RENDERED: MARCH 7, 2025; 10:00 A.M. NOT TO BE PUBLISHED
Commonwealth of Kentucky Court of Appeals NO. 2023-CA-0997-MR
ELDER CONSTRUCTION & ASSOCIATES, INC. AND DAVID S. ELDER APPELLANTS
APPEAL FROM SCOTT CIRCUIT COURT v. HONORABLE JEREMY MICHAEL MATTOX, JUDGE ACTION NO. 10-CI-00703
GEORGETOWN-SCOTT COUNTY AIRPORT BOARD; ELMER J. GEORGE; AND QUALITY AUTO GLASS, INC. APPELLEES
OPINION AFFIRMING
** ** ** ** **
BEFORE: THOMPSON, CHIEF JUDGE; ACREE AND L. JONES, JUDGES.
ACREE, JUDGE: Appellants, Elder Construction and David Elder, appeal the
Scott Circuit Court’s findings of fact, conclusions of law, and order assigning joint
and several liability to Appellants resulting from Appellants’ non-payment of
amounts owed to a subcontractor, Appellee Quality Auto Glass, Inc. (Quality), for work Quality performed pursuant to Elder Construction’s contract with Appellee
Georgetown-Scott County Airport Board (Airport). We detect no error and affirm.
Elder Construction and Airport entered a contract for construction
work to improve the airport. Thereafter, Elder Construction and Quality entered a
subcontract whereby Quality would provide materials and labor for certain
improvements to the airport’s terminal building. Quality completed its work under
the subcontract on March 4, 2010. Per the subcontract, Elder Construction owed
Quality $81,478.00.
Elder Construction had not paid Quality, despite representations to
Airport that all subcontractors had been paid. This included a sworn statement
made to Airport by Elder Construction president David Elder that payment to all
subcontractors had been completed. Quality filed a Statement of Lien with the
Scott County Clerk. Quality served both Elder Construction and Airport with
notice of the lien.
On July 22, 2010, Quality filed the lawsuit underlying this appeal
against Elder Construction, David Elder, and Airport. Quality alleged, among
other claims, breach of contract, wrongful payment, unjust enrichment, fraud, and
violation of the Kentucky Fairness in Construction Act, KRS1 371.400 et seq.
1 Kentucky Revised Statutes.
-2- Alongside its answer, Airport filed a crossclaim against Elder Construction and
David Elder on the basis of the false statements made to Airport.
Protracted litigation ensued. Arbitration was ordered; an arbitration
award for Quality was entered and confirmed, but later set aside. In 2017, Quality
reached a settlement agreement with Airport in the amount of $140,000.
The parties agreed to a bench trial, which the circuit court conducted
on October 25, 2021. Per a request by counsel for Airport, the bench trial was
transcribed. Accompanying a notice of filing by Airport, the transcript was entered
into the trial court record on November 18, 2021.
The circuit court entered its findings of fact, conclusions of law, and
order on December 28, 2022. Therein, the circuit court pierced the corporate veil
against Elder Construction and determined David Elder could be held personally
liable. The circuit court entered judgment against Appellants for breach of their
subcontract with Quality and their contract with Airport. For the amount unpaid
under the subcontract, the circuit court awarded Quality $19,686.88 against
Appellants; it calculated this amount by adding the subcontract price of $81,478.00
with $78,218.88 in interest – determined using the Kentucky Fairness in
Construction Act’s twelve percent per annum interest applied to the unpaid amount
– and subtracting the $140,000 Quality-Airport settlement. Because Quality’s
settlement with Airport represented money Appellants failed to pay Quality, the
-3- circuit court awarded $140,000 to Airport against Appellants with interest of
twelve percent per annum.
The circuit court also determined Appellants had acted in bad faith as
contemplated by the Fairness in Construction Act. It awarded Quality and Airport
attorneys’ fees pursuant to KRS 371.415. Based on “the fraudulent conduct of
David Elder” – specifically, that he fraudulently executed affidavits so that Airport
would release funds to Elder Construction despite Quality not yet having been paid
– the circuit court awarded Quality $244,434.00 in punitive damages and awarded
Airport $200,000.00 in punitive damages. The circuit court also awarded Airport
$80,500.00 in liquidated damages, per the liquidated damages clause in the
contract between Elder Construction and Airport. Because it had pierced the veil
against David Elder, the circuit court determined he was jointly and severally liable
for all attorneys’ fees and damages awards.
Appellants filed a motion to alter, amend, or vacate pursuant to CR2
59.05. Therein, Appellants challenge the validity of the trial transcript filed on
November 18, 2021 for the first time. They argued the circuit court improperly
relied upon and cited a version of the trial transcript that was not the original. The
circuit court denied the motion in an order entered June 19, 2023.
Appellants now appeal.
2 Kentucky Rules of Civil Procedure.
-4- “In all actions tried upon the facts without a jury or with an advisory
jury, the court shall find the facts specifically and state separately its conclusions
of law thereon and render an appropriate judgment[.]” CR 52.01. Findings of fact
may only be set aside if clearly erroneous. Id. “Clear error only occurs when there
is not substantial evidence in the record to support the trial court’s findings.” Elsea
v. Day, 448 S.W.3d 259, 263 (Ky. App. 2014) (citing M.P.S. v. Cabinet for Hum.
Res., 979 S.W.2d 114, 116 (Ky. App. 1998)). Substantial evidence is commonly
defined as “evidence of substance and relevant consequence having the fitness to
induce conviction in the minds of reasonable men.” Smyzer v. B.F. Goodrich
Chem. Co., 474 S.W.2d 367, 369 (Ky. 1971) (citing O’Nan v. Ecklar Moore
Express, Inc., 339 S.W.2d 466 (Ky. 1960)). As for conclusions of law, appellate
courts review them de novo. Hoskins v. Beatty, 343 S.W.3d 639, 641 (Ky. App.
2011).
Appellants first argue we should reverse the circuit court because it
relied upon the November 18, 2021 transcript which Airport had filed. Appellants
describe this document as the “unofficial transcript” in their brief.
This argument fails because Appellants first raised it in their motion
to alter, amend, or vacate the circuit court’s December 28, 2022 order. “A party
cannot invoke CR 59.05 to raise arguments and to introduce evidence that should
have been presented during the proceedings before the entry of the judgment.”
-5- Gullion v. Gullion, 163 S.W.3d 888, 893 (Ky. 2005) (citing Hopkins v. Ratliff, 957
S.W.2d 300 (Ky. App. 1997)). After the November 18, 2021 notice of filing of
Free access — add to your briefcase to read the full text and ask questions with AI
RENDERED: MARCH 7, 2025; 10:00 A.M. NOT TO BE PUBLISHED
Commonwealth of Kentucky Court of Appeals NO. 2023-CA-0997-MR
ELDER CONSTRUCTION & ASSOCIATES, INC. AND DAVID S. ELDER APPELLANTS
APPEAL FROM SCOTT CIRCUIT COURT v. HONORABLE JEREMY MICHAEL MATTOX, JUDGE ACTION NO. 10-CI-00703
GEORGETOWN-SCOTT COUNTY AIRPORT BOARD; ELMER J. GEORGE; AND QUALITY AUTO GLASS, INC. APPELLEES
OPINION AFFIRMING
** ** ** ** **
BEFORE: THOMPSON, CHIEF JUDGE; ACREE AND L. JONES, JUDGES.
ACREE, JUDGE: Appellants, Elder Construction and David Elder, appeal the
Scott Circuit Court’s findings of fact, conclusions of law, and order assigning joint
and several liability to Appellants resulting from Appellants’ non-payment of
amounts owed to a subcontractor, Appellee Quality Auto Glass, Inc. (Quality), for work Quality performed pursuant to Elder Construction’s contract with Appellee
Georgetown-Scott County Airport Board (Airport). We detect no error and affirm.
Elder Construction and Airport entered a contract for construction
work to improve the airport. Thereafter, Elder Construction and Quality entered a
subcontract whereby Quality would provide materials and labor for certain
improvements to the airport’s terminal building. Quality completed its work under
the subcontract on March 4, 2010. Per the subcontract, Elder Construction owed
Quality $81,478.00.
Elder Construction had not paid Quality, despite representations to
Airport that all subcontractors had been paid. This included a sworn statement
made to Airport by Elder Construction president David Elder that payment to all
subcontractors had been completed. Quality filed a Statement of Lien with the
Scott County Clerk. Quality served both Elder Construction and Airport with
notice of the lien.
On July 22, 2010, Quality filed the lawsuit underlying this appeal
against Elder Construction, David Elder, and Airport. Quality alleged, among
other claims, breach of contract, wrongful payment, unjust enrichment, fraud, and
violation of the Kentucky Fairness in Construction Act, KRS1 371.400 et seq.
1 Kentucky Revised Statutes.
-2- Alongside its answer, Airport filed a crossclaim against Elder Construction and
David Elder on the basis of the false statements made to Airport.
Protracted litigation ensued. Arbitration was ordered; an arbitration
award for Quality was entered and confirmed, but later set aside. In 2017, Quality
reached a settlement agreement with Airport in the amount of $140,000.
The parties agreed to a bench trial, which the circuit court conducted
on October 25, 2021. Per a request by counsel for Airport, the bench trial was
transcribed. Accompanying a notice of filing by Airport, the transcript was entered
into the trial court record on November 18, 2021.
The circuit court entered its findings of fact, conclusions of law, and
order on December 28, 2022. Therein, the circuit court pierced the corporate veil
against Elder Construction and determined David Elder could be held personally
liable. The circuit court entered judgment against Appellants for breach of their
subcontract with Quality and their contract with Airport. For the amount unpaid
under the subcontract, the circuit court awarded Quality $19,686.88 against
Appellants; it calculated this amount by adding the subcontract price of $81,478.00
with $78,218.88 in interest – determined using the Kentucky Fairness in
Construction Act’s twelve percent per annum interest applied to the unpaid amount
– and subtracting the $140,000 Quality-Airport settlement. Because Quality’s
settlement with Airport represented money Appellants failed to pay Quality, the
-3- circuit court awarded $140,000 to Airport against Appellants with interest of
twelve percent per annum.
The circuit court also determined Appellants had acted in bad faith as
contemplated by the Fairness in Construction Act. It awarded Quality and Airport
attorneys’ fees pursuant to KRS 371.415. Based on “the fraudulent conduct of
David Elder” – specifically, that he fraudulently executed affidavits so that Airport
would release funds to Elder Construction despite Quality not yet having been paid
– the circuit court awarded Quality $244,434.00 in punitive damages and awarded
Airport $200,000.00 in punitive damages. The circuit court also awarded Airport
$80,500.00 in liquidated damages, per the liquidated damages clause in the
contract between Elder Construction and Airport. Because it had pierced the veil
against David Elder, the circuit court determined he was jointly and severally liable
for all attorneys’ fees and damages awards.
Appellants filed a motion to alter, amend, or vacate pursuant to CR2
59.05. Therein, Appellants challenge the validity of the trial transcript filed on
November 18, 2021 for the first time. They argued the circuit court improperly
relied upon and cited a version of the trial transcript that was not the original. The
circuit court denied the motion in an order entered June 19, 2023.
Appellants now appeal.
2 Kentucky Rules of Civil Procedure.
-4- “In all actions tried upon the facts without a jury or with an advisory
jury, the court shall find the facts specifically and state separately its conclusions
of law thereon and render an appropriate judgment[.]” CR 52.01. Findings of fact
may only be set aside if clearly erroneous. Id. “Clear error only occurs when there
is not substantial evidence in the record to support the trial court’s findings.” Elsea
v. Day, 448 S.W.3d 259, 263 (Ky. App. 2014) (citing M.P.S. v. Cabinet for Hum.
Res., 979 S.W.2d 114, 116 (Ky. App. 1998)). Substantial evidence is commonly
defined as “evidence of substance and relevant consequence having the fitness to
induce conviction in the minds of reasonable men.” Smyzer v. B.F. Goodrich
Chem. Co., 474 S.W.2d 367, 369 (Ky. 1971) (citing O’Nan v. Ecklar Moore
Express, Inc., 339 S.W.2d 466 (Ky. 1960)). As for conclusions of law, appellate
courts review them de novo. Hoskins v. Beatty, 343 S.W.3d 639, 641 (Ky. App.
2011).
Appellants first argue we should reverse the circuit court because it
relied upon the November 18, 2021 transcript which Airport had filed. Appellants
describe this document as the “unofficial transcript” in their brief.
This argument fails because Appellants first raised it in their motion
to alter, amend, or vacate the circuit court’s December 28, 2022 order. “A party
cannot invoke CR 59.05 to raise arguments and to introduce evidence that should
have been presented during the proceedings before the entry of the judgment.”
-5- Gullion v. Gullion, 163 S.W.3d 888, 893 (Ky. 2005) (citing Hopkins v. Ratliff, 957
S.W.2d 300 (Ky. App. 1997)). After the November 18, 2021 notice of filing of
the contested transcripts, Appellants waited over a year to argue against their
validity and only did so after entry of the circuit court’s December 28, 2022 order.
The filing was available to all parties, and Appellants had ample time to review
this filing and to contest it. Therefore, Appellants are estopped from challenging
the circuit court’s reliance on transcripts which Appellants purport to be deficient.
Next, Appellants argue the circuit court’s punitive damages awards to
Quality and Airport do not conform to statutory requirements. They argue that,
because KRS 411.184 expressly states “[i]n no case shall punitive damages be
awarded for breach of contract[,]” KRS 411.184(4), the circuit court erred in
applying punitive damages while also concluding Appellants had breached their
subcontract with Quality.
“As often noted, punitive damages exist to punish and discourage
certain types of bad behavior.” Yung v. Grant Thornton, LLP, 563 S.W.3d 22, 64
(Ky. 2018) (citing KRS 411.184 and Hensley v. Paul Miller Ford, Inc., 508
S.W.2d 759, 762 (Ky. 1974)). KRS 411.184(2) provides for punitive damages “if
a plaintiff proves by clear and convincing evidence that a defendant acted with
fraud, oppression, or malice.” Yung, 563 S.W.3d at 65. Here, the circuit court
explicitly noted the availability of punitive damages for a defendant’s acts of fraud
-6- notwithstanding KRS 411.184(4)’s prohibition against punitive damages for
breaches of contract. As is obvious and contrary to Appellants’ argument, the
circuit court applied punitive damages as a result of fraudulent conduct
independent of its conclusion that the subcontract had been breached.
Third, Appellants assert the circuit court did not support its damages
awards with sufficient findings of fact and conclusions of law as CR 52.01 requires
and that the circuit court record does not support the awards. We will discuss both
the circuit court’s award of punitive damages and liquidated damages.
As to the punitive damages award, the circuit court expressly found
that David Elder submitted a false affidavit to Airport that Elder Construction had
paid all outstanding debts underlying its contract with Airport. The circuit court
found that David Elder acknowledged he signed the affidavit himself. Testimony
of record, noted by the circuit court, confirms David Elder had billed Airport for
the work Quality performed, despite knowing Quality had not yet been paid. In
our view, substantial evidence supports the circuit court’s conclusion that
Appellants engaged in fraud; therefore, substantial evidence also supports its award
of punitive damages.
The circuit court also made specific findings of fact and conclusions
of law supporting its other damages awards. The circuit court awarded statutory
damages to Quality for Appellants’ failure to pay Quality under the subcontract.
-7- The Kentucky Fairness in Construction Act requires contractors to pay
subcontractors undisputed amounts due within fifteen business days of receipt of
payment from the contracting entity. KRS 371.405(8). Should the contractor fail
to do so, “the contractor shall pay interest to the subcontractor beginning on the
sixteenth business day after receipt of payment by the contractor, computed at the
rate of twelve percent (12%) per annum on the unpaid amount.” KRS 371.405(9).
As the record and the circuit court’s findings make clear, Appellants
received payment from Airport for work Quality performed as a subcontractor and
that Appellants still have not paid Quality for this work. The circuit court
calculated the amount due under the subcontract to Quality upon application of the
Fairness in Construction Act’s twelve percent interest rate, less the amount Quality
received after its settlement with Airport. We detect no errors of fact or law in the
circuit court’s conclusions in this regard.
Nor do we detect error in the circuit court’s award of liquidated
damages to Airport. A liquidated damages clause appeared in the contract between
Elder Construction and Airport. The contract required substantial completion of
the contract within 365 days. Construction began January 6, 2009, and was not
substantially completed until June 16, 2010. Therefore, substantial completion was
achieved 161 days late, as the circuit court found. This timeframe is supported by
substantial evidence of record; a January 6, 2009 letter states that Elder
-8- Construction was to immediately commence the project, and Elder Construction’s
June 1, 2010 application for a certificate of occupancy indicated Airport could
occupy the premises on June 16, 2010. Here, too, we detect no reversible error by
the circuit court.
Appellants argue the circuit court’s attorneys’ fee awards to Quality
and Airport were in error because the circuit court made no finding as to the
reasonableness of the fee awards. The Fairness in Construction Act authorizes
attorneys’ fees in certain circumstances. “In any action to enforce KRS 371.400 to
371.425, including arbitration, the court or arbitrator shall award costs and
reasonable attorney’s fees to the prevailing party if the losing party is deemed to
have acted in bad faith.” KRS 371.415. Though Appellants do not contest the bad
faith requirement, the circuit court determined Appellants’ actions, i.e., collecting
payment from Airport after falsely attesting it had paid Quality, constituted bad
faith.
By analogy to statutorily-authorized attorneys’ fee awards in divorce
proceedings, KRS 403.220 empowers family courts with the discretion to award
attorneys’ fees to a party after “considering the financial resources of both
parties[.]” KRS 403.220. A panel of this Court has determined that, though the
statute includes consideration of the parties’ financial resources as a requirement,
“[n]owhere does it state a trial court must make specific findings on the parties’
-9- financial resources.” Hollingsworth v. Hollingsworth, 798 S.W.2d 145, 148 (Ky.
App. 1990). Because the record in Hollingsworth was “replete with circumstances
in which the trial court was made aware of each party’s financial situation[,]” this
Court determined that the trial court’s award of attorneys’ fees met the statutory
requirements, appeared reasonable, and would not be disturbed. Id.
Nowhere does KRS 371.415 require a trial court to make specific
findings as to the reasonableness of an attorneys’ fee award. All that the statute
requires as a prerequisite to an attorneys’ fee award is that the trial court deem the
losing party to have acted in bad faith and that the attorneys’ fees be reasonable.
See KRS 371.415. Appellants plainly acted in bad faith by falsely informing
Airport that all subcontractors had been paid. As to reasonableness of the awards,
the duration of the underlying lawsuit and invoices and affidavits supporting
expenses incurred by Appellees’ counsel demonstrate their reasonableness.
Because attorneys’ fee awards are reviewed for an abuse of discretion, Miller v.
McGinty, 234 S.W.3d 371, 373 (Ky. App. 2007), and because an abuse of
discretion is found only where a trial court’s ruling is arbitrary, unreasonable,
unfair, or unsupported by sound legal principles, Commonwealth v. English, 993
S.W.2d 941, 945 (Ky. 1999), we cannot say the circuit court in the instant case
abused its discretion. Nothing about the circuit court’s attorneys’ fee awards
-10- indicates the awards were arbitrary, unreasonable, unfair, or unsupported by legal
principles.
Finally, Appellants contend the circuit court erred by piercing the
corporate veil and assigning joint and several liability to David Elder. Appellants’
argument is without merit.
While the law generally regards corporations to be legal entities
distinct from their shareholders, “when the corporation is used to justify wrong,
protect fraud or defend crime, the law regards the corporation as an association of
persons.” Bear, Inc. v. Smith, 303 S.W.3d 137, 147 (Ky. App. 2010) (citing Dare
To Be Great, Inc. v. Commonwealth, ex rel. Hancock, 511 S.W.2d 224, 227 (Ky.
1974)). In the instant case, the circuit court relied upon the “instrumentality
theory” for piercing the corporate veil; “[a] Kentucky trial court may proceed
under the traditional alter ego formulation or the instrumentality theory because the
tests are essentially interchangeable.” Inter-Tel Techs., Inc. v. Linn Station Props.,
LLC, 360 S.W.3d 152, 165 (Ky. 2012). Under the instrumentality theory, a
plaintiff must establish three elements before the corporate veil may be pierced:
“(1) that the corporation was a mere instrumentality of the shareholder; (2) that the
shareholder exercised control over the corporation in such a way as to defraud or to
harm the plaintiff; and (3) that a refusal to disregard the corporate entity would
subject the plaintiff to unjust loss.” Bear, Inc., 303 S.W.3d at 148 (citing White v.
-11- Winchester Land Dev. Corp., 584 S.W.2d 56, 61 (Ky. App. 1979), overruled on
other grounds by Inter-Tel Techs., Inc., 360 S.W.3d 152)).
We cannot conclude the circuit court erred in piercing the corporate
veil and assigning liability to David Elder. As the circuit court noted, David Elder
was the president, sole shareholder, sole officer, and sole director of Elder
Construction, and David Elder entered contracts on Elder Construction’s behalf.
Therefore, the first prong is satisfied. The previously discussed actions of David
Elder in falsely representing to Airport in a notarized and sworn affidavit that Elder
Construction had paid all amounts due to Quality – and Airport’s payment to Elder
Construction as a result – satisfy the second prong. Finally, the circuit court
determined the third prong is satisfied because Elder Construction was dissolved
after this lawsuit was filed, so assigning liability to Elder Construction only would
result in undue loss to Quality. Therefore, upon review of the record, sufficient
evidence exists to support the circuit court’s piercing of the corporate veil.
Based on the foregoing, we affirm the judgment of the Scott Circuit
Court.
ALL CONCUR.
-12- BRIEFS FOR APPELLANTS: BRIEF FOR APPELLEE GEORGETOWN-SCOTT COUNTY Harry B. O’Donnell IV AIRPORT BOARD: Louisville, Kentucky Elmer J. George Lebanon, Kentucky
BRIEF FOR APPELLEE QUALITY AUTO GLASS, INC.:
S. Thomas Hamilton Bardstown, Kentucky
-13-