Elliot Megdal & Associates v. Hawaii Planing Mill, Ltd.

814 F. Supp. 898, 1993 U.S. Dist. LEXIS 2239, 1993 WL 49593
CourtDistrict Court, D. Hawaii
DecidedFebruary 23, 1993
DocketCiv. 91-00630 DAE
StatusPublished
Cited by5 cases

This text of 814 F. Supp. 898 (Elliot Megdal & Associates v. Hawaii Planing Mill, Ltd.) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elliot Megdal & Associates v. Hawaii Planing Mill, Ltd., 814 F. Supp. 898, 1993 U.S. Dist. LEXIS 2239, 1993 WL 49593 (D. Haw. 1993).

Opinion

ORDER GRANTING IN PART AND DENYING IN PART DEFENDANT’S MOTIONS FOR PARTIAL SUMMARY JUDGMENT

DAVID ALAN EZRA, District Judge.

The Court heard Defendant’s Motions for Partial Summary Judgment on February 8, 1993. Mark J. Bennett, Esq. appeared on behalf of plaintiffs. Thomas Sylvester, Esq. and Mark Fox, Esq. appeared on behalf of defendant. After reviewing the motions, the Memoranda in Support Thereof and in Opposition Thereto, and hearing oral argument, the Court GRANTS IN PART and DENIES IN PART Defendant’s Motions for Partial Summary Judgment.

I. Background

On August 8, 1989, Elliot Megdal and Associates (“Megdal”) entered into a contract with Stephenson Construction (“Stephenson”) for the construction of a shopping center, the Kopiko Plaza, on property owned by Megdal in Kona, Hawaii (“the contract”). Megdal contracted, with Stephenson on the recommendation of John Parazette, the architect for the building.

Under the terms of the contract, the supply and erection of the steel building to be used for the Kopiko Plaza, as well as the electrical work, was to be handled on an allowance basis. That term was used, in contrast to a fixed-price basis, to mean that the price for the allowance items was to be determined on the basis of a post-contractual calculation of actual costs. The total scheduled value of the contract was $2,265,000. Megdal had earlier rejected Stephenson’s proposal of a fixed-price contract for $2,365,-000.

Megdal obtained financing from First Hawaiian Bank. As a condition of the loan agreement, Megdal was obliged to secure a performance and payment bond of value equal to the cost of the structure. Megdal secured such a bond from Hawaii Planing Mill, Ltd. (“HPM”) for a premium of $23,594. That sum was apparently calculated as one percent of $2,265,000 plus tax.

Subsequently, Megdal, Stephenson, and Panzetta agreed to a change order designating Engineered Structures, Inc. (“ESI”) to provide the steel structure, and Central Steel Construction (“CSC”) to erect it. CSC contracted to do all of the project erection for approximately $150,000, roughly the same amount as the allowance that had been made for those services under the contract. In *901 1990, CSC left the job and did not complete the work. That default is the source of this dispute.

The departure of CSC made it clear that the project would not be completed on time. Megdal and Stephenson each contended that the other was responsible for any damages suffered as a result of the delay caused by CSC’s default. Pursuant to the terms of the contract, which was a standard form agreement of the American Institute of Architects and contained a compulsory arbitration clause, Stephenson filed a demand for arbitration on June 12, 1990. Megdal filed a counterclaim on August 3, 1990 seeking, among other relief, delay costs and consequential damages.

On July 25, 1990, Megdal informed HPM that Stephenson had defaulted and demanded, pursuant to the bond agreement, that HPM pay all additional costs incurred by Megdal as a result of the delay. HPM responded that it would take no action prior to the arbitrator’s ruling. Richard Miller, an attorney for Megdal, issued, and HPM declined, an invitation for HPM to participate in the arbitration. Sometime thereafter, Megdal demanded that Stephenson and HPM remedy certain punchlist work such as alleged defects in the roof and sewer lines. HPM refused contending they were not responsible.

The arbitrator’s award was handed down on May 15, 1991. Precisely how that award is to be interpreted is also a disputed matter, but the award clearly requires Megdal to pay Stephenson $175,664.

On May 17, Stephenson filed a motion in the First Circuit Court of the State of Hawaii to confirm the arbitration award pursuant to Haw.Rev.Stat. §§ 658-8 and 658-12 (1985). Megdal filed a separate motion to clarify the award, contending that the award was ambiguous as to whether Stephenson was excused from performing the punchlist work. Stephenson contended that Megdal was es-topped from arguing the punchlist issue since it ought to have been litigated in the arbitration. The court granted Stephenson’s motion and denied Megdal’s. Thereafter, Megdal paid Stephenson the amount awarded and a satisfaction of judgment was filed September 11, 1991.

Megdal commenced this action on November 11,1991 alleging fraudulent misrepresentation (count I), negligent misrepresentation (count II), breach of contract (count III), tortious interference with contract and tor-tious conduct (count IV), unjust enrichment (count V), insurance code violations (count VI), and punitive damages (count VII). HPM filed separate motions for partial summary judgment on count III and all other counts.

II. Standard of Review

Rule 56(c) of the Federal Rules of Civil Procedure provides that summary judgment shall be entered when:

... the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

The moving party has the initial burden of “identifying for the court those portions of the materials on file that it believes demonstrate the absence of any genuine issue of material fact.” T.W. Elec. Serv., Inc. v. Pacific Elec. Contractors Ass’n, 809 F.2d 626, 630 (9th Cir.1987) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986)). The movant must be able to show “the absence of a material and triable issue of fact,” Richards v. Neilsen Freight Lines, 810 F.2d 898, 902 (9th Cir.1987), although it need not necessarily advance affidavits or similar materials to negate the existence of an issue on which the nonmoving party will bear the burden of proof at trial. Celotex, 477 U.S. at 323, 106 S.Ct. at 2552. But cf., Id., at 328, 106 S.Ct. at 2555 (White, J., concurring).

If the moving party meets its burden, then the opposing party may not defeat a motion for summary judgment in the absence of any significant probative evidence tending to support his legal theory. Commodity Futures Trading Comm’n v. Savage, 611 F.2d 270, 282 (9th Cir.1979). The opposing party cannot stand on his pleadings, nor can he simply assert that he will be able to discredit the *902 movant’s evidence at trial. See T.W. Elec., 809 F.2d at 630. Similarly, legal memoranda and oral argument are not evidence and do not create issues of fact capable of defeating an otherwise valid motion for summary judgment. British Airways Bd. v. Boeing Co., 585 F.2d 946, 952 (9th Cir.1978),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

COHEN v. SUBARU CORPORATION
D. New Jersey, 2022
Sung v. Hamilton
710 F. Supp. 2d 1036 (D. Hawaii, 2010)
Wailua Associates v. Aetna Casualty & Surety Co.
27 F. Supp. 2d 1211 (D. Hawaii, 1998)
Nevada Power Co. v. Monsanto Co.
891 F. Supp. 1406 (D. Nevada, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
814 F. Supp. 898, 1993 U.S. Dist. LEXIS 2239, 1993 WL 49593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elliot-megdal-associates-v-hawaii-planing-mill-ltd-hid-1993.