Elliott Grisell and Lorri Grisell v. Shelly & Sands, Inc.

CourtWest Virginia Supreme Court
DecidedNovember 6, 2023
Docket22-0341
StatusPublished

This text of Elliott Grisell and Lorri Grisell v. Shelly & Sands, Inc. (Elliott Grisell and Lorri Grisell v. Shelly & Sands, Inc.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elliott Grisell and Lorri Grisell v. Shelly & Sands, Inc., (W. Va. 2023).

Opinion

STATE OF WEST VIRGINIA SUPREME COURT OF APPEALS FILED Elliott Grisell and Lorri Grisell, November 6, 2023 Plaintiffs Below, Petitioners released at 3:00 p.m. EDYTHE NASH GAISER, CLERK SUPREME COURT OF APPEALS vs.) No. 22-0341 (Marshall County 19-C-187) OF WEST VIRGINIA

Shelly & Sands, Inc., Defendant Below, Respondent

MEMORANDUM DECISION

Petitioners Elliott and Lorri Grisell appeal the Circuit Court of Marshall County’s April 5, 2022, order granting summary judgment in favor of Respondent Shelly & Sands, Inc. in this negligence action stemming from the slipping of petitioners’ property upon which respondent deposited, leveled, and graded fill material at the behest of the property’s previous owner some four years earlier. Upon our review, we find no error and, accordingly, affirm the circuit court’s order. 1

I. Facts and Procedural History

In 2016, petitioners purchased approximately 6.7 acres of real property located in Glen Dale, Marshall County, from Alfred and Susan Renzella. In 2012, while respondent was performing a local highway improvement project for the West Virginia Division of Highways, Mr. Renzella entered into a Waste Agreement with respondent whereby, at no cost to Mr. Renzella, respondent agreed to deposit on his property surplus excavation and demolition materials “of whatever form, content or nature encountered by [respondent], in the performance of its project excavation and demolition operations (exclusive of any hazardous materials).” It was also agreed that respondent would deposit the materials “at such place or places [on the property] as is deemed desirable in the judgement of [respondent] to facilitate the depositing of the Materials,” and that respondent would not be responsible “for damages or diminution in value resulting to the Premises by reason of . . . the consequences of the placement of the Materials upon the Premises.”

Petitioners appear by counsel Eric M. Gordon. Respondent is represented by 1

counsel Adam M. Barnes.

1 Respondent’s foreman and signator to the agreement, Terry LePage, agreed to “level up waste site + grade slope.”

Prior to selling the property to petitioners, Mr. Renzella informed them that fill material had been placed on the property and, without disclosing the make-up of the material, assured them that the work had been done properly. Petitioners hired an independent excavator to inspect the property to determine if the land was suitable for building a garage or pool. Although the inspector advised petitioners not to build on top of the land for a few more years, petitioners did not have any concerns about the property and proceeded to purchase it.

Beginning in June of 2017, petitioners began noticing cracks in the property, and on July 28, 2017, during a heavy rainstorm, the area became saturated and slipped downhill. The fill material damaged petitioners’ property 2 and encroached upon the property of their neighbor, damaging and knocking over trees.

Petitioners subsequently filed suit, alleging in their Amended Complaint that respondent 3

spread the material on the property in a negligent and improper manner, not up to the reasonable and customary standards of a contractor, and in a manner not fit for the purpose for which it was placed on the property, by spreading the material over a natural freshwater spring and not redirecting the same, and by blocking previously installed drains and/or culverts that previously captured water runoff, allowing the area encompassing the material to become saturated.

[Respondent] owed a duty when placing the material on the property to do so as a reasonable and prudent contractor and in a manner fit for the particular purpose for which it was placed upon the property. [Respondent] further owed a duty in placing the material on the property to do so in a manner that

Petitioners’ residence was not damaged by the slip. 2

The West Virginia Department of Transportation, Division of Highways, was also 3

named as a defendant, but was later dismissed.

2 would not cause damage to the property or adjacent properties. [ 4]

Mr. LePage testified that the waste material from the excavation project consisted of dirt, concrete, and rock and that Mr. Renzella “wasn’t picky about what was being delivered to his property.” He further testified that the City of Glen Dale and the Marshall County School District dumped fill material onto the property both before respondent began dumping and, “occasionally[,] while [he] was there.” According to Mr. LePage, Mr. Renzella directed where he wanted the material dumped on the property; Renzella never objected “that something was dumped where it shouldn’t have been;” and Mr. Renzella never complained about the manner in which the dumped fill was leveled up or how the final sloping was done. Mr. LePage denied covering up the culvert that ran under the road with fill material, testifying that “[t]he culvert was clear.” At one point, Mr. LePage observed water coming out at the toe of the slope where the fill material had been placed and acknowledged that was “going to be an issue over time.” At Mr. Renzella’s request, Mr. LePage addressed the issue by placing stone “[r]ight at the edge so the water would run through the rock on down in the ditch.” Mr. LePage denied that he agreed to terrace the property and confirmed that “it was just going to be a slope.”

Stephen Rogers, a project manager for an excavation firm and petitioners’ designated expert “in the field of land slip mitigation and repair,” testified that he visited the property after the slip occurred to prepare a repair estimate and that his company cleaned out two culverts that “went under the road” and a ditch along the driveway. He testified that one of the culverts “was blocked on the end. And then the culvert backed up and material from the upper side had washed down in it and plugged it up.” However, Mr. Rogers could not determine why the second culvert “was blocked or otherwise not working as desired.” Mr. Rogers conceded that neither he “[n]or anyone at [his] company performed any kind of analysis to determine whether the slip happened because of the water, or the slip happened because of the content of the fill, or some combination, or some other factor.” Although Mr. Rogers initially indicated that he would not testify at trial “as to what caused the slip to happen” or “why [respondent] might be responsible for why the slip happened,” a later-submitted Plaintiffs’ Designation of Expert Witness stated that Mr. Rogers would opine that the cause of the slip was due to (1) the existing culverts being blocked by the fill material, which caused the ground to become “saturated with the weight of the material causing the ground to become unstable thereby resulting in it moving” and (2) respondent’s failure to install any or sufficient drainage to carry water from the area where the fill was installed on the property.

Petitioners were unaware that a written Waste Agreement existed at the time they 4

filed suit.

3 On October 21, 2021, respondent filed a motion for summary judgment. It argued that it performed its duty pursuant to the Waste Agreement and “in accordance with Mr. Renzella’s directives and to his satisfaction;” that there was evidence that other entities also dumped material on the property both before and during the same period of time as respondent; and that, contrary to petitioners’ claim that respondent covered a natural freshwater spring and blocked existing drains and culverts, causing the filled property to slip, the only evidence on this point was Mr. LePage’s testimony that the culvert was clear.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Precision Coil, Inc.
459 S.E.2d 329 (West Virginia Supreme Court, 1995)
Parsley v. General Motors Acceptance Corp.
280 S.E.2d 703 (West Virginia Supreme Court, 1981)
Painter v. Peavy
451 S.E.2d 755 (West Virginia Supreme Court, 1994)
Sewell v. Gregory
371 S.E.2d 82 (West Virginia Supreme Court, 1988)
Wheeling Park Commission v. Joseph and Kerry Dattoli
787 S.E.2d 546 (West Virginia Supreme Court, 2016)
Dicken v. Liverpool Salt & Coal Co.
23 S.E. 582 (West Virginia Supreme Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
Elliott Grisell and Lorri Grisell v. Shelly & Sands, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/elliott-grisell-and-lorri-grisell-v-shelly-sands-inc-wva-2023.