Entergy Nuclear/Vt Yankee Thermal Discharge Permit Amendment
Opinion
STATE OF VERMONT
ENVIRONMENTAL COURT
}
In re: Entergy Nuclear/ Vermont Yankee } Thermal Discharge permit amendment } Docket No. 89-4-06 Vtec (Appeal of Connecticut River Watershed Council, } Trout Unlimited (Deerfield/Millers 349 Ch.), } and Citizens Awareness Network) } (Appeal of New England Coalition } on Nuclear Pollution) } (Cross-Appeal of Entergy Nuclear } Vermont Yankee, LLC) } }
Decision and Order on Renewed Motion for Stay Appellants Connecticut River Watershed Council, Trout Unlimited (Deerfield/Millers 349 Chapter), Citizens Awareness Network (Massachusetts Chapter) and New England Coalition on Nuclear Pollution, and Cross-Appellant Entergy Nuclear Vermont Yankee, LLC, appealed from a March 30, 2006 decision of the Vermont Agency of Natural Resources, approving an amendment of a thermal discharge permit issued to Entergy Nuclear Vermont Yankee, LLC.
Appellants Connecticut River Watershed Council (CRWC), Trout Unlimited, and Citizens Awareness Network (CAN) are represented by Patrick A. Parenteau, Esq., David K. Mears, Esq., and Justin E. Kolber, Esq.; Appellant New England Coalition on Nuclear Pollution (NECNP) is represented by Evan J. Mulholland, Esq.; Cross-Appellant-Applicant Entergy Nuclear Vermont Yankee, LLC (Entergy) is represented by Elise N. Zoli, Esq., Peter D. Van Oot, Esq., Sarah Heaton Concannon, Esq. and U. Gwyn Williams, Esq.; the Vermont Agency of Natural Resources is represented by Catherine Gjessing, Esq. and Warren T. Coleman, Esq.; and the Water Resources Panel of the Natural Resources Board
is represented by John H. Hasen, Esq.1 Appellants have renewed their motion to stay the permit amendment, pending the conclusion of the merits of this appeal2. The trial is scheduled to be held at the Windham Superior Courthouse in Newfane on June 26, 27, 28 and 29; on July 5 and 6; and on July 9, 10, 11, 12, and 13; and will continue, if necessary, at the Environmental Court in Berlin on July 26 and 27. In addition, July 3 is available on the Court’s schedule for any motion hearings or conferences by telephone. The final submission of responsive memoranda on the parties’ requests for findings and memoranda of law is due (on the present schedule) on August 9, 2007.
The permit amendment on appeal in this matter allows the thermal discharge from Entergy Nuclear/Vermont Yankee to increase the temperature of the Connecticut River, within a defined measurement area or mixing zone, by an additional 1/ F (by comparison to its existing permit3) from June 16 through October 14 of each year. Appellants argue that the stay will preserve the status quo of Entergy’s existing permit conditions during the pendency of this litigation. It is the applicant that bears the burden of proof that it qualifies for the amendment at issue in this appeal.
As in 2006, the Court is obligated to consider the movants’ likelihood or substantial
1 The Windham Regional Commission appeared through James Matteau and John Bennett but has since withdrawn as a party.
2 The Court has considered all the memoranda filed in relation to this motion; any motions to exclude them are DENIED as moot.
3 The underlying permit of which this is an amendment expired on March 30, 2006.
The parties have advised the Court that the renewal permit process is unlikely to result in the issuance of a renewal permit until at least January of 2008, and the Court therefore denied a motion to consolidate the prospective appeal of that permit with the present appeal. V.R.E.C.P. 2(b). The parties should be prepared to advise the Court whether the thermal discharge conditions are also at issue in the renewal permit proceedings.
possibility of success on the merits of this de novo appeal, any irreparable injury that may occur in the absence of a stay, whether the grant of a stay will substantially harm other parties, and whether a stay will serve the best interests of the public. In re Allied Power & Light Co., 132 Vt. 554, 556 (1974), as discussed by Justice Skoglund in issuing a stay during the pendency of the appeal in In re Stormwater NPDES Petition, Docket No. 2004- 515 (Vt. Supreme Ct., April 7, 2005).
For the purposes of a motion to stay in a case such as this, the status quo is the facility’s continued operation under its existing permit, not its operation under the amendment on appeal. In their memoranda, the parties continue to raise the issue of the scope of this proceeding in this Court. As we explained in 2006 and in footnote 4 on page 5 of the decision issued today on the other pending motions, the statutory provision under which this appeal is taken is entirely unambiguous that it is de novo. 10 V.S.A. §8504(h). Unlike in judicial review of administrative agency action in the federal system or in some other states, no presumption is afforded the fact that the permit amendment was issued by the ANR, and the Court is not charged with determining whether the ANR determination is supported by substantial evidence on the record as a whole.
The fact that the appeal is de novo casts no aspersions on the capability, hard work, or careful consideration given to these or any other proceedings at the ANR level. It was the legislature, not this court, that established the de novo standard applicable to cases in which the ANR is the decisionmaker appealed from; it was equally a de novo standard when such appeals were heard by the Water Resources Board under former 10 V.S.A. §1269. The de novo standard in these appeals may be contrasted with the deference given ANR technical determinations in Act 250 land use cases, 10 V.S.A. §8504(i), or the deference given ANR technical pollution abatement or environmental restoration directives in enforcement cases. Compare 10 V.S.A. §8012(b)(2) (ANR orders which must be remanded to the agency if the Court disagrees with the remedial provisions) with 10 V.S.A.
§8012(b)(3), (4), (5) (those which may be modified or determined anew by the Court). The de novo standard does not allow or encourage the Court to make policy contrary to that promulgated by the ANR in its regulations or the legislature in its statutes; rather, the Court is obligated to apply to the evidence which the parties will present in the scheduled trial the same substantive standards as were applicable before the agency.
Appellants have come forward with sufficient evidence to demonstrate a substantial possibility that they will prevail on the merits; that is, a sufficiently substantial possibility to examine and weigh the other factors to be considered in whether or not to grant a stay.
Appellants have shown sufficient potential for irreparable injury to American shad in the Connecticut River through the summer of 2007 (for the growth of the present cohort of juveniles and as they become accustomed to cooler water temperatures prior to their migration down the river in the fall) to warrant the stay during the pendency of this summer’s trial, at which further evidence is expected to be presented as to the relative effects of predation, river temperature and any other factors4 on fluctuations in the population of shad, salmon and any other indicator species.
On the other hand, the grant of the stay will not substantially harm the other parties.
Entergy has only shown a financial consequence to it, due to the operation of the cooling towers rather than the discharge to the river during the applicable period. Because the harm is financial, by definition it is not irreparable. The Court expects that the parties at trial will address Entergy’s proffered evidence regarding back pressure in the hottest summer months and the respective limitations of the cooling towers and the river cooling capacity under certain operating conditions. During the approximate two-and-a half to
Free access — add to your briefcase to read the full text and ask questions with AI