Entergy Arkansas, Inc. v. Arkansas Public Service Commission

289 S.W.3d 513, 104 Ark. App. 147, 2008 Ark. App. LEXIS 862
CourtCourt of Appeals of Arkansas
DecidedDecember 17, 2008
DocketCA 07-949
StatusPublished
Cited by7 cases

This text of 289 S.W.3d 513 (Entergy Arkansas, Inc. v. Arkansas Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Entergy Arkansas, Inc. v. Arkansas Public Service Commission, 289 S.W.3d 513, 104 Ark. App. 147, 2008 Ark. App. LEXIS 862 (Ark. Ct. App. 2008).

Opinion

Robert J. Gladwin, Judge.

The Arkansas Public Service Commission (PSC) ordered a $5.67 million rate decrease for Entergy Arkansas, Inc., an electric utility that serves approximately 670,000 customers in the state. Entergy appeals on numerous grounds, one of which merits a partial reversal. In all other respects, we affirm the PSC’s decision.

On August 15, 2006, Entergy petitioned the PSC for an increase in retail rates. The petition, as amended, sought approximately $106.5 million in additional revenue. A number of entities intervened in the case, including the Attorney General’s Utilities Rate Advocacy Division. After the parties submitted voluminous pre-filed testimony, a hearing was conducted from April 25, 2007, through May 4, 2007. Thereafter, the PSC issued Order No. 10, finding that Entergy’s revenue requirement was excessive and should be reduced by approximately $5.67 million, effective June 15, 2007. 1 Entergy petitioned for rehearing, which the PSC’s Order No. 16 denied in all pertinent respects. This appeal followed. Entergy asserts sixteen arguments (along with several sub-arguments) for reversal.

I. Standard of Review

The PSC has wide discretion in choosing its approach to rate regulation and we do not advise the Commission on how to make its findings or exercise its discretion. Consumer Utils. Rate Advocacy Div. v. Ark. Pub. Serv. Comm’n, 99 Ark. App. 228, 258 S.W.3d 758 (2007). Our review of PSC orders is limited by Ark. Code Ann. § 23-2-423 (c) (Repl. 2002), which provides in part:

(3) The finding of the commission as to the facts, if supported by substantial evidence, shall be conclusive.
(4) The review shall not be extended further than to determine whether the commission’s findings are supported by substantial evidence and whether the commission has regularly pursued its authority, including a determination of whether the order or decision under review violated any right of the petitioner under the laws or Constitution of the United States or of the State of Arkansas.

If an order of the Commission is supported by substantial evidence and is neither unjust, arbitrary, unreasonable, unlawful, nor discriminatory, the appellate court must affirm the Commission’s action. See Consumer Utils. Rate Advocacy Div., supra; Bryant v. Ark. Pub. Serv. Comm’n, 46 Ark. App. 88, 877 S.W.2d 594 (1994). To establish an absence of substantial evidence, the appellant must demonstrate that the proof before the Commission was so nearly undisputed that fair-minded persons could not reach its conclusion. Id. Administrative action may be regarded as arbitrary and capricious where it is not supportable on any rational basis, and something more than mere error is necessary to meet the test. See Consumer Utils. Rate Advocacy Div., supra. To set aside the Commission’s action as arbitrary and capricious, the appellant must prove that the action was a willful and unreasoning action, made without consideration and with a disregard of the facts or circumstances of the case. Id.

II. Procedural Arguments

Entergy challenges three of the Commission’s procedural rulings. It argues first that the PSC violated constitutional guarantees of due process by limiting the cross-examination of witnesses. A full and fair hearing is a fundamental requirement of due process in a utility rate case. See Ark. Pub. Serv. Comm’n v. Continental Tel. Co., 262 Ark. 821, 561 S.W.2d 645 (1978). In almost every setting, due process includes the right to confront and cross-examine witnesses. See Ark. Dep’t of Human Servs. v. A.B., 374 Ark. 193, 286 S.W.3d 712 (2008).

Entergy does not argue in this case that it was wholly deprived of the opportunity to cross-examine witnesses. Rather, it contends that it was prohibited from further cross-examination once the Commissioners had questioned the witnesses. We find that Entergy waived this argument by not making a timely objection below.

Prior to the hearing, the Commission informed all parties of its long-standing rule that, once cross-examination of a witness by counsel was completed and the Commissioners began the independent questioning, further examination by counsel was foreclosed. Entergy did not object to this rule prior to the hearing, nor did it object on the first day of the hearing when the Chairman asked if there were any procedural matters to be addressed. Thereafter, the Commission applied the rule over two days of testimony with no objection by any party and no requests for additional cross-examination. It was not until the third day of the hearing that Entergy asked to cross-examine a witness after the Commissioners had questioned him, and, upon being denied permission to do so, objected to the rule for the first time. It is well established that a party waives an argument by not objecting below at the first opportunity. See Swink v. Lasiter Constr., Inc., 94 Ark. App. 262, 229 S.W.3d 553 (2006).

In any event, we cannot say that the Commission abused its discretion in enforcing the rule, which is clearly designed to bring an end to witness examination in these lengthy cases. The Commission has wide latitude in conducting and expediting its hearings. See Continental Tel. Co., supra. To that end, it may prescribe rules of procedure and use its discretion to facilitate its efforts to ascertain the facts. See Ark. Code Ann. § 23-2-403 (Repl. 2002). Further, as the Commission observed, it would be unfair if Entergy were allowed to pursue additional cross-examination when all other parties had refrained from doing so in reliance on the rule. Given the circumstances, we decline to reverse on this point.

Next, Entergy argues that the Commission violated due process by restricting the subject matter of post-hearing briefs to two contested issues, and the length of post-hearing briefs to thirty pages for the initial brief and fifteen pages for the response. Entergy has not demonstrated that the Commission’s action denied it a full and fair hearing. See Ark. Elec. Energy Consumers v. Ark. Pub. Serv. Comm’n, 35 Ark. App. 47, 813 S.W.2d 263 (1991) (holding that the appellant, in attacking a procedure as a denial of due process, has the burden of proving its invalidity). The briefs were filed at the conclusion of an eight-day proceeding, during which the issues were well defined and the parties’ positions were made exceedingly clear. There is no indication that the Commission, having viewed the extensive pre-filed testimony and heard the five testimony and cross-examination of the witnesses, was not fully aware ofEntergy’s arguments for a rate increase.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
289 S.W.3d 513, 104 Ark. App. 147, 2008 Ark. App. LEXIS 862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/entergy-arkansas-inc-v-arkansas-public-service-commission-arkctapp-2008.