Enright v. United States

54 F.2d 182, 73 Ct. Cl. 416
CourtUnited States Court of Claims
DecidedDecember 7, 1931
DocketNo. E-612
StatusPublished
Cited by9 cases

This text of 54 F.2d 182 (Enright v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Enright v. United States, 54 F.2d 182, 73 Ct. Cl. 416 (cc 1931).

Opinion

GREEN, Judge.

The plaintiffs are receivers of the W. & A. Fletcher Company, and as such bring suit to recover the balance which is due that company on overpayments of taxes after deducting certain underpayments thereon. The parties have stipulated that the overpayments on taxes made by the Fletcher Company exceed the underpayments thereon in the sum of $292,671.51, which is due the plaintiffs subject to any counterclaim which the defendant may be able to establish in this suit. The only controversy with reference to the elaim set up in the petition is as to whether the plaintiffs are entitled to any interest thereon and if so, how much.

The principal questions in the case are with reference to the counterclaim which defendant has filed herein, which arises out of contracts made by and between the United States Shipping Board Emergency Fleet Corporation and the W. & A. Fletcher Company in 1918 for the manufacture of certain turbines and boilers. The evidence shows that a contract was entered into between the Fletcher Company and the defendant in the first instance for the manufacture of' ten steam turbine units at a specified price for each unit. The Fletcher Company completed this contract and was paid therefor at the contract price, with the exception of an amount due for increase in cost of labor thereon amounting to $53,919.89, which is conceded to be a credit to which plaintiffs are entitled.

During the pendency of the contract above referred to, which may for convenience be called the original contract, a supplemental contract was entered into for the construction of ten more turbine units on the same terms. This contract has been referred to in the evidence and argument as supplement No. 1. Thereafter there was a further supplemental contract entered into for twelve additional turbine units on the same terms so far as the contract price is concerned. This contract has been referred to as supplement No. 2.

[187]*187Later the Fleet Corporation sent an order to the contractor reinstating certain oil pumps, coolers, and spare parts provided for in supplements 1 and 2. The contractor complied ‘with this order and performed the ■work required thereby. The defendant settled in full for this order of what has been called the “reinstated items” in the manner shown in finding 8.

In the latter part of 1918 a further contract which was also supplemental was entered into between the Fletcher Company and the defendant, whereby the Fletcher Company agreed to construct1 twelve boilers at a specified price.

The two supplemental contracts above referred to were suspended or canceled by defendant before completion, and the boiler contract was suspended before any work had been done thereon, but not until after a certain amount of the materials had been purchased and acquired by the Fletcher Company. On each of these contracts the defendant made large advance payments and also progress payments. Defendant now claims that these advance and progress payments largely exceeded the amount which was due the Fletcher Company, and that, after allowing the Fletcher Company all proper credits on account of the cancellation of the contracts, the contractor was justly indebted to the defendant in the sum of $552,332.13, for which, with interest, the defendant asks judgment.

As against this counterclaim plaintiffs contend:

First, that defendant cannot maintain a suit to recover payments made in accordance with the contracts;

Second, if it be held that plaintiffs cannot be allowed anything above just compensation, the burden of proof is upon defendant to show what this just compensation was, and that defendant has failed to sustain this burden;

Third, that in any event just compensation in this case is measured by the proportion of the cost of the work and materials furnished on the contracts, which were not completely performed as compared with the total cost of the work to be done, and that when this ratio is obtained just compensation will be the same proportion of the total contract price. (This contention was presented on reargument of the ease.)

With reference to the contention made on behalf of plaintiffs that defendant cannot in any event recover any of the advance and progress payments made pursuant to the contracts, we do not think that this contention merits extensive discussion. The argument on behalf of plaintiffs is based in part on the fact" that the notices which terminated further operations on the contracts do not use the word “cancel” or “cancellation” with reference to the contracts, but simply notified the contractor “to suspend all work and hold up all commitments.” From this fact it is contended that the contracts were not in fact canceled. But this action was utterly at variance with the contracts which were not for certain turbines or turbines partially completed, which was the condition of the work when the contracts were terminated. The contracts were indivisible. When the defendant terminated the contracts and refused to allow plaintiffs to go any further with the work and to recognize any commitments that the contractor should thereafter make for material, it in effect canceled the contracts and was ignoring their provisions with reference to the completion of the work for which it had made the contracts. The evidence shows very clearly that all this was fully understood by the parties. It is true that the word “suspend” sometimes means to “cease temporarily,” but the notices also called for a statement under oath with reference to progress condition, piaterials used, and commitments made, and the subsequent conduct of the parties showed clearly that neither party expected any of the work to go on further unless further arrangements were made. The notices were sent out'under the statute in force at the time, which gave the government the right to cancel or suspend the contracts and provided that in such event the contractor should receive just compensation. Authorities are hardly necessary to show that if the contractor received anything above just compensation, then under the provisions of the statute the defendant is entitled to recover back the amount thereof. But see United States v. Skinner & Eddy Corp. (C. C. A.) 35 F.(2d) 889, and United States v. U. S. Fidelity Co., 236 U. S. 512, 35 S. Ct. 298, 59 L. Ed. 696.

In the supplemental contracts there was a provision making the provisions of the original contract a part thereof, and in this connection it becomes necessary to consider a paragraph in the original contract as follows:

“The contractor agrees that in the event the advance of one hundred and eighty-two thousand dollars ($182,000) provided for herein, under subdivision (a) of section 2 of this article, has not been completely repaid upon the date of the final completion and de[188]*188livery of the units contracted for herein, or when the date of the forfeiture or cancellation of this contract, as hereinbefore provided, then in such events, the contractor shall repay, in cash, any balance of the advance payment of one hundred and eighty-two thousand dollars ($182,000) remaining unpaid, as aforesaid, within thirty (30) days from the date of the final completion and delivery of the units contracted for herein, or from the date of the forfeiture or cancellation of this contract, as the case may be.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patton v. United States
74 Fed. Cl. 110 (Federal Claims, 2006)
American Travelers Life Ins. v. Travelers Indemnity Co.
201 N.E.2d 46 (Indiana Court of Appeals, 1964)
Kraemer Mills, Inc. v. United States
319 F.2d 535 (Court of Claims, 1963)
KRAEMER MILLS, INCORPORATED v. the UNITED STATES
319 F.2d 535 (Court of Claims, 1963)
Timm Aircraft Corp. v. Byram
213 P.2d 715 (California Supreme Court, 1950)
Sioux Tribe of Indians v. United States
64 F. Supp. 312 (Court of Claims, 1946)
Ship Construction & Trading Co. v. United States
91 Ct. Cl. 419 (Court of Claims, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
54 F.2d 182, 73 Ct. Cl. 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/enright-v-united-states-cc-1931.