Elizabeth Equipment v. Senterra Building

CourtSuperior Court of Pennsylvania
DecidedApril 11, 2024
Docket154 WDA 2023
StatusUnpublished

This text of Elizabeth Equipment v. Senterra Building (Elizabeth Equipment v. Senterra Building) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elizabeth Equipment v. Senterra Building, (Pa. Ct. App. 2024).

Opinion

J-A29002-23

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

ELIZABETH EQUIPMENT SERVICES, : IN THE SUPERIOR COURT OF INC. : PENNSYLVANIA : Appellant : : : v. : : : SENTERRA BUILDING AND : No. 154 WDA 2023 DEVELOPMENT, INC. :

Appeal from the Judgment Entered May 26, 2023 In the Court of Common Pleas of Allegheny County Civil Division at No(s): GD1715065

BEFORE: BOWES, J., KUNSELMAN, J., and MURRAY, J.

MEMORANDUM BY BOWES, J.: FILED: April 11, 2024

Elizabeth Equipment Services, Inc. (“Elizabeth”) appeals from the

judgment entered on the non-jury verdict in its favor against Senterra Building

and Development, Inc. (“Senterra”). We affirm.

The history of this case is as follows. Elizabeth is an excavation

contractor owned by Arthur Smith. Senterra, owned by James Dinert, is a

residential housing developer. The owners had known each other for years

and worked together on multiple projects. In 2014, Senterra hired Elizabeth

to perform excavation and site preparation on a townhouse project to be

known as Ellison Place in Castle Shannon, Allegheny County, Pennsylvania.

On or about September 8, 2014, the parties executed American Institute of J-A29002-23

Architects standard form agreement A107-2007 to memorialize their

agreement (“Contract”).1

Pursuant to the Contract, Senterra was to pay Elizabeth the stipulated

sum of $308,269, “[s]ubject to mutually signed written change orders.”

Contract, 9/8/14, at § 3.2. The Contract referenced Elizabeth’s Quote No. 222

(“Quote”) for the itemization of the unit prices, again indicating the amount

was “[s]ubject to [a] mutually signed change order or acknowledgment job

slip signed by owner.” Id. at § 3.2.2. See also id. at § 6.1.2 (denoting Quote

No. 222 as “The Supplementary and other Conditions of the Contract”). For

allowances included in the stipulated sum, the Contract referred to the notes

to Quote No. 222 (“Notes”), which were also appended to the Contract. The

Notes included the agreement that “any alterations or deviations from this

Contract or the engineered plans will become an ‘extra charge’ separate from

this Contract, with payment conditions the same as this Contract.” Id. at

Note H (capitalization altered).

The Contract indicated that Elizabeth was to submit to Senterra progress

invoices every thirty days, and Senterra was to make the payment to Elizabeth

within thirty days thereafter, with any remaining balance subject to interest

____________________________________________

1 The date was left blank on the first page of the agreement, and no date accompanied the signatures. However, the list of exhibits to the Contract was dated September 8, 2014. The Contract is found in the certified record as Exhibit A to Elizabeth’s operative complaint and was admitted at trial without objection as Exhibit 1. See N.T. Trial, 1/19/22, at 52.

-2- J-A29002-23

at 1.5% per month. Id. at Note E. The Contract further specified that

Senterra would withhold a ten percent retainage from each payment.2 Id. at

§ 4.1.4. To obtain final payment, Elizabeth was to provide written notice that

its work was ready for final inspection and acceptance and submit a final

application for payment. Id. at § 15.5.1. However, final payment would “not

be due until [Elizabeth] has delivered to [Senterra] a complete release of all

liens arising out of this Contract or receipts in full covering all labor,

materials[,] and equipment for which a lien could be filed, or a bond

satisfactory to [Senterra] to indemnify [it] against such lien.” Id. at 15.5.2.

Final payment was required to be made no later than thirty days after the

“Castle Shannon Borough Engineer has inspected and approved [Elizabeth]’s

work.” Id. at § 4.2.2.

Elizabeth commenced work pursuant to the Contract and submitted

monthly applications for payment to Senterra, which Senterra paid. During

the course of its performance, Elizabeth submitted four documents to Senterra

titled “CHANGE ORDER / CONTRACT ADDENDUM.” The first two, Change

Orders Nos. 1 and 2, amounted to net additional costs of $7,680 and $3,000,

2 A retainage is “[a] percentage of what a landowner pays a contractor, withheld until the construction has been satisfactorily completed and all mechanic’s liens are released or have expired.” RETAINAGE, Black’s Law Dictionary (11th ed. 2019).

-3- J-A29002-23

were signed by Mr. Dinert on behalf of Senterra, and were subsequently paid.3

The last two, Change Orders Nos. 3 and 4, were respectively dated May 20,

2015, for $8,272.80, and dated July 28, 2015, for $5,781.25. See N.T. Trial.,

1/19/22, at Exhibit 2.4

Unlike Change Orders Nos. 1 and 2, Change Orders Nos. 3 and 4 did not

specify whether there were items to be deducted from the Contract in

connection with the change, did not provide a net cost amount for the change,

and were not signed by a representative of Senterra.5 Nonetheless, Senterra

paid Elizabeth for all four change orders. See id. at 96 (Mr. Dinert confirming

payment), 144 (Mr. Smith confirming payment). Indeed, Elizabeth’s ninth

3 In calculating the final contract price in light of the change orders, Elizabeth

listed $19,000 as the amount of Change Order No. 1. In doing so, it improperly utilized the gross cost of the new obligation rather than the net increase after accounting for the $11,320 that was subtracted from the Contract due to the change. The signed change order indicated a “total additional contract cost” of $7,680. See N.T. Trial, 1/19/22, at Exhibit 2.

4 Elizabeth did not ensure that the trial exhibits were made part of the record

certified to this Court as was its duty as the appellant. See, e.g., Commonwealth v. Harlan, 208 A.3d 497, 501 (Pa.Super. 2019) (“Our law is unequivocal that the responsibility rests upon the appellant to ensure that the record certified on appeal is complete in the sense that it contains all of the materials necessary for the reviewing court to perform its duty.”). However, our review is not hampered because the pertinent documents, identified and described in the trial transcript, are included elsewhere in the certified record.

5 Elizabeth’s eighth progress invoice listed the amount of Change Order No. 4

as $2,376. See N.T. Trial, 1/19/22, at Exhibit 2. It does not appear that the progress invoice by which Elizabeth charged Senterra for Change Order No. 3 was offered into evidence or otherwise filed of record.

-4- J-A29002-23

and final progress invoice, dated October 5, 2015, was for $31,869.14, which

was the sum that Senterra had deducted for the retainage. Id. at Exhibit 3.

Senterra became unable to meet its payment obligations. Mr. Dinert

asked Mr. Smith to be patient and refrain from filing any liens on behalf of

Elizabeth while it sought supplementary financing. Id. at 129, 150. While

Elizabeth had previously executed a no-lien document in favor of West View

Bank in connection with its financing of the project, Elizabeth declined

Senterra’s request to agree to forgo filing any liens against it to facilitate the

additional financing. Id. at 129. Ultimately, on June 17, 2016, Senterra paid

the September 30, 2015 progress invoice, along with one-half of the retainage

billed in the final invoice, leaving an outstanding balance of $15,934.57,

namely the other half of the retainage. Id. at Exhibit 3. Senterra indicated

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Rivera
866 A.2d 1148 (Superior Court of Pennsylvania, 2005)
Spang & Co. v. United States Steel Corp.
545 A.2d 861 (Supreme Court of Pennsylvania, 1988)
Darrt Development Co. v. Tri-State Asphalt Corp.
609 A.2d 171 (Superior Court of Pennsylvania, 1992)
Louis Dreyfus Commodities Suisse SA v. Financial Software Systems, Inc.
99 A.3d 79 (Superior Court of Pennsylvania, 2014)
Angino v. Jeffrey R. Lessin & Associates
131 A.3d 502 (Superior Court of Pennsylvania, 2016)
Schell, S. v. Murphy, R.
153 A.3d 379 (Superior Court of Pennsylvania, 2016)
Davis, A. v. Borough of Montrose
194 A.3d 597 (Superior Court of Pennsylvania, 2018)
Pops Pce TT, LP v. R&R Rest. Grp., LLC.
208 A.3d 79 (Superior Court of Pennsylvania, 2019)
Commonwealth v. Harlan
208 A.3d 497 (Superior Court of Pennsylvania, 2019)
Melmark, Inc. v. Schutt by and Through Schutt
206 A.3d 1096 (Supreme Court of Pennsylvania, 2019)
Temple University Hospital, Inc. v. Healthcare Management Alternatives, Inc.
832 A.2d 501 (Superior Court of Pennsylvania, 2003)
Clark, C. v. Peugh, W.
2021 Pa. Super. 131 (Superior Court of Pennsylvania, 2021)
Discover Bank v. Booker, R.
2021 Pa. Super. 139 (Superior Court of Pennsylvania, 2021)
Riverview Carpet & Flooring, Inc. v. Presbyterian
2023 Pa. Super. 119 (Superior Court of Pennsylvania, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Elizabeth Equipment v. Senterra Building, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elizabeth-equipment-v-senterra-building-pasuperct-2024.