Elizabeth Equipment v. Senterra Building

Superior Court of Pennsylvania·Decided April 11, 2024·No. 154 WDA 2023·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

ELIZABETH EQUIPMENT SERVICES, : IN THE SUPERIOR COURT OF INC. : PENNSYLVANIA :

Appellant :

:

:

v. :

:

:

SENTERRA BUILDING AND : No. 154 WDA 2023 DEVELOPMENT, INC. :

Appeal from the Judgment Entered May 26, 2023 In the Court of Common Pleas of Allegheny County Civil Division at No(s): GD1715065

BEFORE: BOWES, J., KUNSELMAN, J., and MURRAY, J. MEMORANDUM BY BOWES, J.: FILED: April 11, 2024 Elizabeth Equipment Services, Inc. (“Elizabeth”) appeals from the judgment entered on the non-jury verdict in its favor against Senterra Building and Development, Inc. (“Senterra”). We affirm.

The history of this case is as follows. Elizabeth is an excavation contractor owned by Arthur Smith. Senterra, owned by James Dinert, is a residential housing developer. The owners had known each other for years and worked together on multiple projects. In 2014, Senterra hired Elizabeth to perform excavation and site preparation on a townhouse project to be known as Ellison Place in Castle Shannon, Allegheny County, Pennsylvania. On or about September 8, 2014, the parties executed American Institute of

Architects standard form agreement A107-2007 to memorialize their agreement (“Contract”).1 Pursuant to the Contract, Senterra was to pay Elizabeth the stipulated sum of $308,269, “[s]ubject to mutually signed written change orders.” Contract, 9/8/14, at § 3.2. The Contract referenced Elizabeth’s Quote No. 222 (“Quote”) for the itemization of the unit prices, again indicating the amount was “[s]ubject to [a] mutually signed change order or acknowledgment job slip signed by owner.” Id. at § 3.2.2. See also id. at § 6.1.2 (denoting Quote No. 222 as “The Supplementary and other Conditions of the Contract”). For allowances included in the stipulated sum, the Contract referred to the notes to Quote No. 222 (“Notes”), which were also appended to the Contract. The Notes included the agreement that “any alterations or deviations from this Contract or the engineered plans will become an ‘extra charge’ separate from this Contract, with payment conditions the same as this Contract.” Id. at Note H (capitalization altered).

The Contract indicated that Elizabeth was to submit to Senterra progress invoices every thirty days, and Senterra was to make the payment to Elizabeth within thirty days thereafter, with any remaining balance subject to interest

1 The date was left blank on the first page of the agreement, and no date accompanied the signatures. However, the list of exhibits to the Contract was dated September 8, 2014. The Contract is found in the certified record as Exhibit A to Elizabeth’s operative complaint and was admitted at trial without objection as Exhibit 1. See N.T. Trial, 1/19/22, at 52.

at 1.5% per month. Id. at Note E. The Contract further specified that Senterra would withhold a ten percent retainage from each payment.2 Id. at § 4.1.4. To obtain final payment, Elizabeth was to provide written notice that its work was ready for final inspection and acceptance and submit a final application for payment. Id. at § 15.5.1. However, final payment would “not be due until [Elizabeth] has delivered to [Senterra] a complete release of all liens arising out of this Contract or receipts in full covering all labor, materials[,] and equipment for which a lien could be filed, or a bond satisfactory to [Senterra] to indemnify [it] against such lien.” Id. at 15.5.2. Final payment was required to be made no later than thirty days after the “Castle Shannon Borough Engineer has inspected and approved [Elizabeth]’s work.” Id. at § 4.2.2.

Elizabeth commenced work pursuant to the Contract and submitted monthly applications for payment to Senterra, which Senterra paid. During the course of its performance, Elizabeth submitted four documents to Senterra titled “CHANGE ORDER / CONTRACT ADDENDUM.” The first two, Change Orders Nos. 1 and 2, amounted to net additional costs of $7,680 and $3,000,

2 A retainage is “[a] percentage of what a landowner pays a contractor, withheld until the construction has been satisfactorily completed and all mechanic’s liens are released or have expired.” RETAINAGE, Black’s Law Dictionary (11th ed. 2019).

were signed by Mr. Dinert on behalf of Senterra, and were subsequently paid.3 The last two, Change Orders Nos. 3 and 4, were respectively dated May 20, 2015, for $8,272.80, and dated July 28, 2015, for $5,781.25. See N.T. Trial., 1/19/22, at Exhibit 2.4 Unlike Change Orders Nos. 1 and 2, Change Orders Nos. 3 and 4 did not specify whether there were items to be deducted from the Contract in connection with the change, did not provide a net cost amount for the change, and were not signed by a representative of Senterra.5 Nonetheless, Senterra paid Elizabeth for all four change orders. See id. at 96 (Mr. Dinert confirming payment), 144 (Mr. Smith confirming payment). Indeed, Elizabeth’s ninth

3 In calculating the final contract price in light of the change orders, Elizabeth

listed $19,000 as the amount of Change Order No. 1. In doing so, it improperly utilized the gross cost of the new obligation rather than the net increase after accounting for the $11,320 that was subtracted from the Contract due to the change. The signed change order indicated a “total additional contract cost” of $7,680. See N.T. Trial, 1/19/22, at Exhibit 2.

4 Elizabeth did not ensure that the trial exhibits were made part of the record

certified to this Court as was its duty as the appellant. See, e.g., Commonwealth v. Harlan, 208 A.3d 497, 501 (Pa.Super. 2019) (“Our law is unequivocal that the responsibility rests upon the appellant to ensure that the record certified on appeal is complete in the sense that it contains all of the materials necessary for the reviewing court to perform its duty.”). However, our review is not hampered because the pertinent documents, identified and described in the trial transcript, are included elsewhere in the certified record.

5 Elizabeth’s eighth progress invoice listed the amount of Change Order No. 4

as $2,376. See N.T. Trial, 1/19/22, at Exhibit 2. It does not appear that the progress invoice by which Elizabeth charged Senterra for Change Order No. 3 was offered into evidence or otherwise filed of record.

and final progress invoice, dated October 5, 2015, was for $31,869.14, which was the sum that Senterra had deducted for the retainage. Id. at Exhibit 3.

Senterra became unable to meet its payment obligations. Mr. Dinert asked Mr. Smith to be patient and refrain from filing any liens on behalf of Elizabeth while it sought supplementary financing. Id. at 129, 150. While Elizabeth had previously executed a no-lien document in favor of West View Bank in connection with its financing of the project, Elizabeth declined Senterra’s request to agree to forgo filing any liens against it to facilitate the additional financing. Id. at 129. Ultimately, on June 17, 2016, Senterra paid the September 30, 2015 progress invoice, along with one-half of the retainage billed in the final invoice, leaving an outstanding balance of $15,934.57, namely the other half of the retainage. Id. at Exhibit 3. Senterra indicated the balance would be released upon Elizabeth’s provision of a maintenance bond for the sanitary sewer and storm sewer. Id. at Exhibit 3. Elizabeth refused based upon the Contract’s provision that Elizabeth was not responsible for any bonds unless the Contract so indicated. See Contract, 9/8/14, at Note D (“All permits, bonds, inspection fees, testing fees, and engineering layout supplied by others unless noted.” (capitalization altered)).

Free access — add to your briefcase to read the full text and ask questions with AI

Elizabeth Equipment v. Senterra Building, (Pa. Ct. App. 2024).

Elizabeth Equipment v. Senterra Building (Elizabeth Equipment v. Senterra Building) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Jones v. Rivera
866 A.2d 1148 (Superior Court of Pennsylvania, 2005)
Spang & Co. v. United States Steel Corp.
545 A.2d 861 (Supreme Court of Pennsylvania, 1988)
Darrt Development Co. v. Tri-State Asphalt Corp.
609 A.2d 171 (Superior Court of Pennsylvania, 1992)
Louis Dreyfus Commodities Suisse SA v. Financial Software Systems, Inc.
99 A.3d 79 (Superior Court of Pennsylvania, 2014)
Angino v. Jeffrey R. Lessin & Associates
131 A.3d 502 (Superior Court of Pennsylvania, 2016)
Schell, S. v. Murphy, R.
153 A.3d 379 (Superior Court of Pennsylvania, 2016)
Davis, A. v. Borough of Montrose
194 A.3d 597 (Superior Court of Pennsylvania, 2018)
Pops Pce TT, LP v. R&R Rest. Grp., LLC.
208 A.3d 79 (Superior Court of Pennsylvania, 2019)
Commonwealth v. Harlan
208 A.3d 497 (Superior Court of Pennsylvania, 2019)
Melmark, Inc. v. Schutt by and Through Schutt
206 A.3d 1096 (Supreme Court of Pennsylvania, 2019)
Temple University Hospital, Inc. v. Healthcare Management Alternatives, Inc.
832 A.2d 501 (Superior Court of Pennsylvania, 2003)
Clark, C. v. Peugh, W.
2021 Pa. Super. 131 (Superior Court of Pennsylvania, 2021)
Discover Bank v. Booker, R.
2021 Pa. Super. 139 (Superior Court of Pennsylvania, 2021)
Riverview Carpet & Flooring, Inc. v. Presbyterian
2023 Pa. Super. 119 (Superior Court of Pennsylvania, 2023)