Ellwood City Forge Corp. v. Fort Worth Heat Treating Co.

636 A.2d 219, 431 Pa. Super. 240, 1994 Pa. Super. LEXIS 10
CourtSuperior Court of Pennsylvania
DecidedJanuary 13, 1994
Docket00842
StatusPublished
Cited by7 cases

This text of 636 A.2d 219 (Ellwood City Forge Corp. v. Fort Worth Heat Treating Co.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellwood City Forge Corp. v. Fort Worth Heat Treating Co., 636 A.2d 219, 431 Pa. Super. 240, 1994 Pa. Super. LEXIS 10 (Pa. Ct. App. 1994).

Opinion

HESTER, Judge:

Fort Worth Heat Treating Co., Inc., formerly Ellwood City Heat Treating, and now Advanced Metallurgical Technology, Inc., appeals from the May 5, 1993 judgment entered by the Lawrence County Court of Common Pleas following a jury trial. The jury found appellant hable to Ellwood City Forge Corporation, appellee, in the amount of $162,500 plus prejudgment interest on a breach of contract claim. Appellant asserts *243 that the trial court erred in denying appellant’s request for judgment notwithstanding the verdict, failing to adequately instruct the jury, and failing to mold the jury’s verdict. We are constrained to reverse and remand.

The record viewed in the light most favorable to the verdict winner reveals the following. Appellee owned, what it believed to be, a 450 kilowatt (“K.W.”) ionitride furnace (hereinafter “furnace”), which uses heat and electrical energy to ionize the surface of a section of metal. The furnace charges the metal, and a plasma with the opposite polarity is applied, thereby binding the plasma to the surface of the metal rendering it much stronger. This process is used to strengthen sections of machinery and also to attach dyes to metal used in manufacturing automobiles. Appellee utilized this relatively new technology as a subsidiary enterprise to its main steel fabricating business but soon discovered the furnace it had acquired was difficult to both operate and maintain, and that the business appellee anticipated obtaining did not materialize or profitably support full-time utilization of the furnace.

Appellee originally came into contact with appellant, headquartered in Fort Worth, Texas, as the result of appellant’s reputation as an expert in operating and repairing ionitride furnaces. Appellee became interested in sub-contracting use of the furnace to appellant since the furnace was not being operated to capacity, and appellee was not realizing a profit from its use. Appellant responded favorably since it had obtained a contract with Chrysler Motor Corp. to ionitride automobile parts and Ellwood City was closer to the center of the automobile industry than Texas. On January 28, 1985, the parties negotiated a written sub-contract agreement (hereinafter the “agreement”), whereby appellant would maintain and operate the furnace (referred to in the agreement as “Equipment”) subject to a number of conditions and terms.

The agreement provided that appellant would use the furnace but reserve at least thirty percent of furnace usage time for appellee during the weekdays, and appellant would provide personnel to operate and maintain the furnace on a twenty-four hour basis. Appellee provided one operator for the *244 weekdays when appellee operated the furnace. For use of the furnace, appellant promised to pay appellee $10,000 per month and thirty percent of the net profits for the five-year term of the agreement. Appellee was responsible under the agreement to provide utilities to power the furnace, including electricity and natural gas, and appellant was to pay for any utilities which exceeded the current utility costs incurred by appellee before net profits were calculated. The agreement included other terms such as insurance provisions and a provision indicating that the agreement was not to be construed as a joint venture or partnership.

The parties experienced difficulties almost from the beginning. Continuous problems were encountered in operating the furnace and in obtaining sufficient heat and electrical power. The furnace could ionitride pieces but not to the' degree appellant desired or anticipated. The parties worked together to resolve the difficulties since each party desired that the other party succeed in the enterprise. Eventually, appellant discovered that the furnace transformers were rated at only 350 K.W., instead of 450 K.W. as set forth on the furnace identification plate. Moreover, the transformers were too old and too worn to provide sufficient power to perform the tasks required by appellant. The parties ultimately determined that the only method to correct the power problem would be to replace the 350 K.W. transformers with 450 K.W. transformers, which would cost approximately $60,000. However, neither party was willing to make this investment. Appellant also encountered fiscal problems and continuously was in arrears in making its rental payments. Appellant eventually abandoned use of the furnace and stopped paying as required in the agreement. Appellee maintained that this breach was due to appellant’s financial difficulties. Appellee further claimed that the furnace was operable, and appellant had assumed responsibility for its operation. Ultimately, appellee filed suit for the balance due under the agreement for the entire term.

Appellant filed an answer and new matter. Appellant contended that the equipment described in the agreement, which *245 included the furnace with 450 K.W. transformers, was not the furnace appellee delivered. Appellant acknowledged that the agreement provided that it was responsible for operating and maintaining the furnace. However, appellant contended that it could not operate and maintain the furnace as required in order to achieve its goals due to the fact that the transformers were underpowered and were not as set forth on the identification nameplate. Appellee regarded the agreement merely as describing whatever the furnace was it purchased and installed in its plant. Appellant, however, concluded that supplying an incorrect and inadequate furnace was a material breach of the agreement by appellee which excused appellant from further payment or performance under the agreement.

Following a trial, the jury rejected appellant’s arguments that the term “power” used in the agreement meant that appellee was responsible for any more than simply delivery of the power to the furnace as supplied by the utility companies. The jury found in favor of appellee for an amount slightly less than the full amount remaining due under the agreement. This appeal followed denial of post-trial motions and entry of judgment. We find merit in appellant’s argument that the trial court improperly denied its request for jury instructions regarding frustration of purpose and commercial impracticability.

We first note that we will not reverse based upon a court’s charge to the jury unless the charge as a whole was in error and prejudiced the complaining party. Schecter v. Watkins, 395 Pa.Super. 363, 577 A.2d 585 (1990). See also Ott v. Buehler Lumber, 373 Pa.Super. 515, 541 A.2d 1143 (1988). In this instance, appellant argues that the underpowered furnace delivered by appellee was not the one it bargained for, and the one supplied by appellee made it commercially impractical to continue to perform under the agreement. Appellant argues it was entitled to these instructions since they are supported by the evidence and the jury could have discharged it from the agreement under these principles.

*246 Appellant, inter alia, requested the following instructions, which were denied by the trial court:

Defendant’s request for jury instruction no. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis, A. v. Borough of Montrose
194 A.3d 597 (Superior Court of Pennsylvania, 2018)
S. Davis-Haas v. Exeter Twp. ZHB and MetroDev V, LP and Exeter Twp.
166 A.3d 527 (Commonwealth Court of Pennsylvania, 2017)
Cornerstone Group XXII, L.L.C. v. Wheat Ridge Urban Renewal Authority
151 P.3d 601 (Colorado Court of Appeals, 2006)
Hart v. Arnold
884 A.2d 316 (Superior Court of Pennsylvania, 2005)
Dole Fresh Fruit Co. v. Delaware Cold Storage, Inc.
961 F. Supp. 676 (D. Delaware, 1997)
Morris v. Lindsay
23 Pa. D. & C.4th 116 (Delaware County Court of Common Pleas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
636 A.2d 219, 431 Pa. Super. 240, 1994 Pa. Super. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellwood-city-forge-corp-v-fort-worth-heat-treating-co-pasuperct-1994.