Ellsworth Builders Supply, Inc. v. Sinclair Builders, Inc.

CourtSuperior Court of Maine
DecidedSeptember 3, 2003
DocketHANre-01-12
StatusUnpublished

This text of Ellsworth Builders Supply, Inc. v. Sinclair Builders, Inc. (Ellsworth Builders Supply, Inc. v. Sinclair Builders, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellsworth Builders Supply, Inc. v. Sinclair Builders, Inc., (Me. Super. Ct. 2003).

Opinion

STATE OF MAINE SUPERIOR COURT HANCOCK, SS. CIVIL ACTION Docket No. RE-01-12

Ellsworth Builders Supply, Inc., Plaintiff

V. Decision and Judgment

Sinclair Builders, Inc. et al., Defendants

Trial in this matter was held on April 17, 2003. At trial, Lawrence R. Sinclair, in his personal and representative capacity, and Terrence E. Pinkham were present with their attorneys. Following the trial, counsel filed written argument that the court has considered.

This action was commenced by Ellsworth Builders Supply, Inc. (EBS). EBS asserted claims against Sinclair Builders, Inc. (SBI) and its principal, Lawrence R. Sinclair (Sinclair), for building materials and supplies that it had sold to the corporate party, payment for which was guaranteed by Sinclair personally. EBS also included claims against Terrence R. Pinkham and his now ex-wife, Nancy S. Pinkham, because some of the material that SBI acquired from EBS was used for construction work on a building owned by the Pinkhams. EBS alleged that the cost of the materials used on the Pinkham job was $25,517.57. A comparison of the entries on the summary of account appended to the complaint and the individual invoices admitted into evidence at trial, see plaintiff's exhibit 41-81, establishes that the amount claimed by EBS against the Pinkhams is included in the larger amount that it sought to recover from SBI and Sinclair. Among other claims, EBS sought to enforce a mechanic’s lien that it purportedly placed

on the property where the building was located. Although the Pinkhams filed a responsive pleading to EBS’ complaint, SBI and Sinclair filed an informal response in which Sinclair wrote that he did not dispute EBS’ claim for the outstanding balance on its account there. This response formed the basis on which EBS moved for judgment on the pleadings. In April 2002, the court granted that motion, and judgment was entered against SBI and Sinclair in the amount of $42,818.25, plus interest and attorney’s fees. This is the same amount that, in its complaint, EBS alleged that SBI and Sinclair owed to it. Neither SBI nor Sinclair filed a cross-claim against either of the Pinkhams.

In January 2003, EBS and SBI and Sinclair entered into a settlement agreement and release regarding the judgment that the court had entered in favor of EBS against the latter two parties. See defendant’s exhibit 1. Under the terms of that agreement, SBI and Sinclair paid EBS the sum of $42,500 in satisfaction of EBS’ claim in this case. The agreement also included comprehensive and mutual releases. The agreement contains the following provision: “Releasor [EBS] hereby assigns to Releasees [SBI and Sinclair] all rights, causes of action and claims that it has or may have against Terrence E. Pinkham and Nancy S. Pinkham, in connection with any and all disputes set forth in Civil Action Docket No. RE-01-12.” That docket number is associated with the proceeding at bar. On the basis of this agreement, SBI and Sinclair successfully moved for substitution of parties. Under the resulting configuration, SBI and Sinclair assumed the role of the plaintiff. Because they did so pursuant to the assignment by EBS of its claims to them, they now may pursue only those claims that EBS could have pursued against the Pinkhams. Because neither SBI nor Sinclair had filed a separate claim against the Pinkhams, any separate rights they may have had have not been raised and thus cannot form the basis for relief now,

By means of a motion to dismiss and on the basis of the trial record, the Pinkhams contend that the agreement between EBS and SBI and Sinclair insulates them from liability to SBI and Sinclair. They argue that any claim that EBS may have had against them was extinguished by the terms of that agreement. As is noted above, EBS’ claim against the Pinkhams was completely subsumed within its claim against SBI and Sinclair. When EBS reached a settlement with SBI and Sinclair and discharged its claim against

them, it also necessarily waived any rights it might have to proceed against the Pinkhams. The amount of the settlement was slightly less than the amount of the balance that EBS alleged was owed on SBI’s account. EBS also sought recovery for attorney’s fees and interest at the contractual rate (18%). The amount of the settlement was well in excess of the amount that EBS claimed was owed to them by the Pinkhams. At the very least, SBI and Sinclair, standing in EBS’ shoes, have failed to demonstrate that any difference between EBS’ total claim and the amount it actually recovered under the settlement can be attributed to any claim against the Pinkhams. Thus, on this record, SBI and Sinclair cannot show that EBS’ claims against the Pinkhams survived the settlement and discharge.’

In effect, SBI and Sinclair seek to use the assignment as a means to pursue a claim for contribution against the Pinkhams. That, however, is an independent theory of liability and was lost when SBI and Sinclair failed to file a cross-claim against the Pinkhams. SBI and Sinclair argue that they could have resolved their claim against EBS earlier or prior to the commencement of this case, and so the release should not operate to bar their right to pursue the assigned claims. As the Pinkhams note, however, the timing of the settlement is immaterial. Instead, the release operated to conclude the larger dispute, of which the claims involving the Pinkhams were merely one part.

Even if EBS’ claims against the Pinkhams survived the execution of its settlement agreement with SBI and Sinclair, those claims would not succeed on their merits. EBS had asserted three claims against or involving the Pinkhams: breach of contract by the Pinkhams as third-party beneficiaries (count 4), unjust enrichment (count 5) and

mechanic’s lien (count 3),

' Presumably, because EBS accepted less than the amount of its full claim against SBI and Sinclair, EBS could have reserved its Claims against the Pinkhams by applying the settlement proceeds to that part of SBI’s accounts that were unrelated to its work for the Pinkhams. EBS did not do so, and thus it is impossible to establish the allocation of the

settlement proceeds among the numerous invoices that were the foundation for the complaint. Third-party beneficiary contract. In count 4, EBS alleged that the Pinkhams were third-party beneficiaries of the contract it had with SBI The complaint alleges that the Pinkhams are liable for the cost of the materials that SBI used to perform construction on their building. The complaint does expressly allege that SBI breached its agreement with EBS. There is no similarly express allegation that the Pinkhams breached a contract, although that allegation may be implied. In support of the viability of this claim, SBI and Sinclair rely on Devine v. Roche Biomedical Laboratories, 659 A.2d 686 (Me. 1995). This authority, however, is inapposite because in that case, the party seeking to enforce contractual rights was not a party to the agreement. Rather, Devine was outside of the contract but attempted to enforce contractual rights as a putative third-party beneficiary, against a party who had entered into a contract. Here, EBS alleged expressly that it sought to have the Pinkhams held liable on the basis of its contract with SBI and Sinclair. Thus, EBS seeks to impose contractual liability on a person who was not a party to the action. This contrasts with the situation in Devine, where a person who was not a party to the contract sought to enforce an obligation that was already imposed on the defendant, because the defendant was a party to the contract.

Devine and a similarly configured case, Fleet Bank of Maine v. Harriman, 1998 ME 275, 721 A.2d 658, rest their third-party beneficiary analysis on the Restatement of Contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George C. Hall & Sons, Inc. v. Taylor
628 A.2d 1037 (Supreme Judicial Court of Maine, 1993)
Fleet Bank of Maine v. Harriman
1998 ME 275 (Supreme Judicial Court of Maine, 1998)
Estate of White
521 A.2d 1180 (Supreme Judicial Court of Maine, 1987)
Durling v. Gould
21 A. 833 (Supreme Judicial Court of Maine, 1890)

Cite This Page — Counsel Stack

Bluebook (online)
Ellsworth Builders Supply, Inc. v. Sinclair Builders, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellsworth-builders-supply-inc-v-sinclair-builders-inc-mesuperct-2003.