Environmental Defense v. U.S. Army Corps of Engineers

515 F. Supp. 2d 69, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20243, 66 ERC (BNA) 1273, 2007 U.S. Dist. LEXIS 67633
CourtDistrict Court, District of Columbia
DecidedSeptember 13, 2007
DocketCivil Action 04-1575 (JR)
StatusPublished
Cited by9 cases

This text of 515 F. Supp. 2d 69 (Environmental Defense v. U.S. Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Defense v. U.S. Army Corps of Engineers, 515 F. Supp. 2d 69, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20243, 66 ERC (BNA) 1273, 2007 U.S. Dist. LEXIS 67633 (D.D.C. 2007).

Opinion

MEMORANDUM

JAMES ROBERTSON, District Judge.

Plaintiffs Environmental Defense and National Wildlife Federation challenge the U.S. Army Corps of Engineers’ authorization of a flood control project in the St. Johns Bayou and New Madrid Flood- *74 way on the west bank of the Mississippi River in the “bootheel” of southeastern Missouri. Plaintiffs ask the court to declare that the Corps, as well as the Secretary of the Army, Pete Geren, have violated the Water Resources Development Act of 1986 (“1986 WRDA”), the Water Resources Development Act of 1974 (“1974 WRDA”), the federal Clean Water Act (“CWA”), the National Environmental Policy Act of 1969 (“NEPA”), the Rivers and Harbor Appropriation Act of 1899 (“RHAA”), and the Administrative Procedure Act (“APA”); to declare that the USDA is violating the Swampbuster provisions of the Food Security Act of 1985 (“FSA”) and the APA; and to enjoin these violations. 1

In plaintiffs’ submission, the St. Johns Bayou-New Madrid Floodway Project is a terrible idea: It will not accomplish the flood control benefits claimed for it; its cost estimate relies on a discount rate last seen during the Eisenhower Administration; it violates statutory requirements for cost-sharing by local districts; and the Corps has improperly manipulated its habitat models to make it seem that the project’s environmental impacts will be fully mitigated, when they will not. It is not for this court to determine whether the project is a good idea or a bad one, or to pass judgment on the policy implications of public works. On their last point, however, the plaintiffs are correct. As discussed below, the Corps of Engineers has resorted to arbitrary and capricious reasoning— manipulating models and changing definitions where necessary — to make this project seem compliant with the Clean Water Act and the National Environmental Policy Act when it is not. Because it is not, and because the government’s arbitrary and capricious actions violate the Administrative Procedure Act, the plaintiffs’ motion for summary judgment [87] must be granted. The defendants’ cross-motion [92] will be denied. Further construction work on the project will be enjoined, and the Corps will be required to restore the disturbances created by the preliminary construction work that has already been completed.

Background 2

“The Mississippi will always have its own way; no engineering skill can persuade it to do otherwise; it has always torn down the petty basketwork of the engineers and poured its giant floods whithersoever it chose, and it will continue to do this.” — Mark Twain

This case presents the latest chapter in the story of the complicated relationship between the Army Corps of Engineers and the mighty Mississippi River. The flood control project in question (originally two projects, now treated as one) would transform two major drainage basins in a 400,-000 acre project area: the New Madrid Floodway, and the St. Johns Bayou Basin immediately to its west. The New Madrid Floodway piece of the project would close a 1500 foot gap in the Mississippi River Levee (“MRL”), construct a concrete box culvert with gates to control water flow between the river and the floodplain, and install a large pump to remove water from *75 behind the closed gates. The St. Johns Basin piece involves construction of a second pump, to remove water that collects in the lower part of the St. Johns Basin, and the widening and straightening of three separate channels to speed water removal from the area.

The New Madrid Floodway is the last sizable section of the lower Mississippi River floodplain that remains connected to the river: 90 percent of the floodplain has been transformed — mostly into cropland— by the Corps and by the private developers it regulates. 2002 RSEIS, attached to Plaintiffs’ MSJ [87] as Ex. 1 at E-53, E-73 (hereinafter “2002 RSEIS”). The construction of approximately 1600 miles of levees and supporting structures along the lower Mississippi began in a coordinated fashion in 1882. When the Corps completed the MRL in 1933, it left a quarter-mile gap along the New Madrid Floodway — the gap the Corps now proposes to close — so that the floodway could serve as a release valve for high water on the river. Id. at 100-01. When inundated, the floodplain provides invaluable habitat for fish and wildlife — half of the river’s fish species follow the river as it spills into the flood-way during flood conditions, to reproduce away from the river’s punishing currents.

Seasonal flooding in the New Madrid Floodway interferes with farming and economic development, however, and the Corps has sought for many years to close the levee gap and drain the floodplain. It received congressional authorization to do so in 1954, and it has spent decades shoring up local support, developing complementary projects, and maneuvering around financial and environmental hurdles, in order to complete what it considers the final component of the Mississippi River Levee system. Especially cumbersome and time-consuming have been the Corps’ efforts to satisfy environmental requirements. In the last eight years alone, in response to numerous concerns and objections from government agencies and environmental groups, the Corps has prepared a Draft Supplemental Environmental Impact Statement (1999), a Final Supplemental Environmental Impact Statement (2000), a Revised Supplemental EIS (2002), and a second Revised Supplemental EIS (2006), prompting a biologist studying the project to fret that the agency may run out of abbreviations.

Plaintiffs filed this lawsuit in September 2004 challenging the 2002 RSEIS and subsequent Record of Decision (“ROD”). They moved for summary judgment on their many claims in March 2005[23]. Defendants cross-moved for summary judgment in May 2005[31]. In June 2005, three days before the date set for oral argument on the cross-motions, defendants acknowledged a major math error in the 2002 RSEIS, withdrew their challenged ROD and their cross-motion for summary judgment, and moved for a remand so that the Corps could prepare another Revised Supplemental Environmental Impact Statement [40]. I allowed the remand on condition that an appropriate attorneys’ fee award be negotiated [48]. When the parties reported their inability to agree on a fee award, I stayed the case anyway, to await the issuance of a revised project plan [51].

In May 2006, plaintiffs moved to compel the filing of an administrative record [53], and in June 2006, plaintiffs moved for a preliminary injunction [58] and filed a second amended complaint [105]. I denied the preliminary injunction in July 2006, finding that, although plaintiffs had demonstrated a substantial likelihood of success on the merits of one of their claims, the first phase of construction was unlikely to inflict irreversible injury [74], I conditioned that ruling on the Corps’ agreement *76 to undo any project construction in the event of plaintiffs’ ultimate success on the merits of their case. In August 2006, the Corps announced that it would shortly issue a Notice of Intent to Proceed with the first phase of construction: site preparation for the pumping plant, involving the creation of a cofferdam [80].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Association of Private Sector Colleges and Universities v. Duncan
110 F. Supp. 3d 176 (District of Columbia, 2015)
Delta Air Lines, Inc. v. Export-Import Bank of the United States
85 F. Supp. 3d 387 (District of Columbia, 2015)
Theodore Roosevelt Conservation Partnership v. Salazar
605 F. Supp. 2d 263 (District of Columbia, 2009)
Wilderness Society v. Babbitt
District of Columbia, 2009
Wilderness Society v. Salazar
603 F. Supp. 2d 52 (District of Columbia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
515 F. Supp. 2d 69, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20243, 66 ERC (BNA) 1273, 2007 U.S. Dist. LEXIS 67633, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-defense-v-us-army-corps-of-engineers-dcd-2007.