Elder Construction & Associates, Inc. v. Georgetown-Scott County Airport Board

Court of Appeals of Kentucky·Decided March 7, 2025·No. 2023-CA-0997·Unpublished

Opinion

RENDERED: MARCH 7, 2025; 10:00 A.M.

NOT TO BE PUBLISHED

Commonwealth of Kentucky

Court of Appeals

NO. 2023-CA-0997-MR

ELDER CONSTRUCTION & ASSOCIATES, INC. AND DAVID S. ELDER APPELLANTS

APPEAL FROM SCOTT CIRCUIT COURT v. HONORABLE JEREMY MICHAEL MATTOX, JUDGE ACTION NO. 10-CI-00703

GEORGETOWN-SCOTT COUNTY AIRPORT BOARD; ELMER J. GEORGE; AND QUALITY AUTO GLASS, INC. APPELLEES

OPINION

AFFIRMING

** ** ** ** **

BEFORE: THOMPSON, CHIEF JUDGE; ACREE AND L. JONES, JUDGES. ACREE, JUDGE: Appellants, Elder Construction and David Elder, appeal the Scott Circuit Court’s findings of fact, conclusions of law, and order assigning joint and several liability to Appellants resulting from Appellants’ non-payment of amounts owed to a subcontractor, Appellee Quality Auto Glass, Inc. (Quality), for

work Quality performed pursuant to Elder Construction’s contract with Appellee Georgetown-Scott County Airport Board (Airport). We detect no error and affirm.

Elder Construction and Airport entered a contract for construction work to improve the airport. Thereafter, Elder Construction and Quality entered a subcontract whereby Quality would provide materials and labor for certain improvements to the airport’s terminal building. Quality completed its work under the subcontract on March 4, 2010. Per the subcontract, Elder Construction owed Quality $81,478.00.

Elder Construction had not paid Quality, despite representations to Airport that all subcontractors had been paid. This included a sworn statement made to Airport by Elder Construction president David Elder that payment to all subcontractors had been completed. Quality filed a Statement of Lien with the Scott County Clerk. Quality served both Elder Construction and Airport with notice of the lien.

On July 22, 2010, Quality filed the lawsuit underlying this appeal against Elder Construction, David Elder, and Airport. Quality alleged, among other claims, breach of contract, wrongful payment, unjust enrichment, fraud, and violation of the Kentucky Fairness in Construction Act, KRS1 371.400 et seq.

1 Kentucky Revised Statutes.

Alongside its answer, Airport filed a crossclaim against Elder Construction and David Elder on the basis of the false statements made to Airport.

Protracted litigation ensued. Arbitration was ordered; an arbitration award for Quality was entered and confirmed, but later set aside. In 2017, Quality reached a settlement agreement with Airport in the amount of $140,000.

The parties agreed to a bench trial, which the circuit court conducted on October 25, 2021. Per a request by counsel for Airport, the bench trial was transcribed. Accompanying a notice of filing by Airport, the transcript was entered into the trial court record on November 18, 2021.

The circuit court entered its findings of fact, conclusions of law, and order on December 28, 2022. Therein, the circuit court pierced the corporate veil against Elder Construction and determined David Elder could be held personally liable. The circuit court entered judgment against Appellants for breach of their subcontract with Quality and their contract with Airport. For the amount unpaid under the subcontract, the circuit court awarded Quality $19,686.88 against Appellants; it calculated this amount by adding the subcontract price of $81,478.00 with $78,218.88 in interest – determined using the Kentucky Fairness in Construction Act’s twelve percent per annum interest applied to the unpaid amount – and subtracting the $140,000 Quality-Airport settlement. Because Quality’s settlement with Airport represented money Appellants failed to pay Quality, the

circuit court awarded $140,000 to Airport against Appellants with interest of twelve percent per annum.

The circuit court also determined Appellants had acted in bad faith as contemplated by the Fairness in Construction Act. It awarded Quality and Airport attorneys’ fees pursuant to KRS 371.415. Based on “the fraudulent conduct of David Elder” – specifically, that he fraudulently executed affidavits so that Airport would release funds to Elder Construction despite Quality not yet having been paid – the circuit court awarded Quality $244,434.00 in punitive damages and awarded Airport $200,000.00 in punitive damages. The circuit court also awarded Airport $80,500.00 in liquidated damages, per the liquidated damages clause in the contract between Elder Construction and Airport. Because it had pierced the veil against David Elder, the circuit court determined he was jointly and severally liable for all attorneys’ fees and damages awards.

Appellants filed a motion to alter, amend, or vacate pursuant to CR2 59.05. Therein, Appellants challenge the validity of the trial transcript filed on November 18, 2021 for the first time. They argued the circuit court improperly relied upon and cited a version of the trial transcript that was not the original. The circuit court denied the motion in an order entered June 19, 2023.

Appellants now appeal.

2 Kentucky Rules of Civil Procedure.

“In all actions tried upon the facts without a jury or with an advisory jury, the court shall find the facts specifically and state separately its conclusions of law thereon and render an appropriate judgment[.]” CR 52.01. Findings of fact may only be set aside if clearly erroneous. Id. “Clear error only occurs when there is not substantial evidence in the record to support the trial court’s findings.” Elsea v. Day, 448 S.W.3d 259, 263 (Ky. App. 2014) (citing M.P.S. v. Cabinet for Hum. Res., 979 S.W.2d 114, 116 (Ky. App. 1998)). Substantial evidence is commonly defined as “evidence of substance and relevant consequence having the fitness to induce conviction in the minds of reasonable men.” Smyzer v. B.F. Goodrich Chem. Co., 474 S.W.2d 367, 369 (Ky. 1971) (citing O’Nan v. Ecklar Moore Express, Inc., 339 S.W.2d 466 (Ky. 1960)). As for conclusions of law, appellate courts review them de novo. Hoskins v. Beatty, 343 S.W.3d 639, 641 (Ky. App. 2011).

Appellants first argue we should reverse the circuit court because it relied upon the November 18, 2021 transcript which Airport had filed. Appellants describe this document as the “unofficial transcript” in their brief.

This argument fails because Appellants first raised it in their motion to alter, amend, or vacate the circuit court’s December 28, 2022 order. “A party cannot invoke CR 59.05 to raise arguments and to introduce evidence that should have been presented during the proceedings before the entry of the judgment.”

Gullion v. Gullion, 163 S.W.3d 888, 893 (Ky. 2005) (citing Hopkins v. Ratliff, 957 S.W.2d 300 (Ky. App. 1997)). After the November 18, 2021 notice of filing of the contested transcripts, Appellants waited over a year to argue against their validity and only did so after entry of the circuit court’s December 28, 2022 order. The filing was available to all parties, and Appellants had ample time to review this filing and to contest it. Therefore, Appellants are estopped from challenging the circuit court’s reliance on transcripts which Appellants purport to be deficient.

Next, Appellants argue the circuit court’s punitive damages awards to Quality and Airport do not conform to statutory requirements. They argue that, because KRS 411.184 expressly states “[i]n no case shall punitive damages be awarded for breach of contract[,]” KRS 411.184(4), the circuit court erred in applying punitive damages while also concluding Appellants had breached their subcontract with Quality.

Free access — add to your briefcase to read the full text and ask questions with AI

Elder Construction & Associates, Inc. v. Georgetown-Scott County Airport Board, (Ky. Ct. App. 2025).

Elder Construction & Associates, Inc. v. Georgetown-Scott County Airport Board (Elder Construction & Associates, Inc. v. Georgetown-Scott County Airport Board) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bear, Inc. v. Smith
303 S.W.3d 137 (Court of Appeals of Kentucky, 2010)
Miller v. McGinity
234 S.W.3d 371 (Court of Appeals of Kentucky, 2007)
Smyzer v. BF Goodrich Chemical Company
474 S.W.2d 367 (Court of Appeals of Kentucky (pre-1976), 1971)
Gullion v. Gullion
163 S.W.3d 888 (Kentucky Supreme Court, 2005)
White v. Winchester Land Development Corp.
584 S.W.2d 56 (Court of Appeals of Kentucky, 1979)
Commonwealth v. English
993 S.W.2d 941 (Kentucky Supreme Court, 1999)
Dare to Be Great, Inc. v. Commonwealth Ex Rel. Hancock
511 S.W.2d 224 (Court of Appeals of Kentucky (pre-1976), 1974)
M.P.S. v. Cabinet for Human Resources Ex Rel. S.A.S.
979 S.W.2d 114 (Court of Appeals of Kentucky, 1998)
O'NAN v. Ecklar Moore Express, Inc.
339 S.W.2d 466 (Court of Appeals of Kentucky (pre-1976), 1960)
Hensley v. Paul Miller Ford, Inc.
508 S.W.2d 759 (Court of Appeals of Kentucky (pre-1976), 1974)
Hollingsworth v. Hollingsworth
798 S.W.2d 145 (Court of Appeals of Kentucky, 1990)
Hopkins v. Ratliff
957 S.W.2d 300 (Court of Appeals of Kentucky, 1997)
Hoskins v. Beatty
343 S.W.3d 639 (Court of Appeals of Kentucky, 2011)
Inter-Tel Technologies, Inc. v. Linn Station Properties, LLC
360 S.W.3d 152 (Kentucky Supreme Court, 2012)
Elsea v. Day
448 S.W.3d 259 (Court of Appeals of Kentucky, 2014)
Yung v. Grant Thornton, LLP
563 S.W.3d 22 (Missouri Court of Appeals, 2018)