Elwood v. Heinz-Young Construction Co.
This text of 166 S.W. 1076 (Elwood v. Heinz-Young Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
This is an action begun before a justice of ’the peace, where plaintiff had judgment. Upon defendant’s appeal to the circuit court, and a trial de novo there, .plaintiff again prevailed, and the case is here upon defendant’s appeal.
The only point involved relates to the sufficiency of the statement, or account, filed before the justice of the peace. This instrument, as it appears before us in the record,-begins: “Started to work for Heinz-Young Construction Company, Montana and Missouri avenues at the rate of sixty dollars per month.” Then follows a list of amounts for which plaintiff gives credit as having been paid him upon various specified dates., in the year 1911, amounting in all to $225. Then follows a heading, “Total amount due 1911;” following which are set out the various amounts claimed to have been earned during designated months of that year, the total thereof being $298. A further item of fifty cents occurs for ‘ ‘ repair of bars; ’ ’ making the bal[291]*291anee, claimed to be dne, $73.50. The paper is signed “Joseph Elwood.”
There is some contention that plaintiff’s name was not signed to the instrument until after the trial before the justice of the peace, but from the record before us, in which but little of the evidence is preserved, we cannot say that such was the case. Hence, we shall take the statement as we find it, without further comment as to the point thus sought to be made;
The instrument is not in the usual form of an account, and is quite informally drawn, but nevertheless it does show upon its face that plaintiff is claiming a balance due for work and labor performed for the defendant, during a certain stated period of time, at sixty dollars per month; and purports to give credit for all payments made plaintiff on account thereof, specifying the dates and amounts of such payments. It seems perfectly clear that it is sufficient to support the judgment. It is thoroughly settled that the test of the sufficiency of such a statement is-merely that it must fairly apprise the defendant of the nature of the claim against him and be sufficiently definite and specific to operate as a bar to-another action upon the same demand. [See Rundleman v. Boiler Works Co., 178 Mo. App. 642, 161 S. W. 609, and cases cited.] We think beyond doubt that the instrument here in question clearly advises the defendant of the nature of the claim, i. e., that it is a balance claimed to be due for services rendered; and that, inasmuch as it definitely sets forth the period during which such services are alleged to have been performed, and purports to give credit for all páyments made, it is sufficiently specific and definite to bar another action upon the same demand. The judgment is affirmed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
166 S.W. 1076, 183 Mo. App. 289, 1914 Mo. App. LEXIS 481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elwood-v-heinz-young-construction-co-moctapp-1914.