Elzy v. Waterloo, Cedar Falls & Northern Railway Co.

193 Iowa 330
CourtSupreme Court of Iowa
DecidedJune 25, 1921
StatusPublished
Cited by6 cases

This text of 193 Iowa 330 (Elzy v. Waterloo, Cedar Falls & Northern Railway Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elzy v. Waterloo, Cedar Falls & Northern Railway Co., 193 Iowa 330 (iowa 1921).

Opinion

Weaver, J.

i damages- non-Sent^oi^iiquidated damages. — -The printed records in this case are very voluminous, but counsel in argument have narrowed the questions on which we must pass within comparatively small compass, it unnecessary for us to indulge in extended discussion of the facts,

Briefly outlining the situation of the parties at the date of the contracts between them, it should be said that the defendant railway company, having undertaken the project of building an electric railway from the city of Waterloo to the city of Cedar Rapids, let the contract for the construction of such improvement to its codefendant, the Cedar Valley Railway Construction Company, which company in turn sublet the work for grading the roadbed to R. A. Elzy, since deceased. For some reason, this work of grading was let to Elzy in four distinct parts, each part being made the subject of a distinct written agreement. The contract for the first of these parts, extending from Waterloo to La Porte, dated April 19, 1912, was to be completed September 1, 1912; the second contract, dated August 20, 1912, was for the grading from La Porte to Urbana, to be completed to Brandon June 1, 1913, and to Urbana Jtxly 1, 1913; the third contract, dated September 8, 1913, was for the grading from Urbana to Center Point, to be completed April 15, 1914; and the fourth and last contract, dated January 6, 1914, provided for the completion of the grade from Center Point to Cedar Rapids June 1, 1914. The said several sections of grading were not all completed within the contract periods, but the work as a whole seems to have been finally and formally accepted on September 5, 1914; and the contractor, Mr. Elzy, died on the following day.

The plaintiffs, as executors of the Elzy estate, engaged in a somewhat prolonged effort to effect' a settlement with the defendants, who, while expressing a willingness and desire to pay whatever was justly due the estate, found themselves hampered, for the time being, by unfavorable conditions in the money market. In November, 1914, counsel for plaintiffs prepared a statement of their claim, ready for filing a mechanics’ lien, but, before placing it upon record, interviewed the defendants again upon the subject of a settlement. Defendants again pleaded the difficulty they were experiencing in obtaining the needed funds, [332]*332but strongly objected to the filing of a lien, and finally, to avoid that movement, and in consideration of a waiver of the right to file such lien, the railway company executed and delivered to plaintiffs its bond or guaranty, with individual sureties, conditioned for the faithful performance and complete payment on part of the Cedar Valley Railway Construction Company for “any and all sums that may be found due to the R. A. Elzy estate for labor performed and materials furnished in the construction of the Waterloo, Cedar Falls & Northern Railway Company from Waterloo to Cedar Rapids. The time of payment of such claims found to be due the R. A. Elzy estate is left indefinite on account of the present banking conditions and the uncertainty of the money market, but it is understood and agreed that the railway company will turn to the account of the Elzy estate any spare money which it may be able to get from the earnings of said company or from any other source, and will complete the payment as rapidly as it possibly can. ’ ’

On August 31, 3917, this action was begun at law, to recover the alleged unpaid remainder of the claim due the estate. The issues, as at first defined by the pleadings, were very numerous; but in the course of the trial below, many minor matters of dispute were eliminated or abandoned, and defendants’ appeal to this court is limited to the single proposition that the trial court erred in refusing to assess liquidated damages against the Elzy estate. In their brief, counsel for appellant state the question thus:

“Did the contract provide for liquidated damages in case of default in the time of performance, or did it provide for a penalty only? If it provided for a penalty only, it is to be conceded, without more ado, that the action of the court was correct, because it was admitted that the amount of actual damages was not attempted to be proven.”

By the ruling of the trial court upon the motions for a directed verdict, the plaintiffs’ recovery was for moneys alleged to be due them upon the claims stated in Count 4 of Division 4 of their amended and substituted petition, which is based upon the contract covering the grading of the roadbed from La Porte to Urbana. Stated in the aggregate, it is there charged that Elzy’s earnings under this contract were $102,259.28, against [333]*333which defendants were entitled to credit in the aggregate sum of $87,561.46.

Answering this claim, the defendants’ admit Elzy’s earnings under this contract and the credits due to the defendants thereon to be as alleged, but aver that the remainder due from defendants upon such account should be reduced by the further sum of $12,600, as liquidated damages because of the .contractor’s failure to complete the work within the agreed time. Upon this contention the court below ruled against the defendants, and upon this holding the principal error argued is assigned.

I. Whether a given contract is to be construed as providing for liquidated damages is not always easy of determination. Counsel for appellant frankly concede upon this question that:

“The court will not necessarily be concluded by the language used in the contract, but will scrutinize the whole contract, the subject-matter thereof, and the extraneous facts tending to make clear the real nature of the stipulation. Neither the use of the word ‘liquidated’ or the words ‘liquidated damages’ nor the fact that the actual damages would be difficult of proof, nor even the intention of the parties to actually provide for liquidated damages, will necessarily control such construction. Doubts will be resolved against the allowance.”

This is, of course, not a concession that such circumstances are to be ignored; for they are both relevant and material, and to be given due consideration for what they are fairly worth, in arriving at a conclusion whether, upon the record as a whole, and under the settled rules of law upon the subject, the contract under investigation does or does not provide for stipulated damages.

At the outset upon this question, let us_ look to the particular clause of the contract which appellants quote as the foundation of their claim for such damages. The language so selected by counsel is that:

“The contractor specifically agrees to pay to the railway company as liquidated damages the sum of $50 for each and every day from and beyond June 1, 1913; that the grading from La Porte to Brandon remains unfinished and $50 for each and every day from and beyond July 1, 1913, that the grading from Brandon to Urbana remains unfinished, and it is specifically [334]*334understood and agreed that the railway company may reimburse itself for the full aggregate amount of sums named for either or both of these defaults from any money or moneys remaining in its hands, and owing the contractor under the terms of this agreement, but should the railway company so elect it may bring action in any of the courts of this state to collect said amounts due under said defaults.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Illingworth v. Bushong
656 P.2d 370 (Court of Appeals of Oregon, 1983)
State v. Butka
299 N.W. 420 (Supreme Court of Iowa, 1941)
Wilson v. Airline Coal Co.
246 N.W. 753 (Supreme Court of Iowa, 1933)
Millard v. Curtis
223 N.W. 489 (Supreme Court of Iowa, 1929)
Shockley v. Paul Davis Dry Goods Co.
205 N.W. 966 (Supreme Court of Iowa, 1925)
Independent School District v. Dudley
195 Iowa 398 (Supreme Court of Iowa, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
193 Iowa 330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elzy-v-waterloo-cedar-falls-northern-railway-co-iowa-1921.