Enviro. Contractors v. Moon

2002 MT 287N
Montana Supreme Court·Decided December 10, 2002·No. 00-572·Published

Opinion

No. 00-572

IN THE SUPREME COURT OF THE STATE OF MONTANA 2002 MT 287N

ENVIRONMENTAL CONTRACTORS, LLC., Plaintiff and Respondent, v.

WINFIELD MOON, SR., Defendant and Appellant.

APPEAL FROM: District Court of the Thirteenth Judicial District, In and for the County of Yellowstone, The Honorable G. Todd Baugh, Judge presiding.

COUNSEL OF RECORD:

For Appellant:

M. Dayle Jeffs, Rodney W. Rivers, Jeffs & Jeffs, Provo, Utah; Kenneth D.

Peterson, Peterson and Schofield, Billings, Montana

For Respondent:

(No Respondent’s Brief filed)

Submitted on Briefs: August 2, 2001

Decided: December 10, 2002 Filed:

Clerk

Justice James C. Nelson delivered the Opinion of the Court.

¶1 Pursuant to Section I, Paragraph 3(c), Montana Supreme Court 1996 Internal Operating Rules, the following decision shall not be cited as precedent but shall be filed as a public document with the Clerk of the Supreme Court and shall be reported by case title, Supreme Court cause number and result to the State Reporter Publishing Company and to West Group in the quarterly table of noncitable cases issued by this Court.

¶2 Winfield Moon, Sr. (Moon), appeals a Supplemental Judgment of the District Court for the Thirteenth Judicial District, Yellowstone County, awarding additional attorney's fees to Environmental Contractors, LLC. (EC), in a dispute involving the dismantling of the Frank Bird Power Plant in Billings. We reverse and remand for an evidentiary hearing.

¶3 We address the following issue on appeal: Did the District Court err when it awarded additional attorney's fees to EC?

Factual and Procedural Background

¶4 On July 24, 1996, Moon entered into a contract with the Montana Power Company (MPC) to dismantle and remove equipment from the Frank Bird Power Plant in Billings. Part of the contract required MPC to pay the general contractor on the project $800,000 for asbestos removal while the plant was being demolished and salvaged.

¶5 Moon entered into a contract with EC on September 5, 1996, designating EC as the general contractor on the project. This contract required Moon to hire a demolition contractor by a specific date, but he failed to do so. Consequently, under the terms of this

contract, EC became the demolition contractor for which EC was to receive payment for the cost of the work plus a 10% contractor's fee.

¶6 An escrow agreement on the project required Moon to deposit into an escrow account the funds necessary to pay the cost of the work. The funds were to be free and clear of any security interest, lien, encumbrance or claim. Moon deposited $1,000,000 into the escrow account and agreed to fund the account for any additional sums owing. Throughout the work on the plant, EC repeatedly advised Moon that the cost of the work would exceed the amount in the escrow account and that additional funds were necessary. The cost of the project, not including the asbestos removal, was $1,354,580.60. Moon paid EC $1,013,363.71 out of the escrow account, leaving a balance owing to EC of $332,544.15 which Moon agreed to pay, but never did.

¶7 On May 6, 1998, EC filed suit for the amount due under the contract. That same day, EC filed a Motion for Writ of Attachment on part of the equipment removed from the power plant. Moon filed his answer on July 6, 1998, claiming that EC was not entitled to any additional funds as $1,000,000 was the agreed price for the entire job.

¶8 Thereafter, EC filed a notice that it intended to take Moon's deposition. The deposition was to be videotaped and telephonic. The place for taking Moon's deposition was set to accommodate Moon, yet Moon failed to appear for the deposition. Consequently, EC moved for sanctions against Moon consisting of granting judgment in favor of EC. In addition, EC moved for attorney's fees and costs.

¶9 A bench trial in this matter was held on September 21, 1999. After hearing testimony

from both parties, the District Court took the matter under advisement and set a time for a hearing to determine the amount of attorney's fees to be awarded in the underlying case. Moon failed to appear at that hearing.

¶10 In its October 27, 1999 Final Judgment, the District Court awarded EC $332,544.15 on the contract claim, $55,141.79 in pre-judgment interest, and $32,099.05 in attorney's fees as the prevailing party in the action and as a sanction against Moon for failing to appear at various depositions and hearings throughout the proceedings. The court also awarded EC interest on the total judgment award of $419,784.99 at 10% per annum from the date of the judgment until that amount is paid in full, as well as reasonable attorney's fees and costs that EC may incur in collecting those amounts. Moon did not appeal this judgment.

¶11 On April 19, 2000, EC moved for supplemental attorney's fees and costs incurred in its attempt to collect on the original judgment from Moon. In its June 9, 2000 Supplemental Judgment, the District Court granted EC's motion and awarded EC attorney's fees and costs in the amount of $91,247.29. Moon now appeals the District Court's Supplemental Judgment.

Standard of Review

¶12 Determining what constitutes reasonable attorney's fees is a discretionary task for the District Court and this Court will not disturb its judgment in the absence of an abuse of that discretion. Majers v. Shining Mountains (1988), 230 Mont. 373, 380, 750 P.2d 449, 453 (citing Talmage v. Gruss (1983), 202 Mont. 410, 412, 658 P.2d 419, 420; Carkeek v. Ayer (1980), 188 Mont. 345, 347, 613 P.2d 1013, 1015).

Discussion

¶13 Did the District Court err when it awarded additional attorney's fees to EC?

¶14 Moon makes several arguments in support of his contention that the District Court erred in awarding supplemental attorney's fees to EC. First, he argues that the court erred in awarding attorney's fees without contractual or statutory authority. Second, he argues that the court erred in awarding attorney's fees without holding an evidentiary hearing on the reasonableness of the attorney's fees. And, third, he argues that the court erred in awarding attorney's fees against Moon for collection efforts against Westco Energy, Inc. (Westco), the company that Moon contends now owns the equipment from the power plant.

¶15 As to Moon's first contention, he is correct that Montana law only allows attorney's fees when authorized by statute or contract. "The measure and mode of compensation of attorneys and counselors at law is left to agreement, express or implied, of the parties. . . ." Section 25-10-301, MCA. "Attorney fees are awardable only where statute or contract provides for their recovery." Northwestern Nat’l Bank v. Weaver-Maxwell, Inc. (1986), 224 Mont. 33, 44, 729 P.2d 1258, 1264 (citations omitted).

¶16 However, in Montana, the contractual right to attorney's fees is treated as reciprocal:

Whenever, by virtue of the provisions of any contract or obligation in the nature of a contract made and entered into at any time after July 1, 1971, one party to such contract or obligation has an express right to recover attorney fees from any other party to the contract or obligation in the event the party having that right shall bring an action upon the contract or obligation, then in any action on such contract or obligation all parties to the contract or obligation shall be deemed to have the same right to recover attorney fees and the prevailing party in any such action, whether by virtue of the express contractual right or by virtue of this section, shall be entitled to recover his

reasonable attorney fees from the losing party or parties. [Emphasis added.]

Section 28-3-704, MCA; Majers, 230 Mont. at 381, 750 P.2d at 454. In this case, the "General Conditions" contract between Moon and EC provided at § 3.18.1 and § 9.10.2, that Moon could recover attorney's fees under certain conditions. Therefore, because attorney's fees are reciprocal in Montana, EC is entitled to its attorney's fees as the prevailing party.

Free access — add to your briefcase to read the full text and ask questions with AI

Enviro. Contractors v. Moon, 2002 MT 287N (Mo. 2002).

2002 MT 287N (Enviro. Contractors v. Moon) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Carkeek v. Ayer
613 P.2d 1013 (Montana Supreme Court, 1980)
Talmage v. Gruss
658 P.2d 419 (Montana Supreme Court, 1983)
Northwestern National Bank v. Weaver-Maxwell, Inc.
729 P.2d 1258 (Montana Supreme Court, 1986)
Glaspey v. Workman
763 P.2d 666 (Montana Supreme Court, 1988)
Stark v. Borner
762 P.2d 857 (Montana Supreme Court, 1988)
Majers v. Shining Mountains
750 P.2d 449 (Montana Supreme Court, 1988)
First Security Bank of Havre v. Harmon
841 P.2d 521 (Montana Supreme Court, 1992)
State ex rel. Department of Highways v. Helehan
615 P.2d 925 (Montana Supreme Court, 1980)
Amundson v. Wortman
777 P.2d 315 (Montana Supreme Court, 1989)