Environmental Elements Corp. v. Mayer Pollock Steel Corp.

497 F. Supp. 58, 1980 U.S. Dist. LEXIS 13633
CourtDistrict Court, D. Maryland
DecidedJanuary 21, 1980
DocketCiv. T-77-1669
StatusPublished
Cited by7 cases

This text of 497 F. Supp. 58 (Environmental Elements Corp. v. Mayer Pollock Steel Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Elements Corp. v. Mayer Pollock Steel Corp., 497 F. Supp. 58, 1980 U.S. Dist. LEXIS 13633 (D. Md. 1980).

Opinion

THOMSEN, Senior District Judge.

This diversity action, tried before the court without a jury, arises out of a subcontract between Environmental Elements Corporation (plaintiff or EEC), a subsidiary of Koppers Company, and Mayer Pollock Steel Corporation (defendant or MP), in which defendant agreed to purchase the material for and to fabricate and paint four large bayline columns, to be installed by plaintiff in a structure known as a “precipitator” which plaintiff had contracted to erect and did erect for American Electric Power Company (AEP) in West Virginia. The columns contained 96 flange welds and 60 web welds. The welding was done by defendant at its plant in Pennsylvania; the columns were accepted there by plaintiff and were sent to the work site in West Virginia; however, after the columns were installed in the precipitator it was discovered that all or almost all of the 156 welds were defective, and that the welding would have to be redone in the precipitator, which was a costly operation. Plaintiff seeks to recover from defendant the cost of examining the welds and rewelding the defective welds.

Diversity jurisdiction exists and is not disputed. Plaintiff’s principal office is in Maryland; defendant’s plant is in Pennsylvania. Those states have enacted the Uniform Commercial Code (UCC), as has West Virginia.

Plaintiff alleged, in the first count of its complaint, that defendant breached the subcontract in question in several ways:

(1) that defendant’s welders were not qualified for unlimited thickness welding, as required by the contract;
(2) that defendant failed to fabricate the bayline columns in accordance with the drawings;
(3) that defendant’s welding was defective in workmanship;
(4) that defendant’s welding failed to comply with the practices set forth by the American Welding Society in its Structural Welding Code (SWC), as required by the contract; and
(5) that defendant failed to comply with its responsibility to perform appropriate quality control.

Defendant denied those allegations, but before final argument on the law the court heard argument on the facts and found that plaintiff had proved all the alleged breaches *60 set out above, except (1). 1 Defendant, therefore, has relied heavily upon its contentions:

(A) that plaintiff itself had responsibilities under SWC to exercise quality control over the welding, which plaintiff failed to do; and

(B) that plaintiff failed to give notice of breach to defendant within a reasonable time after it should have discovered such breach or breaches.

Defendant argues that the failures on plaintiff’s part relieve defendant from any liability under the contract.

Plaintiff’s second count alleged that on October 21, 1976, after the discovery that the welds would have to be repaired, defendant entered into an agreement providing that' defendant would pay for the entire cost of rewelding defendant’s welds on the four bayline columns, all of which had' been installed in the precipitator at the job site in West Virginia; that pursuant to this agreement plaintiff performed the necessary rewelding of the welds, and billed defendant for the costs thereof, which defendant refused to pay.

Defendant denies that the agreement alleged in the second count was made. Defendant concedes, however, that after the defects were discovered and reported by plaintiff to defendant, but before the repair work was begun, defendant’s vice-president (Raker) had discussed the matter with plaintiff’s purchasing officer and other representatives of plaintiff in Baltimore, and had offered to participate, to an unspecified extent, in the costs of replacing the MP welds which required replacement, but defendant argues that no amount was ever agreed upon.

At the trial each side called witnesses and offered depositions and exhibits, some many pages in length.

At the conclusion of the evidence each side presented proposed findings of fact. In accordance with a practice of this court, each side marked its opponent’s proposed findings: blue for those findings or portions thereof which are admitted, red for those which are disputed, and yellow for those which are conceded to be true but considered immaterial. After full argument on the facts the court wrote “found,” “not found” or “found as modified” on each proposed finding, and filed with the clerk as part of the record in this case the proposed findings and the court’s ruling on each. Thereafter, both sides filed briefs, and oral argument on the law as applied to the facts has been heard.

Because of the detailed findings, it is not necessary to set out the facts at length in this opinion. It should be noted that this is not a tort action for negligence, but is an action in contract based upon (I) the original subcontract between the parties hereto, and (II) the alleged agreement between plaintiff’s representatives and Raker, defendant’s vice president, at the meeting in Baltimore on October 21, 1976.

I

As stated above, in the third and fourth paragraphs of this opinion, the facts found by the court support nos. (2), (3), (4) and (5) of the allegations of breach of contract contained in plaintiff’s first count.

(a)

The first defense advanced by defendant thereto is that “plaintiff failed to give notice of breach to defendant within a reasonable time after it [plaintiff] should have *61 discovered such breach and is therefore barred from any remedy.” This defense is based upon UCC § 2-607(3)(a). That subsection provides:

(3) Where a tender has been accepted
(a) The buyer must within a reasonable time after he discovers or should have discovered any breach notify the seller of breach or be barred from any remedy;

Section 1-204(2) states: “What is a reasonable time for taking any action depends on the nature, purpose and circumstances of such action.”

Whether notice of breach has been given within a reasonable time is ordinarily a question of fact based upon all the surrounding circumstances. Lynx, Inc. v. Ordnance Products, Inc., 273 Md. 1, 327 A.2d 502 (1974); Smith v. Butler, 19 Md.App. 467, 311 A.2d 813 (1973). 2 Where the facts are undisputed and but one inference can be drawn therefrom as to the reasonableness of the notice, the question is one of law. Id.

The evidence shows that in mid-December 1975, after receiving an inspection release form from plaintiff, defendant shipped the bayline columns to plaintiff at the job site (the AEP plant then being constructed in West Virginia), where they were accepted by plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
497 F. Supp. 58, 1980 U.S. Dist. LEXIS 13633, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-elements-corp-v-mayer-pollock-steel-corp-mdd-1980.