Energrey Enterprises, Inc. v. Oak Creek Energy Systems, Inc. (In re Oak Creek Energy Farms, Ltd.)

107 B.R. 266, 1989 Bankr. LEXIS 2425
United States Bankruptcy Court, E.D. California·Decided June 9, 1989·No. Bankruptcy No. 187-00644-A-11; Adv. No. 187-0104·Published·Cited by 1 cases

Opinion

MEMORANDUM OPINION

RICHARD T. FORD, Bankruptcy Judge.

INTRODUCTION

ENERGREY ENTERPRISES, INC., Plaintiff, (hereinafter referred to as “EN-ERGREY”) initiated its original action in State Court. After OAK CREEK ENERGY SYSTEMS, INC. (hereinafter referred to as “SYSTEMS”) and OAK CREEK ENERGY FARMS, LTD. (hereinafter referred to as “FARMS”) filed their Petition for protection under Chapter 11 of the Bankruptcy Code, ENERGREY removed its State Court action to the Bankruptcy Court. Philip A. Gasteier and appeared as attorney for ENERGREY ENTERPRISES, INC.; Leslie A. Cohen and David A. Neale appeared as attorneys for the Trustee, Gary H. Goldstick. There was no appearance for DEAN BECKETT OR STEVE CUMMINGS, Defendants in this action. By agreement of counsel for ENERGREY and the Chapter 11 Trustee for SYSTEMS and FARMS, the second and third issue to be tried and argued are the amount of claim to be allowed in favor of ENER-GREY and whether or not there exists a Mechanic’s Lien on the alleged work of improvements, including the turbines. On April 3, 1989, 99 B.R. 36, a decision was given that ENERGREY’s Mechanic’s Lien on real property had been lost through foreclosure. Evidence was taken, briefs were submitted, and arguments were made before the Court, commencing at 10:00 a.m. on May 11, 1989.

FINDINGS OF FACT

1. OAK CREEK ENERGY FARMS, LTD. is a limited partnership composed of OAK CREEK ENERGY SYSTEMS, INC. as a general partner and DEAN BECKETT and STEVE CUMMINGS as limited partners.

2. OAK CREEK ENERGY SYSTEMS, INC. is a California corporation. The stock is owned by DEAN BECKETT and STEVE CUMMINGS.

3. For whatever reason, the above entities were formed, and assuming it to be a legal reason, they are two separate entities.

4. FARMS owned real property known as Oak Creek Farms. This real property is located in Tehachapi, California.

5. FARMS leased the subject real property to SYSTEMS.

6. ENERGREY contracted in writing with the Lessee of the real property, to wit: SYSTEMS, to build cement foundations for wind turbines.

[268]*2687. ENERGREY performed their contract, and SYSTEMS was billed approximately $1,200,000. They paid about $720,-000, leaving a balance of close to $483,-880.00, plus interest and attorney fees.

8. ENERGREY filed its notice claiming a Mechanic’s Lien against SYSTEMS’ property, filed their lawsuit to foreclose, filed an Amended Notice and Complaint to insert as a Defendant FARMS (the owner of the real property). At this point, the Mechanic’s Lien foreclosure action was transferred from State Court to Bankruptcy Court. The effect of the above facts is somewhat in dispute, but it is not necessary to decide these issues at this time.

9. Both FARMS and SYSTEMS filed a Chapter 11 Petition in the above-entitled court on February 24, 1987, a date prior to the above action being transferred from State Court to Bankruptcy Court.

10. The real property owned by FARMS was subject to a Deed of Trust eventually acquired by the Nottingham Group. The real property was subject to other liens, Deeds of Trust and the alleged lien of ENERGREY. For purposes of this decision, it will be assumed that ENERGREY’s Mechanic’s Lien against FARMS was perfected. (The Trustee claims that the lien was filed after 90 days from completion of the work. Energrey denies this allegation.)

11. At an early date in the bankruptcy proceedings, the Nottingham Group filed its Motion/Complaint for relief from the automatic stay so they could foreclose on the real property. ENERGREY objected. The hearing was continued several times, but eventually the Nottingham Group and the Debtor-in-Possession, SYSTEMS, entered into a stipulation approving the Court’s granting relief from stay. This action was consented to by the Creditors’ Committee (turbine owners) and others and was in contravention of the objection of ENERGREY. The Court then approved the stipulation. At this point in time, no Trustee had been appointed. SYSTEMS was acting as a Debtor-in-Possession pursuant to the Bankruptcy Code provisions that came into effect as a result of the Chapter 11 filings on February 24, 1987.

12. At some point in time it was agreed (except by ENERGREY) that, pursuant to the Power of Sale provisions in its Deed of Trust on the real property, the Nottingham Group would foreclose. They would then, by a separate document, lease the property to SYSTEMS, Debtor-in-Possession. The Lease also contained an option to purchase by the Debtor-in-Possession or its successor. The effect of the foreclosure, lease and option would be to cutoff the junior liens and mortgages, including ENER-GREY’S.

13. The foreclosure was accomplished and the Lease became effective. No one appeared at the foreclosure sale to overbid the Nottingham Group’s obligation although all parties, including ENERGREY, had prior notice of the foreclosure sale date and place.

14. Gary H. Goldstick was appointed Chapter 11 Trustee for FARMS and SYSTEMS on May 10, 1988.

15. The Court finds that ENERGREY did not contract with FARMS to place grout around the base of the towers covering the exposed portion of the bolts and threaded rods. As a result, the Court finds that the Trustee is not entitled to a set-off of $33,600.00.

16. The Court finds that it was the intent of the owners of the towers and related machinery to keep said property as personal property and not fixtures permanently attached to the real property.

17. The Court finds that the cement foundations installed by ENERGREY on FARMS’ land were fixtures attached to the real property.

DISCUSSION

The issues before the Court are here as a result of an agreement with both counsel, with the approval of the Court, and are as follows:

1. What is amount of the claim owing to ENERGREY? It is the understanding of the undersigned that arguments regarding amount and validity of pre- and post-petition interest and attorney fees will be reserved for further argument.

[269]*2692. Does ENERGREY’s Mechanic’s Lien attach to the foundations, towers, and other related items separate and apart from the real property?

As to the first issue, the Trustee does not dispute the claim of ENERGREY in an amount of $483,880.00. There is some dispute as to pre-petition interest, post-petition interest, and attorney fees, and that matter will be settled at a later date. The Trustee does allege that they are entitled to a set-off in the sum of $33,600.00. This figure represents the cost to grout 140 towers. As grounds for the set-off, the Trustee alleges that ENERGREY did not perform its contract, which by its terms incorporates plans and specifications prepared by Patrick and Henderson. Those plans and specifications provide in the notes for how the concrete foundations are to be constructed. The notes do not mention grout. The pictures above the notes on the plans, pages one and three, show that the exposed part of the bolts at the threaded rods should be grouted. Page five of Exhibit A does show in the drawing that the exposed bolt and threaded rods are to have a two inch cover of dry pack or grout to be completed after the towers are installed and the levelling and adjustments have been completed. The testimony of an owner and an employee of ENERGREY was that the principals of SYSTEMS did not require grouting, and that ENER-GREY was not to include a cost in their contract for grouting.

Free access — add to your briefcase to read the full text and ask questions with AI

Energrey Enterprises, Inc. v. Oak Creek Energy Systems, Inc. (In re Oak Creek Energy Farms, Ltd.), 107 B.R. 266, 1989 Bankr. LEXIS 2425 (Cal. 1989).

107 B.R. 266 (Energrey Enterprises, Inc. v. Oak Creek Energy Systems, Inc. (In re Oak Creek Energy Farms, Ltd.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related