Electric Serv. Co. of Duluth v. Lakehead Elec. Co.

189 N.W.2d 489, 291 Minn. 22, 1971 Minn. LEXIS 988
CourtSupreme Court of Minnesota
DecidedJuly 30, 1971
Docket42712
StatusPublished
Cited by10 cases

This text of 189 N.W.2d 489 (Electric Serv. Co. of Duluth v. Lakehead Elec. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electric Serv. Co. of Duluth v. Lakehead Elec. Co., 189 N.W.2d 489, 291 Minn. 22, 1971 Minn. LEXIS 988 (Mich. 1971).

Opinion

*23 Nelson, Justice.

Appeals by plaintiff, Electric Service Co. of Duluth, Inc., from an order of the St. Louis County District Court entered June 26, 1970, denying plaintiff’s motions for judgment against defendants-respondents, Lakehead Electric Company, Wesley Harkonen, and Reuben Johnson and Sons, Inc., on the issue of liability, and new trial on the issue of damages only, or, in the alternative, for a new trial against all defendants on all issues.

Plaintiff, hereinafter referred to as Electric Service, is a Minnesota corporation engaged in the electrical contracting business in Duluth and surrounding areas. Reuben Johnson and Sons, Inc., hereinafter referred to as Reuben Johnson, is a Wisconsin corporation engaged in the general contracting business in the Great Lakes region of Minnesota, Wisconsin, and Michigan. Lakehead Electric Company, hereinafter called Lakehead, is a Minnesota corporation engaged in the electrical contracting business in Duluth and surrounding areas. Wesley Harkonen is president, majority stockholder, and general manager of Lake-head.

On July 10, 1968, Reuben Johnson submitted a bid for a prime contract to the State of Wisconsin for the construction of a steam and electrical distribution center at Wisconsin State University located at Superior. The bids were opened later that same day and disclosed that Reuben Johnson was the low bidder. On July 11, 1968, one of Reuben Johnson’s employees telephoned Keith Morse, manager of Electric Service, and asked Morse if Electric Service would be interested in submitting a bid on the subcontract for the electrical work on the project. In response, Morse went to Reuben Johnson’s office in Superior the next day to discuss the requirements of the electrical portion of the project with Troy Johnson, Reuben Johnson’s owner and general manager. Troy Johnson gave Morse plans and specifications for the project and the latter returned to Duluth where he and another employee of Electric Service analyzed the plans and prepared bid *24 summary sheets containing a tentative estimate for performance of the electrical work.

A few days later, Morse returned to Reuben Johnson’s office and, after discussing the estimate with Troy Johnson, made a verbal offer of $322,500. Johnson asked Morse to reduce his offer by $500, which he did, and Johnson thereupon accepted it and told Morse to submit the offer in writing. Morse drafted a written proposal of the agreement, signed it, and took it to Troy Johnson at his office July 19, 1968. Troy Johnson then signed it in behalf of Reuben Johnson and Sons, Inc.

Morse thereupon left the Reuben Johnson office and placed a large order for materials and equipment for the job with Gray-bar Electric Company, an electrical distributor in Duluth. He also arranged for a line of credit to be extended to Electric Service for the job from a Duluth bank and another line of credit from a supplier. On July 23, 1968, Reuben Johnson and the State of Wisconsin signed a written contract for the construction of the steam and electrical distribution center at Wisconsin State University.

On July 29, 1968, Morse was notified by Troy Johnson that Electric Service was “unacceptable” to do the electrical work on the steam and electrical distribution center. Troy Johnson called Morse again the next day and asked him to cancel the order for materials which Electric Service had placed. The factor which caused Reuben Johnson to find Electric Service unsuitable for the job was the opinion of Charles Goldsmith, the consulting engineer on the project, who told Reuben Johnson that he thought Electric Service did not have enough past experience or equipment to adequately perform the electrical work.

Wesley Harkonen had made Reuben Johnson an offer for the electrical work on behalf of Lakehead about a week after he had heard Reuben Johnson was the low bidder on the project, but his offer was rejected. However, when Troy Johnson was informed by Goldsmith that Electric Service was unacceptable, he called Harkonen and asked him for a figure on the project. *25 Johnson was not satisfied with the first figure he received and another was submitted, $320,000, which Johnson accepted and for which he wrote a purchase order contract which was signed by Harkonen July 31, 1968. Lakehead, upon receiving the subcontract, took over Electric Service’s orders for materials which had been placed with Graybar, issuing its purchase order for that material which was already in shipment. On August 2,1968, Troy Johnson informed Morse that he had given the subcontract on the electrical work to Lakehead. Lakehead subsequently performed the electrical work on the project.

Electric Service commenced an action for damages for breach of contract against Reuben Johnson and a second action against Harkonen and Lakehead for wrongful interference with the contract between Electric Service and Reuben Johnson, demanding compensatory and punitive damages. The actions were consolidated for trial and, following a lengthy trial, were submitted to the jury on special interrogatories. The special interrogatories submitted in the action against Reuben Johnson asked:

“1. Did Charles Goldsmith, as a representative of the architect, by any action or conduct on his part cause Reuben Johnson and Sons, Inc., to fail or refuse to perform its agreement of July 19, 1968, with Electric Service Co. of Duluth, Inc.?”

The jury answered “Yes.”

“2. Did defendant Lakehead Electric by any conduct or action on its part, through its officer Wesley Harkonen, cause Reuben Johnson and Sons, Inc., to fail or refuse to perform its agreement of July 19, 1968, with Electric Service Co.?”

The jury answered “No.”

“3. Did defendant Reuben Johnson and Sons, Inc., fail or refuse to perform its agreement of July 19, 1968, with Electric Service Co. for any reason other than reasons stated in questions No. 1 and No. 2?”

*26 “4. What compensatory damages did Electric Service Co. suffer as a direct cause of defendant Reuben Johnson and Sons, Inc., failure or refusal to perform its agreement of July 19,1968, with Electric Service Co.?”

The jury answered “None.”

The special interrogatories submitted in the action against Lakehead and Wesley Harkonen asked:

“1. Did defendant Lakehead Electric by any action or conduct on its part, through its officer defendant Wesley Harkonen, cause Reuben Johnson and Sons, Inc., to fail or refuse to perform its agreement of July 19, 1968, with Electric Service?”

The jury answered “No.” It was instructed that if its answer to that question was “No,” it was to answer no further interrogatories.

Based on the jury’s answers to the special interrogatories, the trial court ordered judgment for all defendants. These appeals followed.

Electric Service contends the defendants should have been given a total of three peremptory challenges to the jury panel, rather than six — three to Reuben Johnson, in the one case, and three to Lakehead and Harkonen, in the other. As we see it, in view of the different theories asserted by plaintiff in the two actions, this ruling was well within the discretion of the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King v. Special Resource Management, Inc.
846 P.2d 1038 (Montana Supreme Court, 1993)
Hunt v. Regents of the University of Minnesota
460 N.W.2d 28 (Supreme Court of Minnesota, 1990)
Hunt v. Regents of University
446 N.W.2d 400 (Court of Appeals of Minnesota, 1989)
Bahl v. Country Club Market, Inc.
410 N.W.2d 916 (Court of Appeals of Minnesota, 1987)
United Wild Rice, Inc. v. Nelson
313 N.W.2d 628 (Supreme Court of Minnesota, 1982)
Strickland v. Roosevelt County Rural Electric Cooperative
612 P.2d 689 (New Mexico Court of Appeals, 1980)
Cornfeldt v. Tongen
262 N.W.2d 684 (Supreme Court of Minnesota, 1977)
Suburban Paving Co. v. Bo-Man Associates, Inc.
195 N.W.2d 816 (Supreme Court of Minnesota, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
189 N.W.2d 489, 291 Minn. 22, 1971 Minn. LEXIS 988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electric-serv-co-of-duluth-v-lakehead-elec-co-minn-1971.