Else v. Acc

CourtCourt of Appeals of Arizona
DecidedJanuary 25, 2018
Docket1 CA-CV 17-0208
StatusUnpublished

This text of Else v. Acc (Else v. Acc) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Else v. Acc, (Ark. Ct. App. 2018).

Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

PETER T. ELSE, Plaintiff/Appellant,

v.

ARIZONA CORPORATION COMMISSION, Defendant/Appellee,

SUNZIA TRANSMISSION LLC, Intervenor/Appellee.

No. 1 CA-CV 17-0208 FILED 1-25-2018

Appeal from the Superior Court in Maricopa County No. CV2016-092030 The Honorable Lori H. Bustamante, Judge

AFFIRMED

COUNSEL

Peter T. Else, Mammoth Plaintiff/Appellant

Arizona Corporation Commission, Phoenix By Charles H. Hains, Wesley C. Van Cleve, Andrew M. Kvesic, Maureen A. Scott Counsel for Defendant/Appellee ELSE v. ACC, et al. Decision of the Court

Ryley Carlock & Applewhite PA, Phoenix By Albert H. Acken, Samuel L. Lofland Co-Counsel for Intervenor/Appellee

Munger Chadwick, Green Valley By Lawrence V. Robertson, Jr. Co-Counsel for Intervenor/Appellee

MEMORANDUM DECISION

Presiding Judge Lawrence F. Winthrop delivered the decision of the Court, in which Judge Jennifer B. Campbell and Judge Paul J. McMurdie joined.

W I N T H R O P, Presiding Judge:

¶1 Peter T. Else (“Else”) appeals the superior court’s order affirming the Arizona Corporation Commission’s (the “Commission”) grant of a Certificate of Environmental Compatibility (“CEC”) to SunZia Transmission LLC (“SunZia”). For the following reasons, we affirm.

FACTS AND PROCEDURAL HISTORY

¶2 SunZia is an independent transmission project owned by Salt River Project, Tucson Electric Power Company, Tri-State Generation and Transmission Association, Shell Wind Energy, and Southwestern Power Group II, LLC. In 2006, the Southwest Area Transmission Subregional Planning Group1 proposed a new transmission line between New Mexico and southern Arizona to provide service for a growing demand for renewable energy (the “Project”). In 2008, SunZia, as a project owner, filed a right-of-way application with the Bureau of Land Management (“BLM”). Subsequently, the BLM, in connection with other federal and state agencies, began to prepare an Environmental Impact Statement. After hearing public comment, the BLM issued its final Environmental Impact Statement

1 The Southwest Area Transmission Subregional Planning Group is a group of governmental entities; transmission regulators, users, owners, and operators; and environmental groups that promote regional planning of transmission lines in the Southwest. Regional Planning, WESTCONNECT, http://regplanning.westconnect.com/swat.htm (last visited Jan. 18, 2018).

2 ELSE v. ACC, et al. Decision of the Court

detailing the Project’s proposed route through southern Arizona, and ultimately in 2015 approved SunZia’s request for a right-of-way.

¶3 After the BLM’s approval of its right-of-way, SunZia applied for a CEC with the Arizona Power Plant and Transmission Line Siting Committee (the “Committee”).2 In support of its application SunZia submitted numerous documents detailing the proposed transmission route’s geography, the flora and fauna in the area, and any negative impacts construction would have on the surrounding environment. SunZia further promoted the Project as helping to generate and transport additional electricity, helping to relieve existing transmission congestion, and helping to provide additional energy delivery options to aid Arizona in meeting its renewable energy portfolio standards and federal mandates. The Project was expected to begin development in 2018 and conclude construction of the first transmission facility by 2021.

¶4 The Committee held a multi-day hearing regarding SunZia’s CEC application. During the hearing, the Committee heard from the Project’s proponents and opponents, went on site visits to view the proposed route, and reviewed environmental impact studies. Numerous parties attended the hearing, including representatives for SunZia, the Commission, Pinal County, Natural Resources Conservation Districts, private residential communities, as well as Else3 and other propria persona intervenors.

¶5 At the hearing, SunZia argued the Project would “create[] access to stranded renewable [energy] resources.” To support this proposition, SunZia presented maps of the Project’s proposed route with estimates of the amount of energy that could be generated from available solar and wind resources in eastern Arizona and western New Mexico. In opposition, Else, and other intervenors, argued there was no proven need for the proposed renewable energy and that it was unlikely the Project

2 The Arizona portion of the Project spans approximately 199 miles from Greenlee County to the existing Pinal Central Substation, and consists of two single-circuit 500-kilovolt transmission lines and associated facilities. The Project primarily crosses lands administered by the Arizona State Land Department and BLM, with only a small portion crossing private lands.

3 Else moved to intervene as a landowner in the San Pedro watershed and a conservation activist in the region, and the Committee granted his motion.

3 ELSE v. ACC, et al. Decision of the Court

would come to fruition. At the conclusion of the hearing, the Committee discussed whether it could require that the Project comply with renewable energy conditions and proposed two requirements: (1) that the Project not begin construction more than 90 days before construction of the New Mexico wind project; and (2) that approval of the Project be conditioned on transmitting a certain percentage of renewable energy. Ultimately, after significant debate, both conditions were rejected.4 The Committee, however, did adopt the condition that SunZia “will, in good faith, and consistent with the requirements of state and federal law, use its best efforts to secure transmission service contracts for renewable energy generation[,]” and approved the CEC.5

¶6 After the Committee approved the CEC, it sent the CEC to the Commission for independent review. The Commission then heard additional public comment and argument on the matter. Opponents of the Project reiterated their concern that the Project would not be constructed as proposed. They further accused SunZia of wanting an approved right-of- way without being obligated to deliver renewable energy to Arizona. To ensure against this, they requested the Commission specifically condition the CEC on SunZia transmitting renewable energy. The Commission, however, did not impose any additional conditions and approved the CEC by a 3-2 vote. In approving the CEC, the Commission incorporated the Committee’s findings of fact and conclusions of law, and adopted the Committee’s “good faith” and “best efforts” conditions.6 Else moved for a rehearing, which the Commission denied, and then filed a timely appeal with the superior court.

4 In rejecting the conditions, the Committee noted that the Commission was better qualified to determine the legality of imposing the proposed conditions on the CEC.

5 The Committee additionally found that “[t]he Project may assist the state in meeting the goal of increasing the use of renewable energy in the state.”

6 In the dissent, Chairman Little argued that SunZia presented “either no evidence or questionable evidence” that any of the Project’s purported benefits would materialize. Chairman Little further argued that SunZia provided no “real assurance that the proposed line will actually lead to the development of additional renewable energy resources.”

4 ELSE v. ACC, et al. Decision of the Court

¶7 In the superior court, Else moved and SunZia and the Commission cross-moved for judgment on the administrative record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abbott Laboratories v. Gardner
387 U.S. 136 (Supreme Court, 1967)
Califano v. Sanders
430 U.S. 99 (Supreme Court, 1977)
Pioneer Trust Co. v. Pima County
811 P.2d 22 (Arizona Supreme Court, 1991)
Winkle v. City of Tucson
949 P.2d 502 (Arizona Supreme Court, 1997)
In Re Estate of Pouser
975 P.2d 704 (Arizona Supreme Court, 1999)
Tucson Electric Power Co. v. Arizona Corp. Commission
645 P.2d 231 (Arizona Supreme Court, 1982)
City of Tucson v. Citizens Utilities Water Company
498 P.2d 551 (Court of Appeals of Arizona, 1972)
Grand Canyon Trust v. Arizona Corp. Commission
107 P.3d 356 (Court of Appeals of Arizona, 2005)
Town of Gilbert v. Maricopa County
141 P.3d 416 (Court of Appeals of Arizona, 2006)
Sierra Club—Grand Canyon Chapter v. Arizona Corp. Commission
354 P.3d 1127 (Court of Appeals of Arizona, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Else v. Acc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/else-v-acc-arizctapp-2018.