Electronics Corp. of America v. Canter Construction Co.

178 N.E.2d 1, 343 Mass. 210, 1961 Mass. LEXIS 637
CourtMassachusetts Supreme Judicial Court
DecidedNovember 17, 1961
StatusPublished
Cited by6 cases

This text of 178 N.E.2d 1 (Electronics Corp. of America v. Canter Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electronics Corp. of America v. Canter Construction Co., 178 N.E.2d 1, 343 Mass. 210, 1961 Mass. LEXIS 637 (Mass. 1961).

Opinion

Cutter, J.

This is a petition, filed on June 8, 1960, by

the plaintiff (Electronics), for acceptance and confirmation of an arbitration award, and for judgment thereon. See Gr. L. c. 251, prior to its amendment by St. 1960, c. 374, l. 1 *211 The defendant (Canter), in an answer and a motion to set aside the award, set up among other defences Electronics’ alleged failure to comply with Gr. L. c. 251, § 17. The case was heard by a judge of the Superior Court. Canter filed two requests for rulings, one of which is set out in the margin. 2 The judge “did not expressly grant or deny” these but made the following ruling, “Arbitrator’s award accepted and confirmed, all statutory requirements having been complied with. ’ ’ The judge found generally for Electronics in the amount of the award. Canter claimed an exception. The case is here upon Canter’s bill of exceptions.

On June 20, 1956, Electronics and Canter entered into a contract under which Canter was to construct a building for Electronics. Article 11 of this contract provided, “All disputes, claims or questions pertaining to the interpretation of this contract or the performance by either party . . . shall be submitted to arbitration in accordance with provisions then obtaining of the American Arbitration Association, and this agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award entered may be entered in the court . . . having jurisdiction. . . . [T]he decision of the arbitrator's shall be a condition precedent to any right of legal action that any party may have against the other. ...”

By letter dated January 22,1958, Electronics gave notice to Canter of alleged defects in Canter’s performance, especially leakage in the walls. The letter read in part, “Per our telephone conversation of . . . January 20, I am submitting to you a copy of the report from W. H. Brown Associates with regard to the rain damage in the tower section of” the building constructed by Canter. After listing complaints and possible solutions, and repairs suggested by an architect it concluded, “I will call you on . . . January 23rd so that we . . . [may] arrange a meeting of . . . the architect, you and myself . . ..”

*212 On June 18, 1959, Electronics demanded arbitration by submitting a demand to American Arbitration Association as follows: “Demand for breach of contract in that the work done by Canter . . . was not done in accordance with the specifications . . . and . . . the building . . . was not tight to the weather because of poor masonry work . . .. Damages in the amount of $10,000 are sought.” It was agreed at the trial that this demand was not filed by stipulation or agreement. Neither the contract nor the rules of the American Arbitration Association provided that a demand for arbitration should be filed by stipulation or agreement or within any specified time.

Shortly thereafter Canter by bill in equity sought to restrain Electronics from proceeding with arbitration, alleging that the controversy described in the demand had been settled by agreement. A preliminary injunction restraining Electronics from proceeding in the arbitration was entered August 4, 1959, and continued in effect until January 6, 1960, when the bill was dismissed, after a hearing before an “auditor” who found that Canter had not sustained its burden of proof that a settlement agreement had been reached.

Shortly after the preliminary injunction had been issued, Electronics began an action at law against Canter, alleging the same breaches of contract referred to in the arbitration demand. Canter moved to stay the action by application under c. 251, § 21, and stated that ‘ ‘ Canter ... is, and has always been ready and willing to submit to arbitration any and all matters arising under said contract of June 20,1956, that are properly referable to [arbitration.” A stay was ordered on January 6, 1960.

On March 31 and April 1,1960, Electronics ’ demand was heard by arbitrators. Their chairman testified before the trial judge that at the commencement of the arbitration he had asked “if either party had . . . objection to going forward with arbitration; that both attorneys . . . stated that the award would be final, and that . . . [Canter’s] attor *213 ney said that it was his intention and expectation that the arbitrators would decide the matter, including the question of whether or not the arbitration demand was reasonably timed.”

In May, 1960, the arbitrators filed an award directing (1) Canter to pay to Electronics $6,045, which included damages on account of leaks; (2) that each side pay its own counsel fees and expenses; and (3) that the expenses of the arbitration be borne equally. This award was filed in the Superior Court about June 8, 1960.

The principal issue presented by the trial judge’s ruling is the correct interpretation of C. L. c. 251, § 17, inserted by St. 1925, c. 294, § 5. 3 Section 17 reads, “The submission shall be made within six months, unless otherwise stipulated by the parties, but in no event within less than a reasonable time, after due notice by any party to the contract claiming the arbitration of any controversy thereunder.” Canter, among other things, contends that the letter of January 22, 1958, constituted notice of a controversy, that submission of the matter to arbitration did not take place thereafter for more than a year and a half, and that, under § 17, this was too late, with the consequence that the Superior Court had no jurisdiction to enforce the award.

Section 17 has not been interpreted by this court, although it was mentioned briefly and inconclusively in Cueroni v. Coburnville Garage, Inc. 315 Mass. 135, 139-140. 4 The section has been referred to by one text writer as, at the time he wrote (1941), the only instance of such a statu *214 tory time limitation. See Kellor, Arbitration in Action, p. 79, no. 32.

The section is ambiguous in various respects: (1) There is doubt about the precise meaning of the term “submission.” (2) It also is not wholly clear whether the “submission” must be (a) within six months of notice of a controversy or (b) within six months of a notice claiming arbitration of a controversy. We consider these two principal obscurities in § 17.

(1) We think that, in a case like this where an agreement for arbitration of future controversies is contained in a contract, “submission,” as used in § 17, refers to the completion by the party demanding arbitration of the action necessarily to be performed by that party, in accordance with the arbitration clause in his contract, to bring about arbitration. Indeed, as is pointed out in Kellor, Arbitration in Action, pp. 67-68, where, “in a primary contract,” there is a clause providing for the “arbitration of a future undisclosed dispute,” then a “party to such a contract and clause may demand arbitration in the same manner as under a submission.” He points out that such a clause is “enforceable ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carpenter v. Pomerantz
634 N.E.2d 587 (Massachusetts Appeals Court, 1994)
Providence Teachers Union v. Providence School Committee
440 A.2d 124 (Supreme Court of Rhode Island, 1982)
Kelleher v. Cersosimo
320 N.E.2d 840 (Massachusetts Appeals Court, 1974)
Glenn Acres, Inc. v. Cliffwood Corp.
228 N.E.2d 835 (Massachusetts Supreme Judicial Court, 1967)
Carter, Moore & Co. Inc. v. Donahue
189 N.E.2d 217 (Massachusetts Supreme Judicial Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
178 N.E.2d 1, 343 Mass. 210, 1961 Mass. LEXIS 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electronics-corp-of-america-v-canter-construction-co-mass-1961.