Elizabethtown Gas Co. v. Federal Energy Regulatory Commission

636 F.2d 1328, 205 U.S. App. D.C. 200
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 23, 1980
DocketNos. 77-1666, 78-1041
StatusPublished
Cited by1 cases

This text of 636 F.2d 1328 (Elizabethtown Gas Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elizabethtown Gas Co. v. Federal Energy Regulatory Commission, 636 F.2d 1328, 205 U.S. App. D.C. 200 (D.C. Cir. 1980).

Opinion

Opinion PER CURIAM

PER CURIAM:

Petitioner Elizabethtown Gas Company seeks review of a series of orders issued by the Federal Energy Regulatory Commission (FERC) and its predecessor the Federal Power Commission approving an interim plan for curtailment of gas by the Texas Eastern Transmission Corporation (Tetco). Elizabethtown challenges the validity of the curtailment plan as a system purportedly based upon the eventual end uses of natural gas, and questions the method established by FERC for challenging the data underlying the curtailment plan. Elizabethtown also raises arguments concerning the plan’s exemption for small customers, the categorization of gas kept in storage in proportion to the actual uses served, and the reservation of the issue of compensation pending the development of a record on the need for a compensation feature. For the reasons which follow, we affirm the Commission’s action in approving the plan here at issue.

Tetco owns and operates a major interstate natural gas pipeline extending from Texas to New York, selling gas to distributors for resale rather than directly to consumers (end-users). Petitioner Elizabeth-town, one of Teteo’s large distributors, purchases gas for resale from Tetco and two other interstate pipelines. In the early 1970’s Tetco began experiencing shortages of natural gas, and was unable to fulfill its contractual sales obligations. In 1973, Tet-co filed with the Commission tariff sheets detailing a system-wide plan for the curtailment of gas deliveries. After extensive proceedings at the agency level, FERC approved an interim curtailment plan which is currently in effect. The plan is based upon a settlement agreement approved by the vast majority of Tetco’s purchasers. The dissenting purchasers sought review within the agency, but only Elizabethtown now seeks judicial review.1

Before the onset of natural gas shortages, Tetco’s customers were entitled to receive up to 100% of the contracted-for supply. Under the curtailment plan, Tetco replaced these contract entitlements with Annual Quantity Entitlements (AQEs), based upon the volume of gas each distributor actually purchased from Tetco during a fixed period in the early 1970’s, rather than upon the volume of gas to which the distributor was contractually entitled.

Tetco collected data regarding the actual use which the customers of its distributors made of the gas purchased from Tetco (end-use data) for the base period, and established a system of priorities for the curtailment of gas. The Tetco plan places residential and small uses of natural gas in the highest priority (priority 1). Priority 2 includes such needs as larger commercial requirements, firm — not interruptible — industrial requirements, and plant protection. The lowest priority (priority 9) is composed of interruptible requirements over a certain volume per day, for which alternative fuel sources are available. The lower priorities are to be fully curtailed before higher priorities are affected under the Tetco plan.

The Commission held hearings on various aspects of the Tetco plan, and adopted with modifications the agreement submitted by the parties but opposed by Elizabethtown. The agreement accepted by the AQE system in place of contract entitlements, and approved the priority of service categorization with an exception to provide for “storage sprinkling.” Storage sprinkling requires that gas placed in storage during the summer be reclassified according to its actual end use during the winter months, when it is withdrawn from storage. The agreement also provided for a “peak day exemption” for small customers with no alternative gas supply, to exempt them from curtailment below their maximum contract entitlement on any one day. In addition, the plan completely exempted from curtailment the priority 1 volumes of small customers, provided that they incur no net growth that would increase their dependence on Tetco for gas.

In Opinion 787, the FPC concluded that the data base underlying the end-use curtailment calculations should be subject to [204]*204cross-examination by the parties, but that this procedure would be considered waived if the challenging parties did not demonstrate to the administrative law judge the areas of unreliability in the current data. The Commission also determined that the record relating to storage sprinkling should be supplemented, and that the plan would be an interim rather than a permanent one, until the Commission could review a final environmental impact statement. In all other respects the Commission accepted the settlement as an interim curtailment plan as of September 1,1976. In Opinion 787-A, the FPC on rehearing found that the appropriateness of a compensation feature should be considered by the administrative law judge in remanded proceedings, reaffirmed its other conclusions, and ordered Tetco to make necessary filings to implement the interim plan. In Opinion 787-B, FERC concluded that implementation of storage sprinkling was required, in view of the decision of this court in City of Willcox v. Federal Power Commission,2 the record compiled, and the revised tariff sheets filed by Tetco. Petitioner Elizabethtown now appeals from the series of orders approving the Tetco plan.

The end-use plan

When Tetco originally entered into contractual agreements with its customers, it apparently agreed to provide the purchasers with as much gas as they could use — with as much as the pipes could carry at maximum flow. This volume became known as contractual entitlement. An AQE is based upon the quantity of gas which a particular distributor actually purchased from Tetco during an “average” year, as opposed to the quantity of gas which that particular distributor was contractually entitled to purchase. Larger distributors historically purchased about 97% of their contract entitlements, while small distributors historically purchased only about 38% of theirs. Under the curtailment plan, purchaser is restricted to the quantity of gas which it normally purchased in an average year (the AQE), rather than its contractual entitlement. Curtailment of AQEs takes place according to the priority classifications under the Tet-co plan.

Elizabethtown first contends that the approved plan is not really an end-use plan, and that curtailment pursuant to the plan effects undue discrimination and unjust and unreasonable results, in violation of 15 U.S.C. § 717c. Elizabethtown argues that the plan curtails wholesalers rather than end-users, on the basis of claimed end-use requirements, while the wholesalers are free to distribute the gas according to operational requirements. Thus, petitioner asserts that because Tetco serves wholesalers, it actually has no “high priority” or “low priority” customers, and therefore FERC could not evaluate the varying impact of the plan on ultimate consumers. Elizabeth-town would substitute for this end-use plan a plan based on a straight pro rata sharing of the shortfalls based upon historical usage of Tetco’s supply.

We reject petitioner’s contention that because Tetco’s customers are wholesalers, its curtailment plan cannot be based upon the ultimate end use of the gas supply. The legality of end-use plans as an appropriate method of curtailment is firmly established. State of North Carolina v. FERC, 190 U.S.App.D.C. 22, 26,

Related

Cite This Page — Counsel Stack

Bluebook (online)
636 F.2d 1328, 205 U.S. App. D.C. 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elizabethtown-gas-co-v-federal-energy-regulatory-commission-cadc-1980.