Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne

Court of Appeals of Texas·Decided July 2, 2015·No. 09-13-00508-CV·Published

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

NO. 09-13-00508-CV

ELTON SENEGAL D/B/A ELTON’S CONSTRUCTION, Appellant V.

SHIRLEY PAYNE AND JAMES PAYNE, Appellees _______________________________________________________ ______________

On Appeal from the 172nd District Court Jefferson County, Texas

Trial Cause No. E-191,964-A ________________________________________________________ _____________

MEMORANDUM OPINION

In a case arising from a dispute over a home remodeling project, Elton Senegal, d/b/a Elton’s Construction, appeals from a judgment notwithstanding the verdict (JNOV) awarding the plaintiffs $70,000, approximately twice the amount of the jury’s award. According to Elton, the evidence supports the jury’s award, and the trial court erred by disregarding it.

Because the evidence on damages that was before the jury allowed it to rationally return a verdict awarding the Paynes $36,000 in damages, we hold the

trial court erred in disregarding the jury’s verdict. We reverse the trial court’s JNOV, and we remand the case to the trial court to allow that court to render a judgment that is based on the jury’s verdict. Tex. R. App. P. 43.3(a).

Background

In October 2011, Elton and Shirley Payne signed a remodeling contract. The contract required Elton to substantially remodel the Paynes’ home, and required Elton to tear down and replace an existing garage with a three-car garage and carport. Due to the nature of the contract, the contract provided that any work required due to “unforeseen damages” could result in an additional charge.

Although the contract generally describes the work, it does not specify the quality or grade of materials that Elton planned to use on the project or the dimensions of the areas to be remodeled. The parties do not dispute that the remodeling contract required Shirley to pay $116,000 for the work. Under the contract, Elton was to receive an initial down payment, and he was then to draw against the balance of the contract as the project progressed. In November 2011, Shirley signed a change order, increasing Elton’s compensation under the contract by $2,100 to $118,100.

Between October 2011 and November 2011, Elton demolished various structures, poured cement, and made significant progress toward the remodeling of the Paynes’ home. In early December 2011, Shirley was sent a new contract, which

proposed to complete the work at a total cost of $197,800. In Shirley’s opinion, Elton was required to perform all of the work in the proposed new contract under the terms of his October 2011 contract. Elton testified that he could not remember if he sent Shirley a new contract proposal or not, but shortly after Shirley failed to return the new proposal, Elton quit the project. Before Elton quit, Shirley paid him $81,366 for his work.

In late December 2011, the Paynes requested that Elton submit the dispute to arbitration through the Better Business Bureau. In early January 2012, Elton agreed to arbitration, and the dispute was arbitrated. In a reasoned decision, the arbitrator found that Elton breached the remodeling contract and awarded relief in favor of the Paynes, requiring Elton to “honor [his] original bid of $116,000 and complete the work in accordance with the original contract . . . on or before 6/30/2012.” The arbitrator’s award also required that the Paynes, upon completion, pay Elton $34,634, the balance due under his original contract.

Several weeks after the arbitrator notified the parties of his award, the Paynes’ attorney sent Elton a letter threatening suit. The letter to Elton alleges that Elton breached the arbitrator’s award; it demands that Elton begin work within ten days. Elton did not return to the project to complete it.

In mid-February 2012, the Paynes’ attorney obtained a bid from Grady Rucker, a contractor, to finish the project for $88,343. During the trial, Rucker

testified that he used the blueprints that Elton used in preparing his bid. Additionally, Rucker indicated that he planned to incorporate any construction materials that were still onsite to complete the project; however, Rucker indicated that the Paynes did not hire him.

Moises Castillo, a carpenter who had been working on the project for Elton before Elton quit, gave Shirley another bid to complete Elton’s contract. Castillo bid $70,600 to complete Elton’s work. Castillo testified that Shirley hired him, and that she paid him $70,000. However, Castillo testified that he was unable to complete the project because he ran out of money.

Before the trial, the Paynes filed a motion for partial summary judgment. In the motion, the Paynes alleged that Elton was bound by the arbitrator’s finding that Elton breached his remodeling contract. The trial court granted the motion, rendered a partial summary judgment, and found that Elton breached the contract. However, the partial summary judgment did not resolve the parties’ disputes about whether some of Elton’s work allowed him to charge the Paynes additional sums to compensate for correcting “unforeseen damages.” The partial summary judgment also did not resolve the reasonable sum required to compensate the Paynes due to Elton’s breach.

The parties tried the dispute to a jury in October 2013. During the trial, Elton suggested that he found termite damage after he started the project, which required

extra work. During the trial, Elton claimed that he had not foreseen the termite damage when he bid the project, and he claimed that repairing termite damage was beyond the scope of the work required by his contract.1 Standard of Review

In one issue, Elton contends the trial court erred by disregarding the jury’s award of damages. Generally, a trial court must render a judgment based on the jury’s verdict in a case; a trial court is authorized to grant a motion to disregard a jury’s verdict only if a directed verdict on the issue would have been proper. Tex. R. Civ. P. 301; Fort Bend Cnty. Drainage Dist. v. Sbrusch, 818 S.W.2d 392, 394 (Tex. 1991). When a trial court’s decision to disregard a jury’s verdict is challenged on appeal, we review the challenge using the same standard that we use to review a challenge to a trial court’s decision to grant a directed verdict. Rush v. Barrios, 56 S.W.3d 88, 94 (Tex. App.—Houston [14th Dist.] 2001, pet. denied). Under that standard, to justify the trial court’s decision to disregard the jury’s verdict in this case, the record must conclusively establish that the jury could reach only one decision on the amount the Paynes were damaged, and that no reasonable

1 While Elton’s trial testimony contradicts a prior statement that he made when the case was arbitrated about why his expenses for the project increased, the statement that he made during the arbitration to explain the increase was not before the jury. Because Elton’s prior statement explaining why he could not complete the project was not before the jury, we do not consider it in evaluating if there was legally sufficient evidence before the jury to explain the jury’s damage award.

factfinder would conclude on this record that the Paynes were damaged in any amount other than $70,000. See Prudential Ins. Co. of Am. v. Fin. Review Servs., Inc., 29 S.W.3d 74, 77 (Tex. 2000); In re Estate of Longron, 211 S.W.3d 434, 438 (Tex. App.—Beaumont 2006, pet. denied).

Evidence is legally sufficient if it “would enable reasonable and fair-minded people to reach the verdict under review.” City of Keller v. Wilson, 168 S.W.3d 802, 827 (Tex. 2005). In evaluating the evidence’s legal sufficiency, we review the entire record and “credit evidence that supports the verdict if reasonable jurors could, and disregard contrary evidence unless reasonable jurors could not.” Kroger Tex. Ltd. P’ship v. Suberu, 216 S.W.3d 788, 793 (Tex. 2006) (citing City of Keller, 168 S.W.3d at 827); see Am. Interstate Ins. Co. v. Hinson, 172 S.W.3d 108, 114 (Tex. App.—Beaumont 2005, pet. denied).

Free access — add to your briefcase to read the full text and ask questions with AI

Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne, (Tex. Ct. App. 2015).

Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne (Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rush v. Barrios
56 S.W.3d 88 (Court of Appeals of Texas, 2001)
Pope v. Moore
711 S.W.2d 622 (Texas Supreme Court, 1986)
Osterberg v. Peca
12 S.W.3d 31 (Texas Supreme Court, 2000)
In Re Estate of Longron
211 S.W.3d 434 (Court of Appeals of Texas, 2006)
Turner, Collie & Braden, Inc. v. Brookhollow, Inc.
642 S.W.2d 160 (Texas Supreme Court, 1982)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
American Interstate Insurance Co. v. Hinson
172 S.W.3d 108 (Court of Appeals of Texas, 2005)
Kroger Texas Ltd. Partnership v. Suberu
216 S.W.3d 788 (Texas Supreme Court, 2006)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Fort Bend County Drainage District v. Sbrusch
818 S.W.2d 392 (Texas Supreme Court, 1991)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Drury Southwest, Inc. v. Louie Ledeaux 1, Inc.
350 S.W.3d 287 (Court of Appeals of Texas, 2011)