Elkhorn & Beaver Valley Railway Co. v. Dingus

220 S.W. 1047, 187 Ky. 812, 1920 Ky. LEXIS 211
CourtCourt of Appeals of Kentucky
DecidedApril 27, 1920
StatusPublished
Cited by4 cases

This text of 220 S.W. 1047 (Elkhorn & Beaver Valley Railway Co. v. Dingus) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elkhorn & Beaver Valley Railway Co. v. Dingus, 220 S.W. 1047, 187 Ky. 812, 1920 Ky. LEXIS 211 (Ky. Ct. App. 1920).

Opinion

Opinion op the Court by

Judge Hurt

Beversing.

This appeal is from a judgment in favor of the appellee, D. C. Dingus, against the appellant, Elkhorn and Beaver Valley Bailway Company, for an alleged breach by the latter of a contract, which it had entered into with the former for the erection and maintenance of a depot upon its line of railroad, between Beaver Creek and Wayland, upon a parcel of land, which had been conveyed to the Bailway Company by Dingus. Dingus owned a tract of land at the place and the parcel conveyed by him was a portion of the tract and was conveyed to the railway company for a right-of-way over which it proposed to construct and operate its 'railroad and upon which to erect and maintain a depot and necessarily to make a stopping place for its trains. The deed by which the conveyance was made was executed in the year 1911 and the consideration for its execution recited was “one dollar and other good .and valuable considerations.” The deed, also, contained the following stipulations: “The Elkhorn and Beaver Valley Bailway Company agrees to build a depot on the strip of land herein conveyed,” and, “It is understood that the foregoing strip or parcel of land is purchased for the purpose of construction and operating thereon a standard gauge railroad and facilities appurtenant thereto.” The habendum contained a clause of general warranty.

[814]*814The action was begun on the 21st clay of April, 1915, by a petition, which averred, that the railway company, as the consideration for the sale and conveyance of the strip of land, covenanted, that, as soon as its road was built and ears operating thereon, it would erect a depot upon the land conveyed, and make a stopping place thereon for its trains and maintain same thereafter. It was, also, averred that, although the railway company had long since constructed its road' over the land and had been operating its trains thereon for more than a year, it had wholly failed to comply with its contract to erect and maintain a depot upon the land, and by reason of its failure so to do, he, Dingus, had suffered large damages in the loss of the enhanced value, which would have accrued to the residue of his lands from the erection and maintenance of the depot. The railway admitted its obligation to erect and maintain a depot upon the land conveyed to it, but denied that it had failed to do so within the time provided, by the contract for the erection of the depot, or that the residue of the lands of Dingus had failed to appreciate in value on that account, or that he had suffered any damages; but, affirmatively alleged that it had fully complied with the contract by the erection of a depot upon the land within a reasonable time after the construction of its road. Dingus by a reply admitted that after the institution of his action the railway company had pretendedly, only, complied with its contract by the erection of a depot, but, averred that the building was too small, temporary, inadequate, and not such a depot as was contemplated by the contract, and therefore denied that the railway company had complied with the contract.

The trial resulted in a verdict by the jury in favor of Dingus and a judgment in accordance therewith. The railway company’s motion for a new trial being overruled, it seeks a reversal of the judgment upon several grounds of which it is not necessary to consider any, except its contention that the court erred to its prejudice in giving and refusing instructions to the jury and in the admission of incompetent evidence against it upon the trial.

(a) The instructions of the court to the jury were erroneous, in that they submitted issues which did not exist, either in the pleadings or in the evidence. They were furthermore so drawn as to submit to the jury and [815]*815leave it to determine for itself what the contract was, as well as what constituted a breach of it, and thus left to the jury to determine what the law of the case was, am well as the facts. The instruction by which it was attempted to define the measure of damages was involved, confusing, and misleading, and applied oily to the measure of damages in such character of a case, when there is no issue made as to whether the railroad company has complied with the contract by the erection of a depot. The railway company offered an instruction covering and defining the measure of damages when a railroad company has erected a depot as agreed upon, but not within the time provided for by the contract, and while the instruction offered was not correct, and was properly refused, the duty then devolved upon the court to give a correct instruction upon the subject. Taylor Sons Co. v. Hunt, 163 Ky. 120; Chicago Veneer Co. v. Jones, 143 Ky. 26; L. & N. R. R. Co. v. Harrod, 115 Ky. 877; L. H. & St. L. R. Co. v. Roberts, 144 Ky. 820.

To determine what the instructions should have been, it is necessary to consider the facts which the evidence conduced to prove. The construction of the railroad began in the early part of the year 1913, but there is a conflict of testimony as to when it arrived at such a state of completion that trains were operated over it carrying passengers and freight. The testimony offered by Dingus tended to prove that trains began to pass over the road in the latter part of 1913, or in the early part of 1914, while the evidence for the railway company was to the effect that the road was not completed for the operation of trains until July 1st, 1914. No pretense was made by the railway company of the erection of a depot upon the land conveyed to it by Dingus until the 5th day of June, 1915, when it let a contract for that purpose, and the building which the railway company now Insists was the one which it had contracted to erect, was built during the months of June and July, 1915, An agent was not maintained at the depot for some months after its erection, the door was not kept locked, and any one could enter at his pleasure. The building was sixteen (16) feet in width and twenty-four (24) feet in length, and after a time it was separated into two rooms by a partition wall, one of which rooms was used as a ticket office, and the other for a waiting room, arid freights could not be put into it at all, but two box cars [816]*816were placed in close proximity to the building and were used as receptacles for freights, and such were the conditions at the time of the trial. The railway company insists that the building, and the box cars provided by it, fully complies with its contract, and indicates no purpose of making any further provision for a depot. The evidence is conflicting as to whether the building is adecpiate for the accommodation of the normal number of passengers and the transaction of the normal freight business at the place. As used by the railway company freights are not stored in the building at all, The evidence is, also, contradictory, as to whether an enhancement of the value of the lands was prevented by the failure of the railway company to erect a depot adequate to the demands of the passenger and freight business at the place.

The contract did not express any time within which the railway company should erect a depot, and neither did it define the style or dimensions of the depot, which was agreed to be erected and maintained. As no reason would exist for a depot unless and until the railroad was so completed, that trains could be operated over it, it must be concluded that the parties intended by the contract, that the depot should be-erected within a reasonable time after the operation of trains began over the road, and that it should be maintained thereafter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Louisville & Nashville Railroad v. Cornett's Administrator
35 S.W.2d 10 (Court of Appeals of Kentucky (pre-1976), 1931)
Trustees of Lone Oak Graded School District v. Gentry
295 S.W. 1063 (Court of Appeals of Kentucky (pre-1976), 1927)
Louisville & Nashville Railroad v. Johnson's Administratrix
270 S.W. 58 (Court of Appeals of Kentucky, 1925)
Louisville & Nashville Railroad v. Letcher County Coal & Improvement Co.
243 S.W. 45 (Court of Appeals of Kentucky, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
220 S.W. 1047, 187 Ky. 812, 1920 Ky. LEXIS 211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elkhorn-beaver-valley-railway-co-v-dingus-kyctapp-1920.