Empire South, Inc. v. Repp

756 P.2d 745, 51 Wash. App. 868
CourtCourt of Appeals of Washington
DecidedJune 28, 1988
Docket8458-2-III
StatusPublished
Cited by3 cases

This text of 756 P.2d 745 (Empire South, Inc. v. Repp) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire South, Inc. v. Repp, 756 P.2d 745, 51 Wash. App. 868 (Wash. Ct. App. 1988).

Opinion

McInturff, C.J.

Mr. and Mrs. William Repp and their son, Steven Repp, appeal a judgment entered against them following their alleged default on a promissory note and a retail installment sales contract. They had signed the note and the contract in connection with their purchase of a used 1976 Allis-Chalmers MH2 combine from Empire South's business predecessor. At issue is whether the Superior Court erred when (1) it employed an objective standard to determine if Empire South had fulfilled its warranty *870 that the combine would run to the Repps' satisfaction, and (2) it awarded a deficiency judgment against the Repps.

In July 1981, Steven Repp and his father went to McSweeney Tractor Company, a Colfax farm equipment dealer, for the purpose of renting a combine to use to harvest their wheat and barley crops. After discussion with Allen McSweeney, the Repps decided instead to purchase a used combine which at that time was disassembled in McSweeney's shop. The Repps inspected the disassembled machine, and Mr. McSweeney promised to get it field ready and that if something did not work, he would make it work. At some point, he made the statement that he would get it working to the Repps' satisfaction.

The purchase price of the combine, including tax, was $57,750. The down payment of $17,750 was paid $1,000 in cash and $16,750 by a promissory note due on July 1, 1986, signed by Steven and cosigned by his father. The Repps also signed a retail installment sales contract in those same capacities which provided the remaining balance, including interest, was to be paid in four annual installments of $14,378, beginning July 1,1982.

The Repps experienced problems with the combine during the 1981 harvest which began August 10 and was completed on August 31. The court's findings of fact 4, 5 and 6, to which the Repps do not assign error, summarize these problems:

4. . . . Beginning August 8, 1981, the Repps experienced some problems with the machine. On August 8, 1981, Mr. Repp rewired the separator clutch. On August 9, 1981, he put on a new header drive belt and completed adjustments on August 11, 1981.
5. On August 17, 1981, the alternator went out and McSweeney Tractors sent out it's chief mechanic to replace it at no cost to the Repps. On August 19, 1981, the straw walker went out and McSweeneys dispatched another mechanic to the Repp field to fix the straw walker and to work on a hydraulic accumulator. On August 20 the shaker pan needed work and a mechanic came. On August 21 a mechanic came and worked on the *871 walker drive and replaced rubber blocks, straw walker blocks, new adjusting rod, spring, belts and idler on hydraulic drive. Later on August 24, 1981, rubber blocks and casting for sieves were replaced. On August 23 and 24 a sieve holding rod was replaced. On August 25, 1981, the Repps experienced some leveling problems and Mr. McSweeney's mechanic again came and fixed the problem. On August 28, 1981, the mechanic again came to the Repp field and fixed a broken sieve rod. On August 29, 1981, McSweeney replaced the walker pan and patched the shoe. Since the shoe is an important part of a combine and there was some question as to whether or not the patch would hold, McSweeneys ordered a replacement shoe and made arrangements to put it on the combine some time before the next harvest season.
6. All of the services performed by McSweeney Tractor Company in 1981 were done at no cost to the Repps for either parts or service. Although there were several problems which occurred during the three week 1981 harvest season, many of them — belts, adjustments, blocks, and castings — are maintenance problems. These are the types of problems that a combine operator might expect to run into periodically during a harvest season. Other problems were unpredictable, such as the alternator going out, the shoe cracking, and the sieve rod breaking. These can and do occur periodically in used machinery.

At the end of the 1981 harvest, William Repp called Allen McSweeney and told him to come get the machine. According to Mr. Repp, he did not expect a reconditioned machine to exhibit the number of problems they in fact experienced with the combine. However, Mr. McSweeney convinced him to give the dealership another chance to make the combine work.

Prior to the due date of the July 1, 1982, installment payment, the Repps negotiated an extension agreement with Empire South, the company which had purchased the McSweeney dealership in October 1981. The agreement extended the payment date to November 1, 1982, in exchange for a $2,000 partial payment and a payment of $825 in extension fees representing interest on the remaining amount from July until November.

*872 Finding of fact 10, to which no error is assigned, summarizes the Repps' problems with the combine in the 1982 harvest season:

10. . . . The 1982 harvest started on August 10. Several days of the first week of harvest were rainy and little harvesting was done on those days. On August 10, 1982, [the Repps] replaced straw chopper bearings, and on August 11, 1982, Defendants put new guards on the combine. On August 16, 1982, a hose burst. On August 17, 1982, the replacement hose burst. On that date Steven Repp told Mr. Conger of Empire South that the hose had burst on several prior occasions, and that he wanted Mr. Conger to come out and take the machine back.

Instead, Mr. Conger and a mechanic worked on the combine, and Mr. Conger operated it for about a half a day in the field on August 19. The Repps refused to use it after August 19, citing their fear that the machine was unsafe and might tip over. Steven Repp said that when the hose burst the last time, he was working on a hillside and the leveling device stopped. This frightened him, and he never got on the machine again.

Bill Conger stated the Repps never said anything to him about returning the machine until August 17 when they experienced the leveling problem. He further stated this problem was due to worn O-rings. He replaced the O-rings the next day, and he testified the action solved the problem.

Mr. Conger repossessed the machine in September 1982. He placed it on his lot, and offered it to several people who were looking for combines during the fall of 1982. However, it was not until January 1983 that he received the paperwork from the Allis-Chalmers Credit Corporation clearing title so he could advertise the combine for auction. The Repps asked him to wait 30 days before scheduling a public sale, and he complied with their request. No one appeared to bid at the first sale date of April 15. On May 17, 1983, Empire South bought the combine for $33,000, which Mr. Conger states was the high end of the wholesale price *873 range. The only other bid at the sale was for $15,000. Empire South sold the machine in July 1983 for $35,000.

Mr. Conger said the price of used equipment went down drastically between the fall of 1982 and when the combine was sold. In August 1982, the combine was equal in value to its value on the day it was originally purchased by the Repps, less 125 hours of wear and 2 years of depreciation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R & J of Tennessee, Inc. v. Blankenship-Melton Real Estate, Inc.
166 S.W.3d 195 (Court of Appeals of Tennessee, 2004)
McChord Credit Union v. Parrish
809 P.2d 759 (Court of Appeals of Washington, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
756 P.2d 745, 51 Wash. App. 868, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-south-inc-v-repp-washctapp-1988.