Emhart Industries, Inc. v. New England Container Co.

130 F. Supp. 3d 534, 2015 WL 5512202
CourtDistrict Court, D. Rhode Island
DecidedSeptember 17, 2015
DocketNos. CA 06-218 S, CA 11-023 S
StatusPublished
Cited by2 cases

This text of 130 F. Supp. 3d 534 (Emhart Industries, Inc. v. New England Container Co.) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Emhart Industries, Inc. v. New England Container Co., 130 F. Supp. 3d 534, 2015 WL 5512202 (D.R.I. 2015).

Opinion

[537]*537PHASE I FINDINGS OF FACT AND CONCLUSIONS OF LAW

WILLIAM E. SMITH, Chief Judge.

Table of Contents

Introduction ..........................................................'.........538

I.Findings of Fact.........................................................541

A. Site Description and Operational History................................541

B. Overview of Indüstrial Practices ................................543

1. Metro Atlantic’s Main-Building Operations.......................... 543

a. Destination of Solid Waste..........'....................".......543

b. Destination of Liquid Waste....................................545

2. Metro Atlantic’s Trifluralin Operations........................____547

3. .NECC’s Drum-Reconditioning Operations............................547

á. Drum Storage.....'.................,..........•;...............548

b. Drum-Reconditioning Processes.................. (..............549

i. Open-Head Drums..................... 549

ii. Closed-Head Drums ..............................550

c. NECC’s Use of the WDA......................................551

C. Metro Atlantic’s HCP-Manufacturing Operations ........................551

1. Storage of Crude Na 2, 4, 5-TCP ....................................552

2. Duration of Metro Atlantic’s HCP-Manufacturing Operations..........555

3. Waste Streams of HCP-Manufacturing Process.......................557

a. Destination of Liquid Waste................................ 558

b. Destination of Solid Waste...............................563

i. Lay-Witness Testimony.........................;_______563

ii. Site Data..............................................565

■ A. HCX ......'...........................,.............566

1. Formation of HCX..............................566

2. Location of HCX................................567

3. Colocation of HCX: Number of Nuchar Treatments............. 568

4.Colocation with Two Nuchar Treatments...........573

B. 2,3, 7, 8-TCDD in the WDA.........................576

4. Soil in Vicinity of HOP Building Footprint...........................582

a. ' Leaks and Spills..................'..............'..............582

b. Presence of Other Substances..................................583

e. NECC as the Source of 2,3, 7, 8-TCDD in This Area.............584

i. Dioxin-Congener Profile.................................585

ii. DOD Drums 1............. 589

d. Metro Atlantic is Responsible for 2, 3, 7, 8-TCDD in the Area . of the HOP Plant'...................................!/.../. .594

5. Radiometric Dating of Pond Sediments..............................595

D. Fate & Transport.............................................. 597
E. Incurrence of Response Costs.........................................600
II. Conclusions of Law ........................................................602
A. Emhart is Liable as a Past Operator under § 9607(a).....................602
B. Emhart Has Not Proven that the Harm at the Site is Divisible.............603

C.- The DOD’s Rule 52(c) Motion..........................................609

III. Conclusion......... 611

[538]*538Introduction

This environmental case arises from pollution discovered within the Centredale Manor Restoration Project Superfund Site (“Site”) located in North Providence, Rhode Island. Plaintiff and Counterclaim Defendant, Emhart Industries, Inc. (“Em-hart”), initiated this case in May 2006, when it asserted cost recovery and contribution claims under §§ 107(a) and 113(f) of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (“CERCLA”), see 42 U.S.C. §§ 9607(a), 9613(f), against New England Container Co. (“NECC”) and its insurers related to the pollution at the Site.1 (C.A. No. 06-218, ECF No. I.)2 In January 2011, Emhart filed suit against the United States Department of the Air Force, the United States Department of the Navy, the United States Department of Defense, the secretaries of each of these departments, and the United States (collectively, “the DOD”), asserting CERCLA claims similar to those asserted in its case against NECC.3 (Emhart’s Compl. ¶¶ 41-54, ECF No. 1.)

Since that time, the parties have filed a bevy of claims against one another: the DOD filed a CERCLA contribution counterclaim against Emhart (Counterclaim ¶¶ 42-44, ECF No. 32); the United States, on behalf of the Environmental Protection Agency (“the EPA” and, collectively with the DOD, “the Government”), filed a CERCLA cost recovery counterclaim against Emhart (Counterclaim ¶¶ 45-50, ECF No. 32); the Government filed a third-party complaint against Black & Decker, Inc. (“Black & Decker”), Emhart’s successor, asserting "the same claims as those asserted in its counterclaim against Emhart (ECF No. 34); Black & Decker filed a third-party counterclaim against the DOD, asserting the same claims that are asserted by Emhart in its claims against the DOD (ECF No. 49);4 the Government filed a crossclaim against NECC, asserting a CERCLA cost recovery claim and a CERCLA contribution claim on behalf of the DOD (ECF No. 67); NECC asserted CERCLA cost recovery and contribution crossclaims against the DOD (ECF No. 93); and the Government filed a claim against Emhart arising from its failure to comply -with a CERCLA cleanup order (Gov’t’s 2d Am. Answer & Counterclaims ¶¶ 53-60, ECF No. 357; Gov’t’s 2d Am.3d Party Compl. ¶¶ 65-72, ECF No. 358).

[539]*539This Court set a phased-trial schedule for this case (8th Rev. Case Mgmt. Order 2, ECF No. 295), which was modified multiple times to accommodate the parties’ discovery needs.5 The first phase was slated to address the liability of Emhart and NECC, including divisibility and the proper allocation of responsibility between Emhart and NECC in the event that both were found jointly and severally liable under CERCLA. (Id.) However, shortly before trial on the first phase commenced, NECC, which had “limited financial ability to pay for response costs incurred and to be incurred at the Site” (Consent Decree 2, ECF No. 375) settled with the Government for $8,750,000-, the remainder of NECC’s insurance - coverage (id. at 2, 5), and a consent decree reflecting this settlement was approved and entered by this Court during trial.6 (Id.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SHAIKH v. GERMADNIG
D. New Jersey, 2025

Cite This Page — Counsel Stack

Bluebook (online)
130 F. Supp. 3d 534, 2015 WL 5512202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emhart-industries-inc-v-new-england-container-co-rid-2015.