Elliott v. Ganley Dodge, Unpublished Decision (4-28-2005)

2005 Ohio 1991
CourtOhio Court of Appeals
DecidedApril 28, 2005
DocketNo. 84970.
StatusUnpublished
Cited by1 cases

This text of 2005 Ohio 1991 (Elliott v. Ganley Dodge, Unpublished Decision (4-28-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elliott v. Ganley Dodge, Unpublished Decision (4-28-2005), 2005 Ohio 1991 (Ohio Ct. App. 2005).

Opinion

JOURNAL ENTRY and OPINION
{¶ 1} Defendant-appellant, Ganley Dodge, Inc. ("Ganley"), appeals the trial court's decision granting judgment in favor of plaintiff-appellee, Donald M. Elliott ("Elliott"), as Trustee under the Trust Agreement dated August 9, 1963. Finding merit to the appeal, we reverse and remand for the entry of judgment for Ganley on its counterclaim.

{¶ 2} In May 2003, Elliott filed a complaint alleging that Ganley breached the terms and conditions of its lease by failing to restore various items on the premises, specifically automobile lifts, heaters, and air compressors. In claim two of Elliott's complaint, he recognized that because Ganley had prepaid the rent for November 2001 and vacated the premises on November 15, Ganley was entitled to a setoff of $3,838.68. Ganley filed a counterclaim for the $3,838.68 in prepaid rent.

{¶ 3} Each party's motion for summary judgment was implicitly denied when the trial court conducted a hearing on the matter at which the following evidence was presented.

{¶ 4} In 1978, Elliott and Ganley entered into an Agreement of Lease ("Lease") for the premises at issue. The Lease was subsequently renewed in 1992/1993, with termination scheduled in December 2002. Pursuant to Article VI, Paragraph 1, Ganley agreed to maintain the premises in "as good condition and repair as at the beginning of the term hereof."

{¶ 5} In 2001, Ganley contacted Elliott to terminate the Lease early. Elliott then contacted the City of Bedford ("City") to inspect the premises in order to determine what repairs were needed. In August 2001, the City and Elliott inspected the premises. Elliott claimed that they were unable to inspect the automobile lifts because cars were on them. He admitted that they did not inspect the overhead heaters because "[I]t was fall. It was warm. We had no reason to look at or ask questions about overhead heaters, which were in the service department." They also did not inspect the back room because it was filled with automobile and truck parts. Rick Heller ("Heller"), Ganley's general manager, testified that he was not contacted regarding the inspection, nor did he meet with the City inspector or Elliot during the inspection.

{¶ 6} The City issued a Certificate of Inspection ("Certificate"), noting approximately 21 repairs that were needed. The Certificate did not mention any problem with the automobile lifts, heaters, or air compressors.

{¶ 7} In October 2001, Elliott met with Jonathan Berns ("Berns"), an employee of The Structure Group, which Ganley hired to repair the cited violations, and John Hochberg, the project manager for The Structure Group. At the meeting, they discussed the repairs that were to be made to the premises. Berns testified that, "It was very vague in what repairs were to be done. And then we discussed using the inspection as one way of identifying in a concrete manner what the repairs were to be done." He further testified that he and Elliot walked around the property on several occasions. Heller testified that at the meeting, no one indicated that the heaters or lifts needed repair or inspection.

{¶ 8} As a result of the meeting, a Lease Termination and Mutual Release Agreement ("Release") was executed by both parties in November 2001. The Release recognized that "disputes exist between the parties concerning the scope of their respective obligations to make the repairs to the Properties sought by the City and similar repairs." The Release provided that Ganley would make all repairs indicated in the Certificate as well as deliver the property to Elliott "in the condition required under the terms of the Lease." In return, Elliott allowed Ganley to terminate the Lease prior to the termination date.

{¶ 9} The Release further provided that Elliott release and hold Ganley harmless "from any and all claims, demands, causes of action, liabilities, damages, attorneys' fees and expenses, whatsoever, whether in law or equity, whether known or unknown, which such party may now have or which such party may have in the future, including, but not limited to, any and all claims whatsoever relating to Lessee's use or occupation of the Properties and any and all obligations under the Leases other than those set forth in paragraph 2 hereof."

{¶ 10} The Structure Group began work on the premises in late fall 2001. All projects were completed by November, except for asphalt repair, which was postponed until early summer 2002. In July 2002, after all violations were corrected, Elliott signed an Acknowledgment recognizing that Ganley had fulfilled all of its obligations under the Release.

{¶ 11} The trial court granted judgment in favor of Elliott. Although not specifically stated in its judgment entry, we presume that it granted Elliott's second claim and Ganley's counterclaim because the total judgment was set off by Ganley's counterclaim of $3,838.68, leaving a final judgment for Elliott in the amount of $6,192.45. Neither party has appealed the disposition of Elliott's second claim and Ganley's counterclaim.

{¶ 12} Ganley appeals the trial court's decision, raising two assignments of error, which will be addressed together.

{¶ 13} In its second assignment of error, Ganley argues that the trial court committed reversible error in ruling that the Acknowledgment was invalid and that the Release was presumably void or invalid. Because of such error, Ganley argues in its first assignment of error that the trial court should have granted its motion for summary judgment.

{¶ 14} Appellate review of summary judgment is de novo. Grafton v.Ohio Edison Co., 77 Ohio St.3d 102, 105, 1996-Ohio-336, 671 N.E.2d 241;Zemcik v. La Pine Truck Sales Equipment (1998), 124 Ohio App.3d 581,585, 706 N.E.2d 860. The Ohio Supreme Court set forth the appropriate test in Zivich v. Mentor Soccer Club, 82 Ohio St.3d 367, 369-370,1998-Ohio-389, 696 N.E.2d 201, as follows:

Pursuant to Civ.R. 56, summary judgment is appropriate when (1) there is no genuine issue of material fact, (2) the moving party is entitled to judgment as a matter of law, and (3) reasonable minds can come to but one conclusion and that conclusion is adverse to the nonmoving party, said party being entitled to have the evidence construed most strongly in his favor. Horton v. Harwick Chem. Corp., 73 Ohio St.3d 679, 1995-Ohio-286,653 N.E.2d 1196, paragraph three of the syllabus. The party moving for summary judgment bears the burden of showing that there is no genuine issue of material fact and that it is entitled to judgment as a matter of law. Dresher v. Burt, 75 Ohio St.3d 280, 292-293, 1996-Ohio-107,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coburn v. Auto-Owners Insurance
938 N.E.2d 400 (Ohio Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 1991, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elliott-v-ganley-dodge-unpublished-decision-4-28-2005-ohioctapp-2005.