Eloquence on the Bay Condominium Association, Inc., Etc. v. CDC Builders, Inc., Etc.
Opinion
Third District Court of Appeal State of Florida
Opinion filed June 18, 2025.
Not final until disposition of timely filed motion for rehearing.
No. 3D23-592
Lower Tribunal No. 16-9912
Eloquence on the Bay Condominium Association, Inc., etc., Appellant,
vs.
CDC Builders, Inc., etc., et al., Appellees.
An Appeal from the Circuit Court for Miami-Dade County, Lisa S.
Walsh, Judge.
Klein Park & Lowe, P.L., and Robert M. Klein and Andrew M. Feldman, for appellant.
Cole Scott & Kissane, P.A., and Scott A. Cole and Therese A. Savona (Orlando), for appellee CDC Builders, Inc.
Before LINDSEY, LOBREE and BOKOR, JJ.
LOBREE, J.
Eloquence on the Bay Condominium Association, Inc. (“Eloquence”)
appeals the entry of final judgment in favor of CDC Builders, Inc. (“CDC”) and an order denying its motion for new trial based on the trial court’s decision to modify the agreed jury instructions mid-trial to include CDC’s new proposed jury instruction on damages. For the reasons that follow, we affirm.
BACKGROUND
In 2016, Eloquence filed suit against its condominium developer Ness Racquet Club, LLC, and its general contractor, CDC, alleging the condominium was constructed with numerous construction and design defects. Eloquence amended its complaint in 2018 to include claims against CDC for breach of the statutory implied warranty of fitness, negligence, and for breach of the Florida Building Code.
The matter proceeded and the case was set for a jury trial. Eleven days before trial began, the parties attended a charge conference where they discussed jury instructions. Both parties had submitted proposed jury instructions, which each stated that the measure of damages was “the reasonable cost of necessary repairs which the greater weight of the evidence shows resulted, or will result, from” CDC’s alleged breach or negligence. At the pretrial conference neither party presented any argument regarding the time frame or date on which the amount of damages should be measured.
An eight-day trial was held. After the jury was sworn in, the trial court told the jury that it would receive a complete set of jury instructions at the end of the trial but that it would give the jury some of the rules at the start of trial so the jury could begin to understand how to apply the evidence. While walking the jury through its instructions, the trial court told the jury that the measure of damages would be “the reasonable cost of any necessary repairs which the greater weight of the evidence shows resulted or will result from Defendant CDC’s” breach of the implied warranty of fitness, negligence, and breach of the Florida Building Code.
As trial progressed, the trial court granted Eloquence’s motion for directed verdict finding CDC violated a provision of the Florida Building Code involving the building’s post-tensioning system because both Eloquence and CDC’s experts testified that there was a violation. However, the trial court reviewed the language of section 553.84, Florida Statutes, and found the jury should still be permitted to make liability findings as to whether CDC knew or should have known that a material violation existed, and whether there was any personal injury or damage to property other than that subject to the construction plans as CDC received approval for its construction plans.
At the end of the sixth day of trial, Eloquence stated its objection to a new set of jury instructions that CDC had circulated that morning. Eloquence
argued it did not agree to the newly-proposed jury instructions as they had substantive changes, the case was already six days into trial, and the parties already had a three-hour charge conference where the trial court ruled on the instructions. The trial court directed the parties to meet and discuss the proposed instructions before the continuation of trial the next day.
The next day, the parties discussed the jury instructions after all parties rested their case. During this discussion, Eloquence noted it objected to CDC’s inclusion of a sentence to the damages instructions that stated: “The cost of repair must be measured at the time of the breach, not the time of trial.” Eloquence asserted this was improper because its claims against CDC were not for breach of contract, but rather breach of statutory warranty and the Florida Building Code. Notably, Eloquence did not argue that inclusion of this jury instruction would mislead the jury or result in an unfair trial.
CDC argued that limitation of the damages to the time of the breach was proper pursuant to Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037, 1040 (Fla. 1982), and further contended the time of the breach should be considered 2015, as that was after the condominium building was turned over to Eloquence. Eloquence countered that damages should be equal to the cost of repair at the time of trial. The trial court disagreed. Eloquence then acquiesced to the inclusion of the modified jury instruction and agreed
that the jury instruction should state the cost of repairs should be measured as of 2015. Eloquence did not move to reopen the evidence, seek to recall its damages expert, or request that the trial court preclude CDC from arguing during closing that Eloquence presented no evidence of what the cost of repair was in 2015.
The next day, before closing arguments, the parties discussed the verdict form and Eloquence did not raise any objections or seek any additional interrogatories. During closing arguments, Eloquence did not address the amended measure of damages. CDC, on the other hand, noted that “[e]very single jury instruction on damages for all three counts requires [Eloquence] to prove the cost of repair in 2015 and you didn’t hear any evidence of it here. You heard 2019, 2022, but you didn’t hear 2015.” Eloquence did not contemporaneously object to this argument or move for a mistrial asserting it had been denied the opportunity to present evidence to the jury about the costs of repair in 2015. At the end of the trial, the jury rendered a verdict for CDC and the trial court entered final judgment in CDC’s favor.
Eloquence filed a motion for new trial asserting that the new jury instruction: (1) misled and confused the jury; (2) was improper as Eloquence’s claims were not based on breach of contract; and (3) was
inconsistent with the prior instructions, warranting a new trial. CDC responded asserting that: (1) the jury never reached the issue of Eloquence’s damages so any error in the measure of damages instruction was harmless; (2) Eloquence’s argument that the jury instructions were misleading was not preserved; (3) the law supported the new damages jury instruction; and (4) the verdict was not contrary to the manifest weight of the evidence. Eloquence filed a reply. The trial court heard the motion for new trial and ultimately denied the motion. This appeal followed.
ANALYSIS
“The standard of review over a trial court’s decision regarding a motion for new trial is abuse of discretion.” Barkett v. Gomez, 908 So. 2d 1084, 1086 (Fla. 3d DCA 2005). “A trial court’s decision to give or refuse to give a proposed jury instruction is reviewed for an abuse of discretion.” Philip Morris USA, Inc. v. McCall, 234 So. 3d 4, 14 (Fla. 4th DCA 2017). “The test regarding jury instructions is whether, under the particular facts of the case, the instructions misled the jury or prejudiced a party’s right to a fair trial.” ITT- Nesbitt, Inc. v. Valle’s Steak House of Fort Lauderdale, Inc., 395 So. 2d 217, 220 (Fla. 4th DCA 1981).
Free access — add to your briefcase to read the full text and ask questions with AI
Eloquence on the Bay Condominium Association, Inc., Etc. v. CDC Builders, Inc., Etc. (Eloquence on the Bay Condominium Association, Inc., Etc. v. CDC Builders, Inc., Etc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.