumption. As we explained, the flexible permit plan by definition covers only Minor NSR and affirmatively requires compliance with any applicable Major NSR. If, as the petitioners argue, some flexible permit holders attempt to evade Major NSR, they will be doing so not in accordance with the SIP but in violation of it.

In short, the EPA raised virtually identical arguments in the earlier proceeding, and we categorically rejected them in our 2012 opinion. The EPA relied on our 2012 opinion on remand when it issued its final order conditionally approving the SIP. The petitioners do not challenge the 2012 opinion and do not raise any arguments which are not foreclosed by that opinion. On this record, we cannot say the EPA’s final rule approving the SIP was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law”; to the contrary, it was explicitly in accordance with the law set out in our 2012 opinion. Thus, we deny the petition for review and uphold the EPA’s final rule approving the SIP.

DENIED.

*

Pursuant to 5th Cir. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5th Cir. R. 47.5.4.

1

. The background for this opinion is set out in Texas v. U.S. E.P.A., 690 F.3d 670 (5th Cir.2012).

2

. Id. at 678.

3

. Id. at 686.

4

.The final rule was conditioned on Texas making certain minor changes irrelevant to this proceeding, which Texas apparently has since completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
610 F. App'x 409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-integrity-project-v-united-states-environmental-protection-ca5-2015.