Engineered Structures, Inc. v. Travelers Property Casualty Company of America

CourtDistrict Court, D. Idaho
DecidedMay 28, 2021
Docket1:16-cv-00516
StatusUnknown

This text of Engineered Structures, Inc. v. Travelers Property Casualty Company of America (Engineered Structures, Inc. v. Travelers Property Casualty Company of America) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Engineered Structures, Inc. v. Travelers Property Casualty Company of America, (D. Idaho 2021).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO

ENGINEERED STRUCTURES, INC., a corporation of Idaho, an Idaho Case No. 1:16-cv-00516-CWD corporation, MEMORANDUM DECISION AND Plaintiff, ORDER

v.

TRAVELERS PROPERTY CASUALTY COMPANY OF AMERICA, a Connecticut corporation,

Defendant.

INTRODUCTION This case involves a dispute regarding the interpretation and application of a builder’s risk insurance policy issued by Travelers Property Casualty Company of America (“Travelers”) to Engineered Structures, Inc. (“ESI”). The parties filed cross-motions for summary judgment. (Dkt. 26, 30.) After a hearing, the Court entered a memorandum decision and order on June 18, 2018, granting in part and denying in part each motion. Both parties appealed. The matter is now before the Court upon remand. (Dkt. 61, 62.) To facilitate consideration of the limited issues on remand, the parties were given an opportunity to submit simultaneous briefs and replies thereto. Both parties availed

themselves of the opportunity to do so. (Dkt. 64 – 67.) Having fully reviewed the record and the parties’ briefing, the Court finds that oral argument would not significantly aid the decision-making process. Accordingly, the matter will be decided on the record before the Court without oral argument. Dist. Idaho L. Rule 7.1(d). BACKGROUND1 On September 29, 2014, ESI entered into a contract with Fred Meyer Stores, Inc.,

to build the Burlingame Fred Meyer Fuel Center in Multnomah County, Portland, Oregon, which was to be a new multi-island fueling station and associated retail space (the Project). The Contract called for installation of two underground storage tanks (“USTs”) for storage and sale of fuel in the anticipated Fred Meyer fueling station. One UST had a 20,000-gallon capacity designed to hold regular unleaded fuel, and the other

was a split 18,000-gallon tank designed to hold both premium and diesel fuel. A component of the Project involved installation of the Liquid Fuel Distribution & Electrical systems, a portion of which work included the installation of the two USTs. In mid-December of 2014, ESI and its subcontractors began the process of installing the two USTs on the Project. The project manual specified that the contractor deliver, handle and

install materials (including specifically the USTs) in accordance with the manufacturer’s

1 The Court is not asked to make further factual findings upon remand. The undisputed facts are well known to the Court and the parties, and therefore will not be repeated in full here. What follows is a brief recitation of the salient facts for consideration on remand, taken directly from the Court’s prior Memorandum Decision and Order. (Dkt. 46.) instructions. Xerxes manufactured the USTs, and the Xerxes Installation Manual set forth the sequential steps for their installation.

Between December 15 and 17, 2014, the two USTs were lowered into a shored excavation, seated into bedding material, strapped down via anchor straps to deadmen (reinforced concrete beams) on either side of the USTs, and partially backfilled with pea gravel, per the Xerxes manual. The backfill material was placed in the hole at least 75 percent of the way up the tank. The 20,000 gallon UST was about half filled with water as ballast (about 10,000 gallons) at that time. Post-installation testing, which included

soaping the fittings to ensure the UST could hold pressure, had not been completed. On December 23, 2014, it began to rain. On the morning of December 24, 2014, ESI discovered that the 20,000 gallon UST had displaced the surrounding soils and emerged from the excavation. Approximately 1.85 inches of rain had fallen over the period of time that the UST was placed in the ground to the time it floated. At that time,

the backfill was at least up to the top of the tank, and the UST was between stages; that is, the UST had been lowered into the excavation and partially backfilled, but it had not yet successfully undergone post-installation testing as required by the Xerxes Installation Manual. Also, the ballasting of the tank was incomplete. In other words, as of the date of loss, the tank installation was incomplete, as was the Project as a whole.

ESI incurred additional costs and expenses to re-excavate the hole and reinstall the UST in the excavated hole. On January 6, 2015, ESI submitted a claim under its builders’ risk policy with Travelers for the loss and associated Project repairs, including reinstallation of the UST and other resulting costs. Travelers denied the claim, relying upon the policy exclusion for faulty workmanship:

B. EXCLUSIONS * * * 4. We will not pay for loss or damage caused by or resulting from faulty, inadequate or defective: *** b. Design, specifications, workmanship, repair, construction, renovation, remodeling, grading or compaction; *** If an excluded cause of loss listed in Paragraph 4.a. through 4.d. above, results in a Covered Cause of Loss, we will pay for the resulting loss or damage caused by that Covered Cause of Loss. Travelers’ denial letter explained, in part: “The referenced Builders’ Risk policy does not cover the faulty, inadequate or defective-planning, workmanship or construction involved in properly installing the fuel tanks. After a thorough investigation it was determined that the subcontractor did not follow installation specifications from the fuel tank manufacturer relating to the amount of ballast to be used….” Both parties agree that ESI was required to follow the Xerxes manufacturer’s installation instructions for wet- hole installation of the USTs as set forth in the Xerxes Installation Manual. The Court found the Policy Exclusion was not applicable, and granted summary judgment to ESI on its breach of contract claim. The Court also granted summary judgment to Travelers on ESI’s bad faith claim. The United States Court of Appeals for the Ninth Circuit affirmed in part and reversed in part, and remanded the matter to the Court for further consideration. The Circuit affirmed the Court’s grant of summary judgment to Travelers, finding that ESI’s evidence was not enough to show more than the existence of a “legitimate question or difference of opinion over the eligibility, amount or value of the claim.” But, it reversed the Court’s grant of summary judgment to ESI on its breach of contract claim.

The Circuit found that the Court and the parties incorrectly focused previously on the term “workmanship” to find the Exclusion ambiguous and inapplicable, and failed to consider the Exclusion’s “unambiguous, process-oriented use” of the term “construction.” The Ninth Circuit construed the term “construction” in the Exclusion as a term referring to the “process of completing the project rather than a defect in the final product being built.” The Circuit directed the Court to resolve “whether ESI’s losses

were, in fact, ‘caused by or result[ed] from faulty, inadequate or defective . . . construction,’ thus making the Exclusion applicable.” Because the Ninth Circuit remanded for further proceedings regarding application of the Exclusion, it addressed also this Court’s references to the Policy’s provision on “resulting loss or damage.” The Circuit held that the “resulting loss or damage” provision

does not contain an anti-concurrent causation clause, so the Exclusion would not bar coverage for all of ESI’s damages if faulty construction was one factor among others causing the underground storage tank’s floatation. However, the Circuit found ESI’s argument that the resulting loss or damage provision would reinstate coverage for all damages other than the cost of additional ballast water needed to prevent floatation

untenable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher v. Garrison Property & Casualty Insurance Co.
395 P.3d 368 (Idaho Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Engineered Structures, Inc. v. Travelers Property Casualty Company of America, Counsel Stack Legal Research, https://law.counselstack.com/opinion/engineered-structures-inc-v-travelers-property-casualty-company-of-idd-2021.