Empire Lath & Plaster, Inc. v. American Casualty Co. of Reading

847 P.2d 276, 256 Mont. 413, 50 State Rptr. 128, 1993 Mont. LEXIS 30
CourtMontana Supreme Court
DecidedFebruary 11, 1993
Docket92-090
StatusPublished
Cited by10 cases

This text of 847 P.2d 276 (Empire Lath & Plaster, Inc. v. American Casualty Co. of Reading) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire Lath & Plaster, Inc. v. American Casualty Co. of Reading, 847 P.2d 276, 256 Mont. 413, 50 State Rptr. 128, 1993 Mont. LEXIS 30 (Mo. 1993).

Opinion

JUSTICE TRIEWEILER

delivered the Opinion of the Court.

Defendant American Casualty Company of Reading, Pennsylvania (American Casualty), appeals from a default judgment of $58,049.40, entered in favor of Empire Lath & Plaster, Inc. (Empire) on November 6, 1991, in the Thirteenth Judicial District Court, Yellowstone County. American Casualty’s subsequent motion to set aside the judgment was deemed denied pursuant to Rule 60(c), M.R.Civ.P., when the District Court failed to rule on the motion within 45 days.

We affirm.

The sole issue for our consideration is whether the District Court abused its discretion when it did not grant American Casualty’s motion to set aside the default judgment.

This litigation arises out of a construction contract associated with the building of the Billings Parking Garage and City Hall Expansion Project. In April 1990, the City of Billings awarded the general contract for the construction project to C & D Contractors, Inc. (CD), and CD thereafter subcontracted a portion of the project to Empire. In connection with the general contract, a bond in excess of $3 million was executed by American Casualty to guarantee payment to subcontractors for labor, material, and equipment supplied during the construction project.

Empire completed its portion of the work on April 16, 1991, and submitted its final billing statement to CD which reflected an unpaid balance due Empire totalling $47,124.96. In addition to the amount owed under the subcontract, Empire had performed a “change order” for the project which had been authorized by CD and approved by the project architect, at a cost of $1,200.00.

At the same time Empire submitted its final statement, CD sent a letter to Empire confirming the outstanding balance due under the contract, but asserting that Empire had failed to “diligently pursue its work in a timely manner.” CD claimed this failure to properly perform under the contract delayed the entire project and resulted in significant additional costs to CD. No further facts nor specifics were ever provided to Empire in regard to the alleged contract breach.

*415 After computing the costs which it alleged were a result of Empire’s delay, CD determined it would withhold $31,576.00, and tendered a check to Empire for $15,548.96. The check contained a restrictive endorsement which provided that Empire’s endorsement would acknowledge final and conclusive payment for all work performed, and would release CD from any further liability under the subcontract. Empire refused to execute the check due to the restrictions, and insisted on either full payment, or payment of the uncontested sum of $15,548.96, with an understanding that the parties would attempt to resolve the dispute over the remaining amount.

Empire received no payments from CD, and on July 2, 1991, Empire submitted a notice to the City of Billings, CD, and American Casualty (as the surety for the project), stating that it had a claim of $47,124.96 against the bond for the work performed under the subcontract, and also for the $1,200.00 incurred for the change order. Empire received no response from either CD or American Casualty regarding the claim notice.

On August 14, 1991, Empire filed a complaint in District Court against American Casualty in order to collect the outstanding balance owed to Empire which was guaranteed by the bond. This civil action was filed in Yellowstone County as required by provisions contained in the bond; CD was not named as a defendant in the case because the subcontract between CD and Empire required venue in Lewis and Clark County. The summons and complaint were served on American Casualty’s legal department on August 23, 1991.

The Claims Analyst for American Casualty immediately forwarded the summons and complaint to CD, along with a letter tendering the defense of the action to CD as was apparently standard practice. Although American Casualty was in communication with CD on other matters, Empire’s pending lawsuit was never discussed, and CD asserts that it had no knowledge of the action nor ever received American Casualty’s letter tendering the defense of the action to CD.

The District Court, based on an affidavit from the supervising architect of the construction project, found that Empire had fully and competently performed the requirements of the subcontract in a timely manner, and that there was no basis to withhold full payment to Empire. The court concluded that Empire had complied with all conditions required by the bond, and was, therefore, entitled to recover from American Casualty under the bond. The court entered a default judgment against American Casualty on November 6,1991, for $58,049.40, which represented the contract amount due Empire, *416 plus interest, the $1,200.00 incident to the change order, and attorney fees and costs of $170.39.

The following day, American Casualty discovered that the default judgment had been entered and that no appearance had been made by CD on behalf of the surety. On November 14, 1991, American Casualty moved to set aside the default judgment, filed its answer to the complaint, and requested a trial on the merits. The District Court did not rule on the motion within 45 days from the time it was filed, and the motion was, therefore, deemed denied pursuant to Rule 60(c), M.R.Civ.P. From this denial of the motion to set aside the default judgment, American Casualty appeals.

The issue presented is whether the District Court abused its discretion when it did not set aside the default judgment. American Casualty argues that the court should have granted relief from the judgment under Rule 55(c), M.R.Civ.P., which allows for the setting aside of a default judgment:

For good cause shown the court may set aside an entry of default and, if a judgment by default has been entered, may likewise set it aside in accordance with Rule 60(b).

Rule 60(b), M.R.Civ.P., states in pertinent part:

On motion and upon such terms as are just, the court may relieve a party or a party’s legal representative from a final judgment, order, or proceeding for the following reasons: (1) mistake, inadvertence, surprise, or excusable neglect... or (6) any other reason justifying relief from the operation of the judgment.

Where a trial court fails to grant a motion to set aside a default judgment, the finding of even a slight abuse of discretion is sufficient to justify reversal of such an order. Board of Directors Edelweiss Owners’ Assn. v. McIntosh (1991), 251 Mont. 144, 822 P.2d 1080. In Lords v. Newman (1984), 212 Mont. 359, 363, 688 P.2d 290, 293, we emphasized two basic tenets to be considered in setting aside default judgments: (1) every litigated case should be tried on its merits and judgments by default are not favored; and (2) trial courts have a certain amount of discretion when considering a motion to set aside a default judgment. We have also clearly stated that the burden of proof rests on the party seeking to set aside the default judgment. Siewing v. Pearson Co. (1987), 226 Mont.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Claire Pesarik v. Gabriel Perjessy
2008 MT 337 (Montana Supreme Court, 2008)
Essex Insurance v. Moose's Saloon, Inc.
2007 MT 202 (Montana Supreme Court, 2007)
In Re the Marriage of Shannon
2004 MT 25 (Montana Supreme Court, 2004)
In Re Marriage of Winckler
2000 MT 116 (Montana Supreme Court, 2000)
Spartan Manufacturing v. Melton
1998 MT 60N (Montana Supreme Court, 1998)
Falcon v. Faulkner
903 P.2d 197 (Montana Supreme Court, 1995)
Kenner v. Moran
868 P.2d 620 (Montana Supreme Court, 1994)
In Re the Marriage of McDonald
863 P.2d 401 (Montana Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
847 P.2d 276, 256 Mont. 413, 50 State Rptr. 128, 1993 Mont. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-lath-plaster-inc-v-american-casualty-co-of-reading-mont-1993.