Empire Construction Co. v. Crawford

57 Colo. 281
CourtSupreme Court of Colorado
DecidedApril 15, 1914
DocketNo. 7391
StatusPublished
Cited by4 cases

This text of 57 Colo. 281 (Empire Construction Co. v. Crawford) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire Construction Co. v. Crawford, 57 Colo. 281 (Colo. 1914).

Opinion

Mr. Justice Hill

delivered the opinion of the court:

This action was instituted upon February 3, 1908, by J. F. and James D. Mowry, copartners, subcontractors, against W. H. Crawford as the original contractor, The Montezuma Valley Irrigation District and The Empire Construction Company as owners, or having an interest in certain canals, reservoirs, etc.-, and against sundry other persons, who were alleged to be subcontractors, materialmen, etc., under the original contractor, Crawford. The purpose of the suit was to secure a judgment against Crawford for services rendered and materials furnished upon, and used in, the construction of the canal and reservoirs, to have the rights of all parties determined, to have a lien upon these properties, foreclosure accordingly, etc. Numerous subcontractors and alleged lien claimants filed answers and cross complaints. On February 29th, Crawford filed a motion to make the complaint more definite. On March 9th this motion was heard, at which time Crawford was represented by attorneys Wheeler and Weiser. The motion was overruled, and he was given until March 16th to answer. On March 9th The Empire Construction Company filed its answer to the complaint, and answers to the cross complaints of- sundry subcontractors. On March 12th the irrigation district filed its answer to the complaint, alleging its ownership of the property; that it was a public corporation, to-wit, an irrigation district, etc., upon account of which its property was not subject to mechanics’ liens, etc. On March 16th the defendant Crawford filed his answer and cross complaint, in which he sets forth an alleged cause of action against The Empire Construction Company for work done and [284]*284materials furnished on these properties, etc., his liens, etc. He prayed for judgment against that company for Etbout $30,000, and that it be decreed a lien, for foreclosure, etc. On March 18th the district filed its answer to his, in which, among other things, it set forth its public character account of which its property was not subject to liens, etc. On March 21st The Empire Construction Company filed its answer and cross complaint to the cross complaint of the defendant Crawford, wherein it denied liability to him, and set forth an alleged cause of action against him for damages growing out of his failure to comply with the provisions of his two contracts with it, etc. It prayed for judgment against him for $30,000, etc. Thereafter, the defendant Crawford filed sundry answers to the cross complaints of sundry subcontractors, motions to make more definite, etc. These were thereafter overruled. On April 23rd the defendant Crawford filed his replication to the answér and cross complaint of The Empire Construction Company. Sundry other pleadings and court’s orders pertaining thereto followed, among which, upon May 4th, was a motion by the defendant Crawford for a continuance until the next term of court, account of the alleged absence of witnesses, and the inability of his attorneys to be present. This motion upon said date, was overruled, and the court proceeded to trial, which consumed part, if not all, of May 4th, 5th, 6th and 7th, 1908; upon which last date decree was entered, which among other things recites “The defendant, W. H. Crawford, appearing by his attorneys Wheeler and Weiser,” also, “Wheeler and Weiser filed a motion for the continuance of this cause for and on behalf of the defendant, W. H. Crawford, which motion was by the court overruled.”

The decree sets forth, that Crawford entered upon the construction and completion of the canals and reservoirs in question under two contracts with The Empire Construction Company; that in violation thereof he abandoned the work before completion; that at the time of this abandonment there was due him from the con[285]*285struction company under these contracts $7,415.02, which money was subject to the liens of the subcontractors ; that the property on which the work was done was impressed with the character of public property, and was not subject to liens, in so far as the title of the district was concerned, but that the money owing Crawford by the construction company grew out of, and was derived from, said property and should be held for the payment of the liens; that Crawford violated his contracts, etc., and was not entitled to recover on his cross complaints and should take nothing; that The Empire Construction Company had been damaged in the sum of $10,000 account of Crawford failing to comply with his contracts, and is entitled to have judgment against him for this amount.

The claims of about thirty subcontractors were established in the decree against Crawford, and fixed at certain amounts. Individual judgments against Crawford for these sundry amounts were inserted and decreed to be liens against the moneys in the hands of the construction company found to be owing Crawford. The decree recites that within ten days from its date The Empire Construction Company pay to the clerk the balance found due on the contracts, viz, $7,415.02, on which liens were established, etc., upon its failure so to do that judgment be entered against it for this amount as of the date of the decree; that upon the payment of this sum to the clerk, the construction company be released and discharged from all further liability upon account thereof; that upon receipt of this money the clerk pay, first, the costs of suit, second, all liens established as first-class, third, fifty-three per cent upon all liens established as second-class, and retain the balance subject to the further order of the court; that the amount of said payments be credited upon the judgments against Crawford; that as to defendants, Graham, Morrison and Brimhall, the hearing be continued until the next term. The decree also contains a judgment against Crawford, in favor of the construction company as follows, “That [286]*286the defendant, The Empire Construction Company, have and recover of the defendant W. H. Crawford, the sum of $10,000 for which judgment is hereby rendered and let execution issue therefor.”

An appeal appears to have been allowed the defendant Crawford from this decree, amount of bond fixed, and time given for bill of exceptions, but nothing done thereunder. Upon May 17th following, the money found to be due from the construction company to Crawford was paid into court, in compliance with the terms of the decree, and it appears to have been disposed of as ordered without any exception or objection being made thereto.

Upon May 17th, 1909, at a subsequent term of court and over a year after the date of the decree, and more than six months after the adjournment of the term at which it was rendered, the defendant Crawford filed a motion to set it aside, alleging as his reasons that through misfortune and unusual hardships he was unable to be present at the trial, by himself or counsel; that both he and his attorneys were taken by surprise, and that any seeming neglect on the part of either was excusable; that the cause was not properly at issue; that a part of it was left over, and the case not fully determined; that no final judgment had been entered from which the defendant could take an appeal; that the decree was tentative only, and subject to be annulled by further action of the court; that the judgment and decree was void; that the. court had no jurisdiction of the subject matter, etc.; that he was unable to apply for relief during the term at which the decree was entered and makes this application at the first opportunity, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Miller
271 P.2d 411 (Supreme Court of Colorado, 1954)
Monte Vista Potato Grower's Co-Operative Ass'n v. Bond
252 P. 813 (Supreme Court of Colorado, 1927)
Wharton v. Devinna
246 P. 279 (Supreme Court of Colorado, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
57 Colo. 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-construction-co-v-crawford-colo-1914.