Enable Midstream Partners, LP v. Louisiana Energy Gateway LLC

CourtLouisiana Court of Appeal
DecidedOctober 2, 2024
Docket55,916-CA
StatusPublished

This text of Enable Midstream Partners, LP v. Louisiana Energy Gateway LLC (Enable Midstream Partners, LP v. Louisiana Energy Gateway LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Enable Midstream Partners, LP v. Louisiana Energy Gateway LLC, (La. Ct. App. 2024).

Opinion

Judgment rendered October 2, 2024. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 55,916-CA

COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA

***** ENABLE MIDSTREAM Plaintiff-Appellee PARTNERS, LP

versus

LOUISIANA ENERGY Defendant-Appellant GATEWAY LLC

***** Appealed from the Forty-Second Judicial District Court for the Parish of DeSoto, Louisiana Trial Court No. 84,243

Honorable Amy Burford McCartney, Judge

*****

ETHAN P. ARBUCKLE Counsel for Appellant

PHELPS DUNBAR, LLP By: H. Alston Johnson, III Brad M. Boudreaux Kevin W. Welsh Stephen R. Vick, Jr. Anthony J. Gambino, Jr. Jordan P. Zeringue Nena M. Eddy

BRADLEY, MURCHISON, Counsel for Appellee, KELLY & SHEA, LLC Enable Midstream By: Kay Cowden Medlin Partners, LP Leland G. Horton Joshua S. Chevallier Ashley G. Gable LIZ MURRILL Counsel for Appellee, Louisiana Attorney General State of Louisiana

WARREN B. BATES, JR. Assistant Attorney General

GORDON, ARATA, MONTGOMERY, Counsel for Appellees, BARNETT, MCCOLLAM, DUPLANTIS American Petroleum Institute & EAGAN, LLC and Interstate Natural Gas By: Clinton P. Hayne, Jr. Association of America Scott A. O’Conner

CARVER, DARDEN, KORETZHY, Counsel for Appellee, TESSIER, FINN, BLOSSMAN & Louisiana Landowners AREAUX, LLC Association, Inc. By: Brandon T. Darden

Before COX, ROBINSON, and ELLENDER, JJ. COX, J.

This appeal arises out of DeSoto Parish, Louisiana. Louisiana Energy

Gateway, LLC (“LEG”) appeals a preliminary injunction granted in favor of

Enable Midstream Partners, LP (“Enable”). For the following reasons, we

reverse the trial court’s judgment.

FACTS

On July 24, 2023, Enable filed a petition for a temporary restraining

order, preliminary injunction, and permanent injunction to prevent LEG

from interfering “with its property rights and natural gas pipeline

operations[.]”

On February 26, 2010, Enable’s predecessor, CenterPoint Energy

Field Services, entered into a pipeline agreement with Dorothy and James

Ricks, which grants an “exclusive fifty foot (50’) wide” pipeline easement

on property in Section 1, Township 12 North, Range 13 West in DeSoto

Parish (“Enable Ricks Servitude”). CenterPoint’s successor in title, Enable,

operates a gathering pipeline on the Enable Ricks Servitude.

On April 1, 2023, LEG obtained their own servitude over the Ricks

property (“LEG Ricks Servitude”) intersecting the Enable Ricks Servitude.

Enable’s affiliate, Energy Transfer, LP (“ETC”) was contacted by

representatives of Williams Company on behalf of LEG requesting

assessment and consent to 42 proposed pipeline crossings on May 23, 2023.1

Each pipeline crossing involved various sizes of pipe and specifications

throughout DeSoto, Caddo, Beauregard, Sabine, and Vernon Parishes.

Enable alleged that it was given only 14 days to evaluate the proposed 42

1 LEG is a subsidiary of Williams Company. crossings and not given all the pertinent information. After numerous email

exchanges between the companies, Enable, through an email from Mark

Vedral, denied all crossings on June 30, 2023.

In its petition, Enable argued that the Enable Ricks Servitude is an

exclusive servitude, and it did not agree to allow any crossing of that

servitude. Enable stated that LEG intends to construct a 36-inch natural gas

pipeline that would cross the Enable Ricks Servitude. The trial court granted

the temporary restraining order.

Mark Vedral, the Senior Director of Land and Right of Way with

ETC, stated in his affidavit that Enable/ETC received a request for

assessment and consent of more than 40 pipeline crossings. The request was

received on May 23, 2023, with a requested response date of June 6, 2023.

He stated that complete details and documentation were not provided. Mr.

Vedral stated that after receiving inaccurate and incomplete information

from LEG, Enable informed LEG that it did not have permission to cross the

pipeline. He stated that LEG’s contractors were also informed that LEG did

not have permission to cross after receiving a Louisiana One Call notice.

Mr. Vedral is of the opinion that the Enable Ricks Servitude is exclusive.

He alleged “imminent safety and operational risk” and “immediate and

irreparable loss.”

LEG filed its answer, affirmative defenses, and reconventional

demand on September 6, 2023. LEG stated that the documents and written

communications are the best evidence of their content. LEG alleged that

Enable never identified the missing information and denied that it needed

Enable’s consent to cross the pipeline. LEG asserted the following

affirmative defenses: Enable’s petition fails to state a claim upon which 2 relief can be granted; LEG has complied with all laws to exercise its rights

on the property; Enable’s rights have not been and will not be adversely

affected; LEG has accommodated all of Enable’s rights; LEG pleads waiver,

release, estoppel, unclean hands, laches, and extinguishment of obligation;

LEG asserts all rights under any applicable servitude agreement; Enable

does not have a right to a TRO, preliminary, or permanent injunction; and

Enable’s servitude is an absolute nullity and against public policy.

LEG alleged that Enable has the right to construct one pipeline at a

maximum depth of six feet (four feet of cover plus two feet of pipeline

diameter), and it has already been installed. LEG stated that it would

maintain at least three feet of clearance under Enable’s servitude, a depth

where Enable has no rights. LEG stated that Mr. Vedral objected to all

crossings without explanation. LEG requested a preliminary injunction

against Enable’s action to block LEG’s pipeline, damages, attorney fees,

court costs, legal interest, and all other relief which may be equitable under

the circumstances.

A hearing on the preliminary injunction was held on September 20,

2023. Steven Futch testified that he is the vice president of interstate

engineering for ETC; Enable is a pipeline company owned by ETC; and he

is responsible for all project development and project execution for all

company pipelines. He stated that he has never received 42 proposed

pipeline crossings at once. When reviewing the request, Mr. Futch believed

that 42 crossings meant LEG would switch back and forth over the Enable

Pipeline and end up back on the same side. He stated the two-week

turnaround was not a normal request. Mr. Futch detailed ways in which a

pipeline crossing could pose obstacles in the future: the pipeline never leaves 3 because a hole or dirt settling would remain; maintenance is more difficult;

the inability to move the pipeline if there is a change in the surface usage;

and repeated need to coordinate between the pipeline companies. Mr. Futch

clarified that the Enable Ricks Servitude does not have a maximum depth

limitation, only a minimum depth of three or four feet depending on the

surface use.

On cross-examination, Mr. Futch disagreed with opposing counsel

regarding whether the LEG pipeline is a gathering pipeline and the

applicable federal laws. Counsel for LEG asked Mr. Futch to clarify that the

42 crossings were planned to cross not only pipelines owned by Enable but

also different pipelines. Mr. Futch stated that the crossings were of “all of

our assets,” which includes companies within the ETC/Enable family of

companies. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Louisiana Granite Yard, Inc. v. La Granite Countertops, L.L.C.
47 So. 3d 573 (Louisiana Court of Appeal, 2010)
Powertrain of Shreveport, L.L.C. v. Stephenson
149 So. 3d 1274 (Louisiana Court of Appeal, 2014)
Whitlock v. Fifth Louisiana District Levee Board
164 So. 3d 310 (Louisiana Court of Appeal, 2015)
Louisiana Granite Yard, Inc. v. LA Granite Countertops, L.L.C.
51 So. 3d 733 (Supreme Court of Louisiana, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Enable Midstream Partners, LP v. Louisiana Energy Gateway LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/enable-midstream-partners-lp-v-louisiana-energy-gateway-llc-lactapp-2024.