Elastic Stop Nut Corp. v. United States

113 F. Supp. 446, 126 Ct. Cl. 100, 1953 U.S. Ct. Cl. LEXIS 32
CourtUnited States Court of Claims
DecidedJuly 13, 1953
DocketNo. 48986
StatusPublished
Cited by4 cases

This text of 113 F. Supp. 446 (Elastic Stop Nut Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elastic Stop Nut Corp. v. United States, 113 F. Supp. 446, 126 Ct. Cl. 100, 1953 U.S. Ct. Cl. LEXIS 32 (cc 1953).

Opinion

MaddeN, Judge,

delivered the opinion of the court:

The plaintiff sues for $166,911.33 which, it claims, is the amount which it expended above the amount which it was paid for the manufacture, for the Government, of shell fuzes. By order of the court, the instant phase of .the suit is limited to the question of liability, leaving, to further proceedings the amount which the plaintiff may recover, if the Government is liable.

The plaintiff corporation’s principal place of business is at Union, New Jersey. Its principal business is the manufacture of a self-locking nut,.known as the “elastic stop nut.” It has a factory at Union, and another one at Lincoln, Nebraska. Until the middle of 1944 its factories and facilities were engaged in the manufacture of these nuts, principally for airplane manufacturers and for the Army and the Navy. In the summer of 1944 orders for the elastic stop nuts decreased and the plaintiff sought contracts with the Government for the manufacture of other things. It was given a contract, No. 1932, for the manufacture of 1,011,000 shell fuzes, at the unit price of $1.58 each, to be manufactured at its New Jersey plant, under the supervision of the Army’s New York Ordnance District. At the same time it was given another contract, No. 828, for the same number of fuzes at the same price at its Lincoln, Nebraska, plant. The instant claim arises out of Contract No. .1932.

Article. 33 of the contract, which is set out verbatim in the findings, stated that the parties recognized that the unit price of $1.58 set in the contract might turn out, upon experience, to be too high or too low,' and that they therefore agreed to [103]*103revise the price in the light of actual experience in the manufacture of the first 40% of the total number of fuzes, which they called the “trial run.” The contractor was to keep a careful record of its costs and furnish to the Government within 30 days after the completion of the trial run its data and its proposal for a revised price. The parties were, thereupon, to negotiate in good faith and attempt to .reach an agreement upon a revised price. If they could not agree, either party might then terminate the contract, and in that case the provisions of Article 12, “Termination at the Option of the Government” were to apply, except that the contractor was to be allowed no profit on the uncompleted portion of the contract. Article 12 provided, in substance, that the contractor should, upon termination, be reimbursed for its costs.

: After the execution of Contract No. 1932, the plaintiff acquired the necessary machinery and tools for its performance, and began the manufacture of fuzes at its New Jersey plant and did the same, under Contract No. 828 at its Nebraska plant. By December 1944, it had learned that it could manufacture the fuzes more efficiently and at lower cost at its Nebraska plant. Besides, the demand for elastic stop nuts had revived, and practically all of these were being made at the New Jersey plant. The plaintiff after discussions with representatives of the Ordnance Department, made a written request on January 1,1945, for permission to manufacture the fuzes under Contract No. 1932 at its Nebraska plant. The request was granted. The plaintiff was notified on January 11 that Contract No. 1932 had been transferred for administration from the New York to the St. Louis Ordnance District. The St. Louis District was directed to administer the contract from the date of transfer “including any price redetermination under Article 33 * * The plaintiff had already, pursuant to the preliminary discussions, shipped machinery from New Jersey to Nebraska.

Before the contract was transferred, a number of change orders concerning Contract No. 1932 had been issued but the amounts due the plaintiff under them and other details had not been worked out. The St. Louis District said that it [104]*104would be confusing to administer these matters from the St. Louis office, when the data concerning them were in the New York District. The St. Louis District suggested that Contract No. 1982 be returned to the New York District, and be there terminated at a quantity of fuzes which would use up the parts in process, and that a new contract be made by the St. Louis District for the production of the uncompleted balance of the fuzes, they to be manufactured at the Nebraska plant. A meeting of the parties took place in Washington, D. C., and the problem was discussed. The plaintiff’s representative at the meeting inquired whether the plaintiff would lose its rights under Contract No. 1932 if the suggested procedure was followed. It was agreed by all present that the rights and obligations of the parties would be the same as they would have been if the transfer of Contract No. -1932 to St. Louis had not been rescinded. The plaintiff thereupon agreed to the suggested procedure.

' After negotiations with the plaintiff, the St. Louis Ordnance District issued a “letter order” designated as Contract No. 1523, dated January 31, 1945, for 2,429,000 fuzes, subsequently reduced to 1,001,600 fuzes, at prices to be sube-quently agreed on. At the same time a change order was issued accelerating the production of the fuzes then being manufactured at the Nebraska plant under Contract No. 828.

On February 21, 1945, the plaintiff wrote the New York Ordnance District as follows:

* * * we are willing to accept cancellation of Contract No. * * * 1932 contingent upon February production and delivered and accepted fuzes. The remaining undelivered quantity upon which we accept cancellation is 931,000 pieces.
This cancellation will be accepted without termination charge with the complete understanding that all other provisions as outline in Contract No. * * * 1932 remain in full effect.

On February 22, the New York Ordnance District sent to the plaintiff a notice of the partial termination, for the convenience of the Government, of Contract No. 1932, which said that the contract was terminated as to all but 80,000 fuzes, and was further terminated as to any of the 80,000 [105]*105fuzes .not completed on February 28. The notice contained a paragraph 6 (b)- which said:

❖ * ❖ . ❖ # •
(b) If you wish to waive any termination claim against the Government, please sign and return all three . copies of the inclosed “No-Cost” Prime Contract Settle- . ment Agreement. One copy signed by the Contracting Officer will be returned for your files.

The notice of termination was accompanied by a form of document entitled “Acknowledgment of Notice and Intent To File or Not To File a Claim”, and by a draft of a proposed “Supplemental Agreement No. 5 to Contract * * * 1932.” The draft said, inter alia:

. % ❖ * ❖ *
.WhbReas, the Contractor is willing to waive unconditionally any claim against the Government by reason of such termination; and
Whereas, such unconditional waiver by the Contractor will expedite settlement of the Contract and will ■otherwise promote the objectives of the Contract Settlement Act of 1944.
Now, therefore, the parties hereto agree a,s follows:
Article 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Langoma Industries, Inc. v. United States
135 F. Supp. 282 (Court of Claims, 1955)
United States v. Lennox Metal Manufacturing Co.
225 F.2d 302 (Second Circuit, 1955)
Elastic Stop Nut Corp. of America v. United States
132 F. Supp. 466 (Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
113 F. Supp. 446, 126 Ct. Cl. 100, 1953 U.S. Ct. Cl. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elastic-stop-nut-corp-v-united-states-cc-1953.