English v. Hetherington & Berner, Inc.

71 F.2d 613, 1934 U.S. App. LEXIS 3155
CourtCourt of Appeals for the Seventh Circuit
DecidedJune 4, 1934
DocketNo. 5098
StatusPublished

This text of 71 F.2d 613 (English v. Hetherington & Berner, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
English v. Hetherington & Berner, Inc., 71 F.2d 613, 1934 U.S. App. LEXIS 3155 (7th Cir. 1934).

Opinion

Before EVANS, SPARKS, and FITZ HENRY, Circuit Judges.

This action was instituted by appellee, a citizen of Indiana, against appellant, a citizen of Illinois, to recover damages for the alleged breaeh of a contract wherein it was agreed that appellee’s assignor as a sub-eon-tractor would furnish, and appellant would pay for, certain labor and material consisting of the fabrication and installation of the steel required in the erection of a court house at Kokomo, Howard County, Indiana.

The first count of the declaration relied specifically upon the contract, and the second count consisted of the common counts in assumpsit. Appellant under oath filed the general issue and four special pleas in which ho contended: (1) That at the time of signing the contract in suit it was orally agreed by the parties that it would not become effective until a pending suit to enjoin the Commissioners of Howard County from building the court house should terminate favorably to the Commissioners; (2) that the contract was signed upon the implied condition that the litigation would terminate favorably and that the court house would be built; (3) that inasmuch as the litigation terminated unfavorably to the Commissioners, and their contract to construct the court bouse was held to bo void, the contract here in issue became impossible of performance by operation of law, and appellant was thereby excused from performance ; (4) that the parties hereto, acting under the mutual mistake that the Commissioners had the right to contract for the construction of the court house and believing that the [615]*615litigation would be promptly terminated favorably to the construction, entered into the contract in suit which provided that the work contemplated should be done “as the progress of the building requires,’’ and that because of the adverse decision of the Supremo Court of Indiana, no work was required to be done oil the building. The ease was tried by the court without a jury, and judgment was rendered for appellee in the sum of $6,205.22, and from that judgment this appeal is prosecuted.

SPARKS, Circuit Judge

(after stating the facts as above).

Prior to September 6, 1927, the Commissioners and the County Council of Howard County had taken steps toward the erection of, a court house, and on that date a taxpayers’ injunction suit was instituted contesting their authority to erect the building. On December 14, 3 927, the contract for constructing the building was entered into by appellant and the Board of Commissioners. The taxpayers’ suit was afterwards beard, and the injunction was denied on March 10,1928. This decree was affirmed by the Appellate Court of Indiana on December 20, 1929, State ex rel. Kautz v. Commissioners of Howard County, 3 69 N. E. 364, but was later reversed by the Supreme Court of that state cut March 13, 1933,184 N. E. 780'.

On December 16, 1927, the instrument in. suit was executed by appellee’s assignor, the Robert Berner Structural Steel Company, referred to therein as the Sub-Contractor, and by appellant under the name of English Brothers, referred to therein as the Contractor. For a proper determination of the questions here presented it is necessary to consider only certain provisions of the contract which are set out in the margin.1 It was stipulated that appellee had not furnished appellant any material F.O.B. Indianapolis, or made shipment of any kind to appellant for the construction of the court house, and it is uncontroverted that while the old court house was demolished, there was no work done in constructing the new one, because of the result of the state litigation.

We are first confronted with appellee’s motion to dismiss the appeal, or in the alternative, to affirm the judgment, because the record presents no reviewablo question. This contention is based upon the assumed premise that the alleged errors upon which appel[616]*616lant seeks a reversal .merely tender questions of fact -which cannot be reviewed by this court. We cannot, however, accept the premise because the second, third and fourth special pleas involve the alleged erroneous interpretation of the contract; and the verified general denial and the first special plea present the question of the court’s alleged error in rejecting and failing to consider certain oral evidence calculated to prove non-delivery of the contract. These are pure questions of law which are properly raised.

It is contended by appellant with respect to his second, third and fourth special pleas, that the conditions under which the instrument in suit was made, or was to be performed, had wholly failed, whereby he was excused from performance. Aside from the conditions expressed in the contract he relies upon the following alleged implied conditions: (1) That the court house would be| constructed; (2') that it would be necessary to provide the materials and perform the work referred to in the contract; and (3) that the state litigation would terminate in the approval of the original contract to construct the building. Those implied conditions are alleged to arise out of Article VI which states that the sub-contractor shall complete the several portions, and the whole of the work, comprehended in the agreement “as progress of building requires.” He argues, therefore,' that on account of the destruction; of the subject matter of the original contract appellee became disabled from performing the subcontract, hence appellant was excused. He further insists that appellee and appellant entered into the subcontract under the mutual mistaken belief that the original contract was valid, where in fact, as a result of the state litigation, the subject matter of the subcontract never existed, hence there was no subcontract.

Appellant’s argument is obviously and exclusively based upon Article VI of the contract and the implication which might reasonably arise from the language there used. From that basis he assumes that appellee merely contracted to furnish such material and perform such services as would be required in the construction of the building, and the authorities upon which he relies are those which deal with such a contract. Typical of those cases are Higbie v. Rust, 211 Ill. 333, 71 N. E. 1010, 103 Am. St. Rep. 204; Joliet Bottling Co. v. Brewing Co., 254 111. 215, 98 N. E. 263; Minnesota Lumber Co. v. Whitebreast Coal C'o., 160 111. 85, 43 N. E. 774, 31 L. R. A. 529. But Article VI did not provide for the furnishing of anything. It only provided relatively when the steel work should be completed, that is to say, as the progress of the building required. Article I designated exactly what materials and labor should be furnished, and Article IX stated the consideration which was to be paid by appellant, and it was stated in the aggregate. There were no express conditions imposed and we find nothing in the contract which would warrant us in reading into it the implied conditions upon which appellant relies. The contract in this respect was quite improvident, but appellant had the right to make it, and if he chose not to protect himself by proper limitations he cannot now be heard to complain. He had limited himself to a definite time when the building should be completed, and as a protection to himself against that agreement he contracted with appellee to complete the steel work in such manner as not to delay the progress of the building. This in turn required appellee to have the steel ready when called for. It had to be fabricated, and that process manifestly required time, but the contract was silent as to when that should be done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ware v. Allen
128 U.S. 590 (Supreme Court, 1888)
Burke v. Dulaney
153 U.S. 228 (Supreme Court, 1894)
Guerini Stone Co. v. P. J. Carlin Construction Co.
240 U.S. 264 (Supreme Court, 1916)
State, Ex Rel. Kautz v. Bd., Etc., of Howard Co.
184 N.E. 780 (Indiana Supreme Court, 1933)
Wood v. Edison Electric Illuminating Co.
69 N.E. 364 (Massachusetts Supreme Judicial Court, 1904)
Higbie v. Rust
71 N.E. 1010 (Illinois Supreme Court, 1904)
Joliet Bottling Co. v. Joliet Citizens' Brewing Co.
98 N.E. 263 (Illinois Supreme Court, 1912)
Kilcoin v. Ortell
135 N.E. 16 (Illinois Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
71 F.2d 613, 1934 U.S. App. LEXIS 3155, Counsel Stack Legal Research, https://law.counselstack.com/opinion/english-v-hetherington-berner-inc-ca7-1934.