EMS USA, Inc. v. Epoxy Design Systems, Inc.

CourtCourt of Appeals of Texas
DecidedApril 24, 2012
Docket14-10-01037-CV
StatusPublished

This text of EMS USA, Inc. v. Epoxy Design Systems, Inc. (EMS USA, Inc. v. Epoxy Design Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EMS USA, Inc. v. Epoxy Design Systems, Inc., (Tex. Ct. App. 2012).

Opinion

Affirmed and Memorandum Opinion filed April 24, 2012.

In The

Fourteenth Court of Appeals

NO. 14-10-01037-CV

EMS USA, INC., Appellant

V.

EPOXY DESIGN SYSTEMS, INC., Appellee

On Appeal from the 311th District Court Harris County, Texas Trial Court Cause No. 2009-05057

MEMORANDUM OPINION A subcontractor sued a general contractor seeking to recover unpaid sums allegedly owing under the parties’ contract. The jury found that the parties agreed to be bound by certain contract provisions. The trial court concluded that these provisions were unambiguous and rendered judgment based upon the jury’s verdict and the trial court’s interpretation of these provisions. On appeal, the subcontractor asserts that the trial court erred in its interpretation of these provisions and in its failure to render judgment in favor of the subcontractor based upon the subcontractor’s interpretation of these provisions. Concluding that the subcontractor failed to preserve error as to one issue and failed to adequately brief the other, we affirm the trial court’s judgment. I. FACTUAL AND PROCEDURAL BACKGROUND

Appellant/plaintiff EMS USA, Inc. sued appellee/defendant Epoxy Design Systems, Inc. seeking to recover more than $300,000 that Epoxy failed to pay EMS allegedly in breach of Epoxy’s contract with EMS. In the alternative, EMS sought to recover under a quantum-meruit theory. Epoxy filed a counterclaim seeking declaratory relief.

Under the contract in question, EMS, as subcontractor, performed services that Epoxy was obligated to perform under a contract with Equistar Chemicals, LP, the owner of the plant where the services were performed. EMS performed the services and invoiced Epoxy, and Epoxy invoiced Equistar under Epoxy’s contract with Equistar. Before Equistar made all payments required under its contract with Epoxy, Equistar filed for bankruptcy protection. Epoxy took the position that it had no obligation to pay EMS for EMS’s services until Epoxy received payment from Equistar. EMS took the position that, under its contract with EMS, Epoxy was required to pay EMS for its services regardless of whether Equistar paid Epoxy for the services.

The case was tried to a jury. EMS presented evidence that (1) its contract with Epoxy was governed by terms and conditions contained in an August 5, 2008 letter (the “Terms and Conditions”) and (2) EMS and Epoxy agreed that Epoxy would pay EMS for its services regardless of whether Equistar paid Epoxy for the services. Epoxy presented evidence that (1) the parties did not agree to be bound by the Terms and Conditions; (2) the parties agreed to be bound by the provisions of a Subcontract Agreement sent by EMS to Epoxy on August 6, 2008 (the “Subcontract”); (3) under the Subcontract, Epoxy had no obligation to pay EMS for EMS’s services until Epoxy received payment from Equistar; and (4) as of the time of trial, Equistar had not paid Epoxy for the services that formed the basis of EMS’s suit against Epoxy.

During the charge conference, the trial court stated that if the jury were to find that the parties agreed Epoxy would pay EMS for its services regardless of whether Equistar paid Epoxy for the services performed by EMS, then there would be no need to submit a

2 question on breach of contract or damages because breach and damages in the amount of $200,621.14 had been proved as a matter of law. Thus, the trial court instructed that if the jury found such an agreement, then the jury was to answer a question as to whether EMS could recover an additional $109,663.35 under a quantum-meruit theory. The trial court further instructed the jury that, if the jury did not find such an agreement, the jury was not to answer this question.

The jury unanimously found that (1) EMS failed to prove by a preponderance of the evidence that the parties agreed Epoxy would pay EMS for its services regardless of whether Equistar paid Epoxy for the services performed by EMS and (2) the parties agreed to be bound by the provisions of the Subcontract. Under the trial court’s charge, these were the only two findings that the jury was required to make, and the jury obeyed the trial court’s instructions not to answer any of the quantum-meruit questions.

Epoxy submitted to the trial court a proposed judgment on the jury’s verdict. In response, EMS filed a motion requesting that the trial court not grant the relief provided in the judgment proposed by Epoxy. The trial court rendered judgment in favor of Epoxy, concluding that, under the unambiguous language of the Subcontract, Epoxy is only obligated to pay EMS when Epoxy receives payment from Equistar and that Equistar had not paid Epoxy. The trial court ordered that EMS take nothing by way of its claims. The trial court declared that, under the unambiguous language of the Subcontract, (1) Epoxy is not required to pay EMS until Epoxy receives payment from Equistar; and (2) EMS is only entitled to payment for the amount Epoxy actually receives from Equistar up to $310,284.49, the total amount of the invoices for the work EMS provided to Equistar. The trial court did not award attorney’s fees to either party.

After the trial court rendered judgment, EMS did not ask the trial court to modify, correct, or reform its judgment. EMS timely filed a motion for new trial, which was overruled by operation of law.

3 II. ISSUES PRESENTED

EMS presents two appellate issues. First, EMS asserts that the trial court erred as a matter of law in its interpretation of the unambiguous Subcontract. In its second issue, EMS asserts that, as a result of its erroneous interpretation of the Subcontract, the trial court erred in granting a take-nothing judgment in favor of Epoxy and that instead the trial court should have granted a judgment in favor of EMS in a sum equal to $200,621.14, plus attorney’s fees, interest, and court costs.1

III. ANALYSIS

A. Did the subcontractor preserve error as to its argument that the trial court erred by failing to render judgment in the subcontractor’s favor? EMS argues that, under the unambiguous language of the Subcontract, Epoxy is obligated to pay EMS within a reasonable time after EMS performed its services, and that Epoxy’s obligation to pay is not conditioned upon its receipt of any payment from Equistar. EMS cites cases supporting the proposition that, to shift the risk of the owner’s insolvency from the general contractor to the subcontractor, the subcontract must contain an express condition clearly showing that the parties intended to shift this risk to the subcontractor. See Sheldon L. Pollack Corp. v. Falcon Indus., Inc., 794 S.W.2d 380, 384 (Tex. App.—Corpus Christi 1990, writ denied). EMS argues that the Subcontract does not contain such language and therefore the parties did not agree to shift the risk of Equistar’s insolvency from Epoxy to EMS. On appeal, EMS effectively argues that, under the unambiguous language of the Subcontract, the trial evidence proves as a matter of law that Epoxy breached its contract with EMS and that $200,621.14 in actual damages resulted from this breach. EMS argues that the trial court erred by failing to render judgment in EMS’s favor for the $200,621.14 in contract damages, the amounts of reasonable and necessary attorney’s fees to which the parties stipulated during trial,

1 In the alternative, EMS requests that this court reverse and remand for a new trial “for the reasons stated in this appeal.”

4 interest, and court costs.2 To have preserved error, EMS must have raised this appellate complaint in the trial court. See Tucker v. Thomas, No. 14-09-01081-CV, —S.W.3d— ,—, 2011 WL 6644710, at *14–15 (Tex. App.—Houston [14th Dist.] Dec. 20, 2011, pet. filed) (en banc).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Environmental Procedures, Inc. v. Guidry
282 S.W.3d 602 (Court of Appeals of Texas, 2009)
San Saba Energy, L.P. v. Crawford
171 S.W.3d 323 (Court of Appeals of Texas, 2005)
Weinberger v. Longer
222 S.W.3d 557 (Court of Appeals of Texas, 2007)
Gammill v. Fettner
297 S.W.3d 792 (Court of Appeals of Texas, 2009)
Sheldon L. Pollack Corp. v. Falcon Industries, Inc.
794 S.W.2d 380 (Court of Appeals of Texas, 1990)
Rosscer Craig Tucker, II v. Lizabeth Thomas
405 S.W.3d 694 (Court of Appeals of Texas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
EMS USA, Inc. v. Epoxy Design Systems, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ems-usa-inc-v-epoxy-design-systems-inc-texapp-2012.