Empire Bucket, Inc. v. Contractors Cargo Company

739 F.3d 1068, 2014 WL 128708, 2014 U.S. App. LEXIS 1958
CourtCourt of Appeals for the Seventh Circuit
DecidedJanuary 15, 2014
Docket13-2452
StatusPublished
Cited by9 cases

This text of 739 F.3d 1068 (Empire Bucket, Inc. v. Contractors Cargo Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire Bucket, Inc. v. Contractors Cargo Company, 739 F.3d 1068, 2014 WL 128708, 2014 U.S. App. LEXIS 1958 (7th Cir. 2014).

Opinion

MANION, Circuit Judge.

Contractors Cargo Company engaged Empire Bucket, Inc., to fabricate a steel railcar deck. After the deck fractured, Contractors Cargo refused to pay the full purchase price and Empire Bucket sued for breach of the contract. Contractors Cargo countersued for breaches of the contract, the implied warranty of merchantability, and the implied warranty of fitness for a particular purpose. Prior to trial, the district court granted Empire Bucket’s motion in limine to exclude any testimony concerning one of the tests performed on the deck after it failed. The jury returned a verdict for Empire Bucket. Contractors Cargo appeals. We affirm.

I. Facts

Contractors Cargo Company, a transportation business engaged in heavy-haul operations throughout the United States, commissioned Empire Bucket, Inc., to fabricate a steel railcar deck to be used with Contractors Cargo’s Schnabel railcar — a specialized railroad freight car for transporting heavy and oversized loads. Contractors Cargo hired a third to design the deck. The designs specified that the deck be fabricated from T-l high-strength steel and that the welding be performed pursuant to American Welding Society specifications. The deck was designed to attach to the Schnabel car and to transport up to an 800,000-pound load. Empire Bucket fabricated the deck, which passed inspection by an outside agency and all nondestructive tests, and delivered it. Contractors Cargo *1070 connected the deck to its Schnabel railcar and loaded it to approximately 820,000 pounds. The next morning, an employee observed that the deck had dropped about three inches overnight. Contractors Cargo attempted to raise the deck with a hydraulic jacking system, but the deck fractured during the attempt.

Contractors Cargo hired a metallurgical engineer, Josh Schwantes, to determine why the deck had fractured. Schwantes determined that the deck contained an inclusion — which in this case meant a portion of the weld was composed of material with properties different from the properties of the material in the rest of the weld. The inclusion was approximately l/10th of an inch in length at the location where the crack originated. Schwantes also performed various tests on the deck, including a “Charpy v-notch impact test.” This test showed that the material around the inclusion had low fracture toughness, which meant that the weld material was more brittle than expected. The deck passed all other nondestructive and destructive tests for the purposes of satisfying American Welding Society specifications. 1

Based on this testing, Contractors’ Cargo concluded that the deck failed because Empire Bucket did not properly fabricate it. Thus, Contractors Cargo refused to pay Empire Bucket the full purchase price. Empire Bucket sued in Wisconsin state court for breach of contract. Contractors Cargo removed the action to federal district court and filed various counterclaims, including claims for breaches of the contract, the implied warranty of merchantability, and the implied warranty of fitness for a particular purpose.

Prior to trial, Empire Bucket filed a number of motions in limine, including a motion to exclude any testimony regarding the Charpy impact test performed on the deck. American Welding Society standards provide that if a project is to be welded to Charpy toughness criteria, that criteria must be specified in the contract documents. Thus, Empire Bucket argued, the Charpy impact test was irrelevant because the parties’ contract did not specify any Charpy toughness criteria. The district court directed Contractors Cargo to proffer its proposed testimony regarding the Charpy impact test and its relevance to Contractors Cargo’s claims.

Contractors Cargo explained that it did not intend to offer testimony regarding the Charpy impact test performed on the deck for the purpose of demonstrating that the parties’ contract required the deck to pass such testing. (Indeed, Contractors Cargo stipulated that the contract did not require the deck to satisfy any Charpy toughness criteria.) Rather, Contractors Cargo stated that it intended to offer testimony concerning the Charpy impact testing to establish that the weld material at the location of the inclusion had low fracture toughness (that is, that it was unusually brittle). And the test indicating brittleness supported Contractors Cargo’s experts’ conclusion that the weld containing the inclusion was the cause and origin of the deck’s failure, which in turn supported the implied warranty claims.

In ruling on Empire Bucket’s motion in limine, the district court focused almost entirely upon Contractors Cargo’s breach of contract claim. The district court remarked that there “may be a better case for admitting ... testimony about the cause of the deck failure for the purposes of discussing a breach of implied warranty theory, as the actual performance of the deck might then be relevant to whether it was adequate for the general or specific purposes for which it was built.” None *1071 theless, the district court observed that “the liability question at issue in this case is not whether or why the deck failed, but whether the deck satisfied the terms of the contract.” The district court concluded that the testimony regarding the Charpy impact test was irrelevant and granted Empire Bucket’s motion in limine to bar testimony regarding that test at the liability phase of the trial.

However, at trial the district court clarified that only specific references to the Charpy impact test were barred. General references to the weld material’s “brittleness” or “toughness” were otherwise admissible. Consequently, Contractors Cargo’s experts were permitted to testify regarding the low fracture toughness (that is, brittleness) of the material at the location of the inclusion in the weld. For instance, Duane Gilbert, an experienced welder who qualified as an expert in the areas of welding, fitting, and quality assurance and control, testified that a weld can become brittle if “the heat input is too high.” He testified further that the deck failed at the inclusion because it had a “brittle fracture.” Specifically, Gilbert explained, the crack in the deck originated at the inclusion because it was the weak point in the brittle weld material. Similarly, Schwantes, who qualified as an expert in metallurgical failure analysis and static, dynamic, and fatigue mechanical testing, testified that the deck suffered from a “brittle fracture,” which he defined as “a fracture that occurs below the yield strength of the material.” 2 He explained that his testimony was drawn from initial observations that were confirmed “[biased on the analysis we had performed, based on metallography and some of the other test results.” Schwantes concluded that the inclusion was the “primary factor” in the deck’s failure, and that the deck’s fracture was similar to “a textbook case for a brittle fracture.” Nonetheless, the jury returned a verdict for Empire Bucket. Contractors Cargo appeals.

II. Discussion

On appeal, Contractors Cargo argues that the district court erred in excluding as irrelevant specific references to the Charpy impact test performed on the deck.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
739 F.3d 1068, 2014 WL 128708, 2014 U.S. App. LEXIS 1958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-bucket-inc-v-contractors-cargo-company-ca7-2014.