Ellithorpe Air-Brake Co. v. Sire

41 F. 662, 1890 U.S. App. LEXIS 2059
CourtU.S. Circuit Court for the District of Southern New York
DecidedMarch 6, 1890
StatusPublished
Cited by1 cases

This text of 41 F. 662 (Ellithorpe Air-Brake Co. v. Sire) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Southern New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellithorpe Air-Brake Co. v. Sire, 41 F. 662, 1890 U.S. App. LEXIS 2059 (circtsdny 1890).

Opinion

Shipman, J.

This is an action at law, which was tried by the court; a trial by jury having been waived by written stipulation signed by the' parties’. ’ Upon- said trial the following facts were found to have been proved, and to be true: The plaintiff is, and was at the commencement of this suit, a corporation duly incorporated under and by virtue of the laws of the state of Illinois, and located in and an inhabitant of Chicago, in said state, where it has and continuously has had its principal place of business. The defendant is, and was at the commencement of this suit, a citizen of the state of New York, and a resident and an inhabitant óf New’York city, in the southern district of said state. The’ plaintiff is a manufacturer of elevators. On or about October 1, 1888,the plaintiff and defendant entered into a written contract whereby the plaintiff agreed to furnish and erect for the defendant, in a good, substantial, and workman-like manner, two hydraulic passenger elevators in his double [663]*663apartment or flat buildings on Fifty-Ninth street, opposite Central park, and known as the “East and West Flats,” and two safety steam passenger elevators, — one in the adjoining residence building on Fifty-Ninth street, and one in the office building corner of Center and Reade streets, — all in the city of New York; making in all four elevators, with the appurtenances and appliances as specified and agreed upon, ready for use in 80 to 90 days from date of receipt of approved plans, for the sum of $6,750; one-half thereof to be due and payable when the machines were in the buildings, and the other half thereof to be paid when the said elevators were up, and in complete running order; payments to be made upon the written order of the plaintiff, provided the defendant should he satisfied with the amount, as the work progressed. The plaintiff, in its complaint, avers that it complied with the terms and conditions on its part to he performed, and erected, and completed in runningorder, the elevator in the West flat, and very nearly completed the erection of the elevator in the East flat, when the prosecution of the work was stopped and prohibited by the defendant; that the steam elevators were ready for shipment, but the defendant requested that they should not be shipped from Chicago, but should remain there in store until he should decide upon some proposed changes, all of which was done, and that they remained subject to his order; that he has never ordered the same to be shipped, although the plaintiff has been ready to do so, and to comply with the contract. The complainant also alleged that it had suffered special damage by reason of obstructions and hindrances by the defendant to the rapid prosecution of said work, and had incurred extra expense for insurance and storage of the property. The sum of $1,900 was paid by the defendant upon the contract. The defendant alleges in his answer that the plaintiff wholly neglected and failed to perform its contract, and also sets up a counter-claim for damages arising from such neglect.

The finding of facts in this case is made difficult by the complete antagonism of the witnesses for the respective parties to each other in regard to almost every important fact in'the case. This diversity commences with the terms of the written contract; the respective copies which are produced by the parties being unlike. Quite an important part of the terms of payment contained in the printed proposals of the plaintiff is erased in the defendant’s copy, and upon the question whether this erasure was made by consent or wrongfully the parties are at variance. I am convinced of the honesty of each of the witnesses God-win and A. B. Ellithorpe, whose testimony upon this point is not reconcilable. The weight of the testimony leads to the conclusion that the contract, which has been heretofore stated, and which is known in the case as “Exhibit D,” was the one which was made. Exhibit C was made in the manner and at the time stated by A. B. Ellithorpe.

On October 28, 1888, A. B. Ellithorpe, the plaintiff’s general manager, came to. New York with Frank Roche, his foreman, and on the next day saw the defendant, and the different buildings in which the elevators were to be placed. Roche did not commence work until December 20.th, when he began in the apartment, house on Fifty-Ninth street. [664]*664During a portion, at least, of his time, he was at work in the erection of elevators for other people. The reason which is given by the plaintiff for this delay is that the Fifty-Ninth street cellars and the hatchways were not ready for the elevators, and that it was practically impossible to commence sooner. There may have been some ground for this assertion on the very first few days of November, but the extent and the duration of this alleged cause are very much exaggerated. The important reason was that the machinery was not completed in Chicago. This conclusion is based upon the correspondence. On November 28, 1888, the plaintiff' wrote the defendant as follows: ,

“"We to-day send you design of ears for your passenger elevator for your approval; all cars t,o be of the same design. Please approve and return same, so that they may be put under way. The hydraulic engines are under way, and will soon be ready to ship.”

On November 30th the defendant wrote the plaintiff requesting an interview in regard to the Center and Reade street elevator, to which the plaintiff replied, on December 3d: “Your elevators are being pushed with all possible dispatch;” and, in regard to the Center-Street elevator, that it was waiting the defendant’s decision in regard to his option as to the kind of machine which he would take. At the date of this letter the machines were, manifestly, not ready in Chicago. The machinery for the hydraulic elevators reached New York about December 22, 1888. While this delay existed, and its chief cause is to be attributed to the plaintiff, the defendant was not particularly burdened or annoyed by it. He was not at that time, apparently, anxious for the speedy completion of his houses. The plaintiff prosecuted its work in the apartment houses with some breaks, occasioned, to a very limited extent, by the fact that its workmen were at times hindered by the use of the stairways by the defendant’s workmen. On January 24,1889, it drew upon the defendant for $1,500, which draft was returned protested; and then it stopped work on account of this non-payment. On January 31st the defendant complained by letter of this cessation, which he said was not in accordance with the'contraot. The plaintiff replied on February 2d, claiming compliance, and on February 8th the defendant agreed in writing to pay $1,-500 on account, “as per contract,” immediately after the elevator in the West flat was running. Work was then resumed, and the elevator in the West flat was completed March 6th, and the $1,500 were paid in accordance with the agreement of February 8 th. .At this time the work upon the elevator in the East flat was nearly done. The only remaining work was to place the car in position, and to connect with it the cables, sheaves, and fittings. The car and these articles were in the cellar, ready to be put up. Two weeks’ work would have completed the elevator.

The design for all the cars was sent to the defendant for his approval by letter of November 28th, which-has been heretofore quoted. The contract specified that the design was to be submitted for approval. The other plans had been approved. The defendant did not reply by letter-, but in January the general manager of the plaintiff saw him in New York-on the subject.. He did not dissent to the design, and cars for the apart

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Decatur County v. Praytor, Howton & Wood Contracting Co.
137 S.E. 247 (Supreme Court of Georgia, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
41 F. 662, 1890 U.S. App. LEXIS 2059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellithorpe-air-brake-co-v-sire-circtsdny-1890.