Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne

CourtCourt of Appeals of Texas
DecidedJuly 2, 2015
Docket09-13-00508-CV
StatusPublished

This text of Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne (Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne, (Tex. Ct. App. 2015).

Opinion

In The

Court of Appeals Ninth District of Texas at Beaumont ____________________ NO. 09-13-00508-CV ____________________

ELTON SENEGAL D/B/A ELTON’S CONSTRUCTION, Appellant

V.

SHIRLEY PAYNE AND JAMES PAYNE, Appellees _______________________________________________________ ______________

On Appeal from the 172nd District Court Jefferson County, Texas Trial Cause No. E-191,964-A ________________________________________________________ _____________

MEMORANDUM OPINION

In a case arising from a dispute over a home remodeling project, Elton

Senegal, d/b/a Elton’s Construction, appeals from a judgment notwithstanding the

verdict (JNOV) awarding the plaintiffs $70,000, approximately twice the amount

of the jury’s award. According to Elton, the evidence supports the jury’s award,

and the trial court erred by disregarding it.

Because the evidence on damages that was before the jury allowed it to

rationally return a verdict awarding the Paynes $36,000 in damages, we hold the

1 trial court erred in disregarding the jury’s verdict. We reverse the trial court’s

JNOV, and we remand the case to the trial court to allow that court to render a

judgment that is based on the jury’s verdict. Tex. R. App. P. 43.3(a).

Background

In October 2011, Elton and Shirley Payne signed a remodeling contract. The

contract required Elton to substantially remodel the Paynes’ home, and required

Elton to tear down and replace an existing garage with a three-car garage and

carport. Due to the nature of the contract, the contract provided that any work

required due to “unforeseen damages” could result in an additional charge.

Although the contract generally describes the work, it does not specify the

quality or grade of materials that Elton planned to use on the project or the

dimensions of the areas to be remodeled. The parties do not dispute that the

remodeling contract required Shirley to pay $116,000 for the work. Under the

contract, Elton was to receive an initial down payment, and he was then to draw

against the balance of the contract as the project progressed. In November 2011,

Shirley signed a change order, increasing Elton’s compensation under the contract

by $2,100 to $118,100.

Between October 2011 and November 2011, Elton demolished various

structures, poured cement, and made significant progress toward the remodeling of

the Paynes’ home. In early December 2011, Shirley was sent a new contract, which 2 proposed to complete the work at a total cost of $197,800. In Shirley’s opinion,

Elton was required to perform all of the work in the proposed new contract under

the terms of his October 2011 contract. Elton testified that he could not remember

if he sent Shirley a new contract proposal or not, but shortly after Shirley failed to

return the new proposal, Elton quit the project. Before Elton quit, Shirley paid him

$81,366 for his work.

In late December 2011, the Paynes requested that Elton submit the dispute to

arbitration through the Better Business Bureau. In early January 2012, Elton agreed

to arbitration, and the dispute was arbitrated. In a reasoned decision, the arbitrator

found that Elton breached the remodeling contract and awarded relief in favor of

the Paynes, requiring Elton to “honor [his] original bid of $116,000 and complete

the work in accordance with the original contract . . . on or before 6/30/2012.” The

arbitrator’s award also required that the Paynes, upon completion, pay Elton

$34,634, the balance due under his original contract.

Several weeks after the arbitrator notified the parties of his award, the

Paynes’ attorney sent Elton a letter threatening suit. The letter to Elton alleges that

Elton breached the arbitrator’s award; it demands that Elton begin work within ten

days. Elton did not return to the project to complete it.

In mid-February 2012, the Paynes’ attorney obtained a bid from Grady

Rucker, a contractor, to finish the project for $88,343. During the trial, Rucker 3 testified that he used the blueprints that Elton used in preparing his bid.

Additionally, Rucker indicated that he planned to incorporate any construction

materials that were still onsite to complete the project; however, Rucker indicated

that the Paynes did not hire him.

Moises Castillo, a carpenter who had been working on the project for Elton

before Elton quit, gave Shirley another bid to complete Elton’s contract. Castillo

bid $70,600 to complete Elton’s work. Castillo testified that Shirley hired him, and

that she paid him $70,000. However, Castillo testified that he was unable to

complete the project because he ran out of money.

Before the trial, the Paynes filed a motion for partial summary judgment. In

the motion, the Paynes alleged that Elton was bound by the arbitrator’s finding that

Elton breached his remodeling contract. The trial court granted the motion,

rendered a partial summary judgment, and found that Elton breached the contract.

However, the partial summary judgment did not resolve the parties’ disputes about

whether some of Elton’s work allowed him to charge the Paynes additional sums to

compensate for correcting “unforeseen damages.” The partial summary judgment

also did not resolve the reasonable sum required to compensate the Paynes due to

Elton’s breach.

The parties tried the dispute to a jury in October 2013. During the trial, Elton

suggested that he found termite damage after he started the project, which required 4 extra work. During the trial, Elton claimed that he had not foreseen the termite

damage when he bid the project, and he claimed that repairing termite damage was

beyond the scope of the work required by his contract.1

Standard of Review

In one issue, Elton contends the trial court erred by disregarding the jury’s

award of damages. Generally, a trial court must render a judgment based on the

jury’s verdict in a case; a trial court is authorized to grant a motion to disregard a

jury’s verdict only if a directed verdict on the issue would have been proper. Tex.

R. Civ. P. 301; Fort Bend Cnty. Drainage Dist. v. Sbrusch, 818 S.W.2d 392, 394

(Tex. 1991). When a trial court’s decision to disregard a jury’s verdict is

challenged on appeal, we review the challenge using the same standard that we use

to review a challenge to a trial court’s decision to grant a directed verdict. Rush v.

Barrios, 56 S.W.3d 88, 94 (Tex. App.—Houston [14th Dist.] 2001, pet. denied).

Under that standard, to justify the trial court’s decision to disregard the jury’s

verdict in this case, the record must conclusively establish that the jury could reach

only one decision on the amount the Paynes were damaged, and that no reasonable

1 While Elton’s trial testimony contradicts a prior statement that he made when the case was arbitrated about why his expenses for the project increased, the statement that he made during the arbitration to explain the increase was not before the jury. Because Elton’s prior statement explaining why he could not complete the project was not before the jury, we do not consider it in evaluating if there was legally sufficient evidence before the jury to explain the jury’s damage award. 5 factfinder would conclude on this record that the Paynes were damaged in any

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rush v. Barrios
56 S.W.3d 88 (Court of Appeals of Texas, 2001)
Pope v. Moore
711 S.W.2d 622 (Texas Supreme Court, 1986)
Osterberg v. Peca
12 S.W.3d 31 (Texas Supreme Court, 2000)
In Re Estate of Longron
211 S.W.3d 434 (Court of Appeals of Texas, 2006)
Turner, Collie & Braden, Inc. v. Brookhollow, Inc.
642 S.W.2d 160 (Texas Supreme Court, 1982)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
American Interstate Insurance Co. v. Hinson
172 S.W.3d 108 (Court of Appeals of Texas, 2005)
Kroger Texas Ltd. Partnership v. Suberu
216 S.W.3d 788 (Texas Supreme Court, 2006)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Fort Bend County Drainage District v. Sbrusch
818 S.W.2d 392 (Texas Supreme Court, 1991)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Drury Southwest, Inc. v. Louie Ledeaux 1, Inc.
350 S.W.3d 287 (Court of Appeals of Texas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Elton Senegal D/B/A Elton's Construction v. Shirley Payne and James Payne, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elton-senegal-dba-eltons-construction-v-shirley-pa-texapp-2015.