Ellis v. Brenner

34 So. 2d 633, 1948 La. App. LEXIS 427
CourtLouisiana Court of Appeal
DecidedApril 1, 1948
DocketNo. 7162.
StatusPublished
Cited by4 cases

This text of 34 So. 2d 633 (Ellis v. Brenner) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellis v. Brenner, 34 So. 2d 633, 1948 La. App. LEXIS 427 (La. Ct. App. 1948).

Opinion

The primary question tendered in this case is the right of the plaintiff, the lessee of the defendants, to recover from them the amount necessarily expended by him to install a new electrical system in the leased premise to replace the old and antiquated one that had almost entirely ceased to function.

Defendants resist the suit mainly upon the ground that they were not notified of the necessity to have the new system installed and that, as a condition precedent to their liability for the expense of the new work, they should have had opportunity to have the work done themselves, which opportunity they did not have.

Defendants appealed from judgment that sustained plaintiff's contention.

The leased premise involved herein is identified as being the ground floor of the brick building at municipal numbers 865-867 Texas Street in the City of Shreveport, Louisiana. Plaintiff had occupied the premise under leases from the defendants for some four years prior to the time the electrical system failed. This occurred on July 2, 1947. The efficient conduct of his business requires dependable electrical current to operate the many motors and other equipment employed by him. The electric system, installed in the building, some fifteen or twenty years ago, was considered adequate for all practical purposes at that time, but, under the heavy load it was required to carry to meet plaintiff's needs, it gradually deteriorated until three circuits of the four "went out." This, so long as it continued, paralyzed plaintiff's business activities.

Plaintiff promptly called Frank Parker, an experienced electrician, and, thinking the trouble could be easily remedied, asked him to do what was necessary to restore the current. Parker found that the service equipment had "burned up * * * melted down." It could not be fixed. He then put in what he described as a weather proof socket" which was designed to, and in fact did, temporarily restore the current. Thereafter, he discussed the matter with the city electrician and was informed that as the old system was obsolete and would not provide the maximum security against fire hazard, a modern system of greater capacity would have to be installed in order to pass inspection. This, it is shown, was required by the laws and regulations of the city. However, to meet this requirement it was not necessary to re-wire the leased part of the building.

While there is dispute as to the date when Parker returned to plaintiff's place of business and informed him of the situation with respect to the city's requirements, we are convinced it was on the 9th or 10th of July. Plaintiff inquired about the cost of the new work and was informed that it would be about $100. He then, in the presence of the electrician, called the office of Mr. Alphonse Brenner, who with his sister, Mrs. Bertha B. Florsheim, are the owners and lessors of the property, for the purpose of discussing the matter with him, and of procuring his consent to the expenditure necessary to put in the new system. Mr. Brenner was then absent from the city and would not return for a week, according to information given plaintiff by someone in his office. Without further delay or effort to contact the lessors, plaintiff had Parker do the final work at a cost of $97.50.

We base our conclusion that it was on July 9th or 10th when Parker reported to plaintiff what would have to be done to meet the city's inspection, at which time plaintiff endeavored to get in touch with Mr. Brenner, upon the following facts, to-wit:

The bill of the electrician for services rendered shows a charge of $3.50 on July 2nd for temporary repairs and also shows a charge of $97.50 on July 11th for permanent work and repairs. Mr. Parker is quite sure this bill is correct in all respects, although the secretary of his company prepared it. The permanent work required about one and one-half days. If it began on the 10th it was concluded on the 11th. *Page 635 If begun on the 9th, it was finished on the 10th. Mr. Brenner left Shreveport for Chicago on July 8th, and returned one week later. Since he was not in the city when called on the telephone by plaintiff, it follows that the call was made after the 8th of July and before the 11th.

There is no doubt that what was done to the electrical system was indispensable, within the meaning of the law pertinent to such matters. Without it the fire hazard would be greatly increased and, in addition, to meet the city's requirements such a system had to be installed.

It is not suggested that plaintiff did not act in perfect good faith in proceeding as he did to have a safe and dependable current provided; nor is it suggested that the cost of the new system was excessive.

The lessors well knew the purpose for which plaintiff leased the property and the use to which he had put the same during his occupancy of it.

R.C.C. Article No. 2692, enumerating some of the obligations of the lessor, numbers the following, viz.:

"To maintain the thing in a condition such as to serve for the use for which it is hired."

Article No. 2693 of the R.C.C. reads as follows:

"The lessor is bound to deliver the thing in good condition, and free from any repairs. He ought to make, during the continuance of the lease, all the repairs which may accidentally become necessary; except those which the tenant is bound to make, as hereafter directed."

Repairs, the cost of which are imposed upon the lessee, are listed in Article No. 2716 of the R.C.C. These do not cover, expressly nor by implication, the sort of repairs and improvements involved in this case. This being true, of course, the duty to make or pay for the costs thereof, rests upon the lessor. However, Article No. 2694 of the R.C.C., relied upon by defendants to escape reimbursement to plaintiff, reads:

"If the lessor does not make the necessary repairs in the manner required in the preceding article, the lessee may call on him to make them. If he refuses or neglects to make them, the lessee may himself cause them to be made, and deduct the price from the rent due, on proving that the repairs were indispensable, and that the price which he has paid was just and reasonable."

The lease contract between the parties does not derogate from the provisions of this article.

The contract of lease in effect when the electric system failed, and the one preceding it, were negotiated by plaintiff and Mr. Brenner who admits that he acted as Mrs. Florsheim's agent, although the contract itself was actually signed by her son as her agent. Plaintiff was not acquainted with Mrs. Florsheim at the time nor with her son. In every instance when repairs to the leased premises were necessary he consulted Mr. Brenner only, and invariably he was authorized by him to have the repairs made at the lessors' expense. In view of this course of conduct, it was but natural that plaintiff first sought to discuss the matter with Mr. Brenner. But, the question arises: Was he not required to go further under the law in order to be in a position to hold the lessor responsible for the repair bill? While it is true plaintiff did not personally know Mrs. Florsheim, he did know she lived in Shreveport because he monthly paid directly to her one-half of the monthly rent. In addition to this, Mr. Brenner was not so far away that he could not have been contacted by telephone before the repairs were made by plaintiff.

It is true, as contended by defendants, that the jurisprudence of this state abounds in cases that strictly construe and enforce Article No. 2694 of the R.C.C. as written. The earliest case on the subject by the Supreme Court is that of Scudder v. Paulding, 4 Rob. 428, and the last one, so far as we have been able to discover, is Hartz v. Stauffer et al.,163 La. 382

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G. Woodward Jackson Co., Inc. v. Crispens
414 So. 2d 855 (Louisiana Court of Appeal, 1982)
Brignac v. Boisdore
288 So. 2d 31 (Supreme Court of Louisiana, 1973)
Teekell v. Drewett
103 So. 2d 525 (Louisiana Court of Appeal, 1958)
Barrow v. Culver Bros. Garage
78 So. 2d 69 (Louisiana Court of Appeal, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
34 So. 2d 633, 1948 La. App. LEXIS 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellis-v-brenner-lactapp-1948.