Enterprise Partners v. County of Perkins

619 N.W.2d 464, 260 Neb. 650, 2000 Neb. LEXIS 226
Nebraska Supreme Court·Decided November 3, 2000·No. S-99-1096·Published·Cited by 5 cases

Opinion

McCormack, J.

NATURE OF CASE

Enterprise Partners (Enterprise) brought a declaratory judgment action seeking the declaration of the trial court as to whether two ordinances passed by the Perkins County Board of Commissioners (the Board) were valid. These ordinances attempt to locally regulate livestock confinement facilities by regulating odor and flies emanating from the facilities (Ordinance 98-1) and by preventing the escape of animal waste onto land within the county (Ordinance 98-2). The trial court found generally for the Board and found that both ordinances were valid and enforceable. Enterprise appeals this ruling. This court removed this case from the Nebraska Court of Appeals under the power to regulate the caseloads of this court and the Court of Appeals.

BACKGROUND

In April 1998, the Board became aware of proposals to build hog confinement facilities in Perkins County. At subsequent meetings of the Board, individuals and public groups expressed concerns about the effect these types of facilities would have on the environment, on the health of the citizens of Perkins County, and the need to prevent these facilities from being built. The Board sent a letter to the Nebraska Department of Environmental Quality (DEQ) voicing its concerns and going on record as opposing the approval of a permit to allow Enterprise to construct a hog confinement facility in Perkins County.

DEQ responded in a letter addressing the Board’s concerns and explaining evaluation procedures and the requirements that needed to be met in order for a permit to be issued. DEQ also *652 pointed out that two of the Board’s concerns could not be addressed by DEQ as it did not have the authority to regulate those issues. These issues were the odor and insects and the impact on county roads. DEQ stated that “[t]he Legislature has given counties the authority to implement land use planning and adopt zoning regulations which could govern the location of livestock facilities. Odors, dust and insects are considered to be nuisances and are not regulated by the DEQ.” With regard to the impact on county roads, DEQ stated that “[t]his is not an issue which DEQ can address, but as a local issue it may possibly be addressed through load limit restrictions.”

Proposed ordinances were submitted to the Board, and discussion was held on December 21, 1998. Ordinance 98-1 attempts to locally regulate livestock confinement facilities by regulating odor emanating from the facility by requiring that certain parts of the facility be covered. By controlling odor, other problems with flies would be avoided. Ordinance 98-2 requires large-scale livestock operations to demonstrate that no livestock waste, liquid or solid, would be carried or washed onto or into county roads, ditches, or properties adjacent to the facility during or following a 25-year storm. This demonstration must also be updated on a yearly basis through inspections by the county. The Board passed both ordinances and increased the civil penalty contained in them from $200 to $5,000 per day for each violation.

Enterprise filed a petition for declaratory judgment arguing that the ordinances are zoning ordinances and were passed in violation of Neb. Rev. Stat. '§ 23-114.03 (Reissue 1997) which requires the Board to have a county comprehensive development plan before the adoption of zoning regulations. The Board stipulated that it had not adopted a comprehensive zoning plan pursuant to § 23-114.03. Enterprise also asserted that Ordinances 98-1 and 98-2 contain environmental requirements that are specifically reserved for the state. Enterprise also argued that these ordinances deprived it of property without due process of law and that the Board lacked the authority to impose civil penalties.

The trial court ruled that the ordinances were not zoning ordinances but fell within the exercise of police powers granted to *653 the counties by the Legislature, that no preemption or conflict existed between the ordinances and state statutes, and that the ordinances were not arbitrary or unreasonable and did not violate the constitution. The trial court found generally for the Board and found that both ordinances were valid and enforceable.

ASSIGNMENTS OF ERROR

Enterprise assigns as error the trial court’s finding that (1) Ordinances 98-1 and 98-2 fall within the exercise of police power granted to the counties by the Legislature, (2) the ordinances were not zoning ordinances, (3) the Board did not have to comply with § 23-114.03 when it adopted the ordinances and that they are valid, (4) Neb. Rev. Stat. § 54-2401 et seq. (Reissue 1998) and Neb. Rev. Stat. § 81-1501 et seq. (Reissue 1994 & Cum. Supp. 1996) did not preempt the field in the areas covered by the ordinances, (5) the ordinances were additional to and complimentary to or in aid of the furtherance of § 54-2401 et seq. and § 81-1501 et seq., and (6) the ordinances were not arbitrary and vague.

STANDARD OF REVIEW

In an appeal from a declaratory judgment, an appellate court, regarding questions of law, has an obligation to reach its conclusion independent from the conclusion reached by the trial court. Dunn v. Daub, 259 Neb. 559, 611 N.W.2d 97 (2000); Callahan v. Washington Nat. Ins. Co., 259 Neb. 145, 608 N.W.2d 592 (2000).

ANALYSIS

Enterprise assigns that the trial court erred in not finding that Ordinances 98-1 and 98-2 were zoning ordinances. Enterprise asserts that the ordinances are zoning ordinances and were passed by the Board in violation of § 23-114.03. Section 23-114.03 provides that “[z]oning regulations shall be adopted or amended by the county board only after the adoption of the county comprehensive development plan by the county board ...” Both Enterprise and the Board stipulated that “Perkins County, Nebraska, has not adopted a comprehensive zoning plan pursuant to Neb. Rev. Stat. §23-114, et. seq.” *654 Therefore, Enterprise concludes that Ordinances 98-1 and 98-2 are invalid because the Board does not have a comprehensive development plan. We agree.

A county is a political subdivision of the state having subordinate powers of sovereignty conferred by the Legislature. Hoiengs v. County of Adams, 245 Neb. 877, 516 N.W.2d 223 (1994). A political subdivision has only that power delegated to it by the Legislature; a grant of power to a political subdivision is to be strictly construed. Metropolitan Utilities Dist. v. Twin Platte NRD, 250 Neb. 442, 550 N.W.2d 907 (1996).

Free access — add to your briefcase to read the full text and ask questions with AI

Enterprise Partners v. County of Perkins, 619 N.W.2d 464, 260 Neb. 650, 2000 Neb. LEXIS 226 (Neb. 2000).

619 N.W.2d 464 (Enterprise Partners v. County of Perkins) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Amorak v. Cherry Cty. Bd. of Comrs.
318 Neb. 723 (Nebraska Supreme Court, 2025)
In Re Initiative Petition No. 382
2006 OK 45 (Supreme Court of Oklahoma, 2006)
GUENZEL HANDLOS v. County of Lancaster
655 N.W.2d 384 (Nebraska Supreme Court, 2003)
DLH, Inc. v. Lancaster County Board of Commissioners
648 N.W.2d 277 (Nebraska Supreme Court, 2002)
Wilkerson v. City of Pauls Valley
2001 OK CIV APP 66 (Court of Civil Appeals of Oklahoma, 2001)