EMERALD COAST UTILITIES AUTHORITY v. AMERICAN CAST IRON PIPE COMPANY

CourtDistrict Court, N.D. Florida
DecidedJuly 10, 2023
Docket3:20-cv-05986
StatusUnknown

This text of EMERALD COAST UTILITIES AUTHORITY v. AMERICAN CAST IRON PIPE COMPANY (EMERALD COAST UTILITIES AUTHORITY v. AMERICAN CAST IRON PIPE COMPANY) is published on Counsel Stack Legal Research, covering District Court, N.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EMERALD COAST UTILITIES AUTHORITY v. AMERICAN CAST IRON PIPE COMPANY, (N.D. Fla. 2023).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF FLORIDA PENSACOLA DIVISION

EMERALD COAST UTILITIES AUTHORITY,

Plaintiff,

v. Case No. 3:20cv5986/MCR/ZCB

AMERICAN CAST IRON PIPE COMPANY; VULCAN PIPE & STEEL COATINGS, INC.; and INDURON COATINGS, LLC,

Defendants. /

ORDER

This matter is before the Court on motions for summary judgment filed by Defendants American Cast Iron Pipe Company and Induron Coatings, LLC. See ECF Nos. 70, 72.1 I. Background2

This action involves a dispute over the alleged premature corrosion and failure of ductile iron pipe internally lined with a ceramic epoxy called “Protecto 401”

1 The Court previously ruled on the parties’ respective motions to exclude expert testimony and opinions under Federal Rule of Evidence 702 and Daubert v. Merrell Dow Pharm., Inc., 509 U.S. 579 (1993), and American’s motion for partial summary judgment. See Order, ECF No. 94. 2 Most of the relevant facts were detailed in a prior Order. See id. at 1-5. The Court now restates and supplements many of those same facts to correspond with new issues presented in the instant motions. (“P401”), which was used in two sewer pipeline construction projects commissioned by Plaintiff Emerald Coast Utilities Authority (“ECUA”) in Escambia County,

Florida. Defendant American Cast Iron Pipe Company (“American”) manufactured the unlined ductile iron pipes used in the two projects, Defendant Induron Coatings, LLC (“Induron”) manufactured the P401 coating, and Defendant Vulcan Pipe and

Steel Coatings, Inc. (“Vulcan”) applied Induron’s P401 coating to American’s pipes.3 ECUA alleges that, due to each defendant’s negligence, the P401 coating failed to adequately protect the interior metal surfaces of both sewer pipelines, resulting in leaks and/or corrosion, and also that the defendants misrepresented the

quality and fitness of P401-lined pipes, which ECUA relied on to its detriment in selecting them for use in the projects. The facts relevant to the instant motions, construed in the light most favorable to ECUA, the non-moving party, are as

follows.4 ECUA operates the sewer system in Escambia County, Florida. In early 2006, ECUA began the process of upgrading Escambia County’s sewer system by, among other things, building a new sewer plant and associated pipelines. As relevant to the

3 Defendant Vulcan and ECUA have settled the claims against Vulcan. See Notice of Settlement, ECF No. 57. American and Induron will be referred to collectively in this Order as “Defendants.” 4 At the summary judgment stage, a court must construe the facts in the light most favorable to the non-moving party. Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 888-89 (1990); Zaben v. Air Prods. & Chems., Inc., 129 F.3d 1453, 1455 (11th Cir. 1997). All disputed facts must be resolved in the non-movant’s favor, and all reasonable inferences arising from those facts must be drawn in its favor. Id. instant motion, ECUA contracted with Utility Service Co., Inc. (“USC”) to construct one of the pipelines (known as the Blue Angel Project), and procured ductile iron

pipe for that project from Defendants through USC.5 See Second Amended Complaint, ECF No. 38 at ¶ 11. ECUA’s original specifications called for the use of PVC pipe in the projects.

That changed, however, after a series of in-person meetings and phone calls between ECUA and representatives for Defendants. More specifically, ECUA’s design engineers provided American with the plans and specifications for the pipeline projects, see William Carter Dep., ECF No. 80-1 at 29, and met with representatives

of all three defendants for site visits in Birmingham, Alabama. While there, ECUA received presentations and promotional materials from Defendants about the attributes and quality of P401-lined ductile iron pipes for “tough” domestic sewer

applications. See ECUA Am. Interrog. Resp., ECF No. 69-1 at 3. According to ECUA, its representatives also discussed with Defendants their “primary concerns” regarding P401-lined ductile iron pipe; namely, whether it could handle the “extreme[]” levels of corrosivity expected to exist in ECUA’s pipelines. See Patrick

Byrne Aff., ECF No. 88-2 at 3-5. In response—again, according to ECUA—both

5 Utility Service Co., Inc. was contracted to construct a pipeline known as the Blue Angel Force Main Replacement. Morgan Contracting, Inc. was contracted to construct a second pipeline, known as Central Water Reclamation Facility Government Street Regional Lift Station & Regional Lift Station B. American and Induron assured ECUA that the product would withstand the anticipated levels of corrosivity and was suitable for ECUA’s particular project

specifications. See id. This information “convinced ECUA that P401-lined ductile iron pipe would be suitable for” its current domestic sewer projects, as well as for others in the future. See Bruce Neu Affidavit, ECF No. 59-2 at 4. Soon thereafter,

American contacted ECUA directly to request that the project specifications be modified to allow for the use of P401-lined ductile iron pipe “as a reasonable and practical additive alternate” for PVC pipe. See id. The modification was subsequently approved, id., and inserted into the project specifications as an

addendum, see Blue Angel Project Plans Addendum 1, ECF No. 59-1 at 10. Consistent with ECUA’s project specifications, USC contracted with American to obtain the P401-lined ductile iron pipe “on behalf of and at the direction

of ECUA” in early 2008. See ECUA Response, ECF No. 59 at 4. As agreed, American manufactured ECUA’s ductile iron pipes, Induron produced the P401 coating, and Vulcan applied the P401-coating to the interior metal surfaces of the pipes, which were then delivered to USC and used in the construction of ECUA’s

domestic sewer pipelines.6 The Blue Angel pipeline went into service later that same

6 Each “batch” of P401 produced by Induron had two components—the epoxy resin and an activator—that were shipped together to Vulcan. See White 30(b)(6), ECF No. 71-1 at 5, 10- 11. Vulcan mixed the epoxy and the activator, then applied the mixture to the subject pipes. See id. at 14-17. There is no evidence or argument in this case, at least not in connection with the instant motions, that the P401 was applied improperly. year, see Nixon Dep., ECF No. 68-1 at 39, 44 & 47, and the alleged premature corrosion and failure of various sections of that pipeline was discovered in January

2017, see id. at 47. This suit followed. ECUA’s complaint asserts four claims against American and Induron: negligence, negligent misrepresentation, breach of implied warranty of

merchantability, and breach of implied warranty of fitness for a particular purpose.7 The Court has already granted American’s motion for partial summary judgment on the implied warranty claims. American now moves for summary judgment on ECUA’s negligent manufacturing and negligent misrepresentation claims, and

Induron moves for summary judgment on all claims. II. Legal Standard Summary judgment is appropriate where the record reflects there are no

genuine disputes of material fact and the moving party is entitled to judgment as a matter of law. See Fed. R. Civ. P. 56; see also Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hickson Corp. v. Northern Crossarm Co.
357 F.3d 1256 (Eleventh Circuit, 2004)
North American Medical Corp. v. Axiom Worldwide, Inc.
522 F.3d 1211 (Eleventh Circuit, 2008)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Larry Bonner v. City of Prichard, Alabama
661 F.2d 1206 (Eleventh Circuit, 1981)
W.C. Lane, Jr. v. Celotex Corporation, Keene Corporation
782 F.2d 1526 (Eleventh Circuit, 1986)
Norma Rollins v. Techsouth, Inc.
833 F.2d 1525 (Eleventh Circuit, 1987)
Cedars of Lebanon Hosp. Corp. v. European X-Ray Distributors
444 So. 2d 1068 (District Court of Appeal of Florida, 1984)
Newbern v. Mansbach
777 So. 2d 1044 (District Court of Appeal of Florida, 2001)
Wasser v. Sasoni
652 So. 2d 411 (District Court of Appeal of Florida, 1995)
McDougald v. Perry
716 So. 2d 783 (Supreme Court of Florida, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
EMERALD COAST UTILITIES AUTHORITY v. AMERICAN CAST IRON PIPE COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emerald-coast-utilities-authority-v-american-cast-iron-pipe-company-flnd-2023.