Elizabeth Moxham v. Eric Crafton, et a l

CourtCourt of Appeals of Tennessee
DecidedJanuary 31, 2001
DocketM2000-00803-COA-R3-CV
StatusPublished

This text of Elizabeth Moxham v. Eric Crafton, et a l (Elizabeth Moxham v. Eric Crafton, et a l) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elizabeth Moxham v. Eric Crafton, et a l, (Tenn. Ct. App. 2001).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE January 31, 2001 Session

J. ELIZABETH MOXHAM v. ERIC W. CRAFTON, ET AL.

Appeal from the Chancery Court for Davidson County No. 97-3525-I Irvin H. Kilcrease, Jr., Chancellor

No. M2000-00803-COA-R3-CV - Filed May 4, 2001

During the trial of a construction dispute, the parties reached a settlement in the hallway of the courthouse, and subsequently announced the terms of their agreement to the trial court. Before the agreed order was entered, however, the plaintiff attempted to withdraw her consent. The plaintiff argues on appeal that the trial court erred by signing and entering the agreed order, and by denying her motion to set it aside. We affirm the trial court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed and Remanded

BEN H. CANTRELL , P.J., M.S., delivered the opinion of the court, in which WILLIAM C. KOCH , JR. and PATRICIA J. COTTRELL , JJ., joined.

Dana C. McLendon, III, Franklin, Tennessee, for the appellant, J. Elizabeth Moxham.

Thomas V. White and Jude A. White, Nashville, Tennessee, for the appellees, Eric W. Crafton, Individually, and C & C Development and Construction Co., Inc.

OPINION

I. A CONSTRUCTION DISPUTE

On October 23, 1996, C & C Development and Construction Company (C & C) entered into a contract with Elizabeth Moxham to build her a house “of good quality and free of defects,” on a 5.5 acre tract she owned in Bellevue. Ms. Moxham agreed to make periodic payments as the work progressed, totaling $69,874 upon completion. She also agreed to convey 0.4 acres of her tract to the contractor, which would enable him to shorten the length of a sewer line to an adjoining subdivision that he was building, and possibly to add another residence to it. Another provision in the contract allowed either party to terminate it by written notice. Construction on the house began, but things did not go smoothly. Ms. Moxham was dissatisfied with the quality of the work, and refused to make two progress payments requested by Mr. Crafton, even though the bank that made the construction loan to her had authorized the payments after inspection by their agents. On July 15, 1997, Eric Crafton sent a letter to Ms. Moxham, terminating the contract and demanding proportional payment for the work completed, as well as Ms. Moxham’s signature on a deed transferring the 0.4 acre tract to him.

On October 27, 1997, Ms. Moxham filed suit against C & C and against Eric Crafton, C & C’s president, for breach of contract, negligent construction, and breach of the builder’s warranty. She alleged that an inspection of the uncompleted house conducted by the Metropolitan Codes Department had revealed numerous construction defects. Ms. Moxham asked for damages, as well as for injunctive relief in the form of an order to complete the project, including compliance with the repairs listed by Codes or, in the alternative, to cancel the defendants’ building permit.

On November 4, 1997, Wayne Crafton, Vice President of C & C and Eric Crafton’s father, filed a mechanics’ and materialmen’s lien on Ms. Moxham’s property, and a complaint to enforce it. He claimed that C & C had not been paid for its work, and demanded payment in full on the contract, or in the alternative that the property be sold to enforce the lien.

The two lawsuits were subsequently consolidated by agreed order. The order also stated that C & C would cause the building permit for the project to be cancelled and withdrawn, and that Ms. Moxham would be allowed to amend her complaint to add Wayne Crafton as a party defendant. Sometime after the building permit was cancelled, Ms. Moxham hired another contractor to finish the house, and to repair defects in Mr. Crafton’s work. When this was completed, she moved into the house.

The defendants filed a motion to amend their complaint on August 2, 1999. Their amended complaint reduced the amount of the mechanics’ and materialmen’s lien from $69,874 to $10,000, but added a claim for $20,900 in consequential damages, allegedly resulting from Ms. Moxham’s failure to convey the 0.4 acres to them.

II. A TRIAL AND A SETTLEMENT

The trial of the case began on December 13, 1999. Ms. Moxham testified all morning and part of the afternoon. Three Codes inspectors and two contractors were also called to the stand. The defendants objected to some of the evidence the plaintiff tried to present through the testimony of the contractors, because she had not complied with the local rule that requires each party to provide opposing counsel with certain information about the evidence it intends to present at least 72 hours in advance of the trial. For her part, the plaintiff argued that the defendants had failed to make proper requests for discovery under Rule 26, Tenn. R. Civ. P. The judge rebuked both parties for failing to follow the discovery rules, and adjourned the court at 4:10 p.m. He stated that he would put the case back on the docket only after the parties had complied with the discovery rules.

-2- At that point, the parties met in the courthouse hallway and negotiated a settlement. The court reporter had already gone home, but the judge was called back to the bench, where the parties announced their settlement, which he approved. In general terms, the settlement called for both sides to abandon all claims for money damages against each other, and for Ms. Moxham to convey the 0.4 acres to the defendant, with the parties to use their best efforts to complete the terms of the agreement by January 1, 2000.

On December 15, 1999, defendants’ counsel submitted to the court a draft of an agreed order, signed by counsel for both parties, which recited the terms of the agreement that had been announced in open court. However, the agreed order was not signed by the chancellor until January 12, 2000, a fact upon which the plaintiff places great emphasis.

On January 6, 2000, the defendants filed a motion for contempt against Ms. Moxham for failing to convey the 0.4 acre tract in accordance with the agreement. In the interim, Ms. Moxham’s attorney had withdrawn from representing her, so on January 10, 2000, Ms. Moxham filed a pro se motion, captioned “Motion to Set Aside Agreed Order, and Reset the Case for Trial.” She claimed that the settlement reached on December 13 was the product of “extreme duress” resulting from strong pressure by her attorney to settle, and emotional upset from four hours of questioning on the stand.

The Clerk and Master conducted a hearing on the motion for contempt on February 4, 2000. Ms. Moxham appeared pro se. The evidence showed that in order to convey the tract to C & C, she would have to replace her construction loan, secured by the entire 5.5 acre tract, with a mortgage loan secured by the property remaining after the conveyance. She testified that she had contacted two banks about the loan, and both were prepared to make the mortgage loan, but she chose not to do business with the first bank, and didn’t follow through with the second bank because of an $800 fee for a title policy. The trial court found Ms. Moxham to be in contempt, and ordered her to convey the 0.4 acre tract to the defendants by February 25.

Ms. Moxham subsequently made the conveyance. A hearing before the Clerk and Master on March 3 resulted in a finding that she had purged herself of the contempt. The only contempt sanction the court imposed upon her was an order to reimburse the defendants for attorney fees and costs they incurred in the contempt action, in the amount of $1,025.

Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tennessee Farmers Mutual Insurance Co. v. Farmer
970 S.W.2d 453 (Tennessee Supreme Court, 1998)
Environmental Abatement, Inc. v. Astrum R.E. Corp.
27 S.W.3d 530 (Court of Appeals of Tennessee, 2000)
Starks v. Browning
20 S.W.3d 645 (Court of Appeals of Tennessee, 1999)
Nails v. Aetna Insurance Co.
834 S.W.2d 289 (Tennessee Supreme Court, 1992)
Harbour v. Brown for Ulrich
732 S.W.2d 598 (Tennessee Supreme Court, 1987)
John Barb, Inc. v. Underwriters at Lloyds of London
653 S.W.2d 422 (Court of Appeals of Tennessee, 1983)
Bemis Co., Inc. v. Hines
585 S.W.2d 574 (Tennessee Supreme Court, 1979)
Jefferson v. Pneumo Services Corp.
699 S.W.2d 181 (Court of Appeals of Tennessee, 1985)
Edmundson v. Pratt
945 S.W.2d 754 (Court of Appeals of Tennessee, 1996)
Toney v. Mueller Co.
810 S.W.2d 145 (Tennessee Supreme Court, 1991)
Jerkins v. McKinney
533 S.W.2d 275 (Tennessee Supreme Court, 1976)
REM Enterprises, Ltd. v. Frye
937 S.W.2d 920 (Court of Appeals of Tennessee, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Elizabeth Moxham v. Eric Crafton, et a l, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elizabeth-moxham-v-eric-crafton-et-a-l-tennctapp-2001.